| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/07/2024 | Permit Issued | ARIANA CONTRACTING INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/08/2024 | Complete | MEGA ELEC'L CONTR'G, INC | General Wiring |
| 06/06/2022 | Permit Issued | ALL WAYS ELECTRIC CORP.W | — |
| 12/13/2018 | Complete | POWER ON ELECTRIC CORP | General Wiring |
| Firm | Filings | Most Recent |
|---|---|---|
| VALENTINO POMPEO ARCHITECT, P.C. | 6 | 03/07/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EJP CONTRACTING CORP | General Contractor | 3 | 07/08/2026 |
| MEGA ELEC'L CONTR'G, INC | Electrical | 1 | 03/22/2026 |
| ARIANA CONTRACTING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| VALENTINO POMPEO ARCHITEC | 1013 | 2 | 02/06/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | EJP CONTRACTING CORP | 09/11/2023 |
| DOB NOW | Plumbing | Permit Issued | ARIANA CONTRACTING INC | 05/23/2023 |
| DOB NOW | General Construction | Signed-off | EJP CONTRACTING CORP | 05/19/2023 |
| DOB NOW | General Construction | Signed-off | EJP CONTRACTING CORP | 02/07/2023 |
| BIS | PL | ISSUED | GAROFALO MASTER P&H CORP | 09/05/2003 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/16/2024 | Insulation placement and R values | VALENTINO POMPEO | energy_progress |
| 02/16/2024 | Fire-Resistant Penetrations and Joints | VALENTINO POMPEO | special |
| 02/16/2024 | Fire-Resistance Rated Construction | VALENTINO POMPEO | progress |
| 02/16/2024 | Energy Code Compliance Inspections | VALENTINO POMPEO | progress |
| 02/16/2024 | Fenestration and door U-factor and product ratings | VALENTINO POMPEO | energy_progress |
| 02/16/2024 | Lighting in dwelling units | VALENTINO POMPEO | energy_progress |
| 02/16/2024 | Fenestration air leakage | VALENTINO POMPEO | energy_progress |
| 02/16/2024 | Air barrier - visual inspection | VALENTINO POMPEO | energy_progress |
| 02/16/2024 | Fenestration areas | VALENTINO POMPEO | energy_progress |
| 02/05/2024 | Fire-Resistant Penetrations and Joints | VALENTINO POMPEO | special |
| 02/05/2024 | Energy Code Compliance Inspections | VALENTINO POMPEO | progress |
| 02/05/2024 | Fire-Resistance Rated Construction | VALENTINO POMPEO | progress |
| 02/05/2024 | Fenestration and door U-factor and product ratings | VALENTINO POMPEO | energy_progress |
| 02/05/2024 | Fenestration areas | VALENTINO POMPEO | energy_progress |
| 02/05/2024 | Fenestration air leakage | VALENTINO POMPEO | energy_progress |
| 02/05/2024 | Insulation placement and R values | VALENTINO POMPEO | energy_progress |
| 02/05/2024 | Lighting in dwelling units | VALENTINO POMPEO | energy_progress |
| 02/05/2024 | Air barrier - visual inspection | VALENTINO POMPEO | energy_progress |