| Owner | Filings | Most Recent |
|---|---|---|
| PRIMROSE SERVICE | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/18/2024 | $1.1M | — | Private party → Private party | $580/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MEI ARCHITECT PLLC | 2 | 11/24/2025 |
| SYNERGIC DESIGN ARCHITECTS | 1 | 11/13/2025 |
| MEHDI GHAZI, P.E., P.C. | 5 | 10/29/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| ALPHA HOME DESIGN LLC | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PRIMROSE SERVICE INC | General Contractor | 9 | 04/09/2026 |
| ACCORD POWER INC | General Contractor | 2 | 03/21/2026 |
| DYNAMIC PLBNG & SPRKR COR | Fire Protection | 1 | 07/08/2026 |
| WASOFF PLBG & UTILITY CO | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MEHDI GHAZI, P.E. P.C. | 7129 | 5 | 11/24/2025 |
| SYNERGIC DESIGN LLC | 8561 | 1 | 11/13/2025 |
| TRIANGLE INSPECTION & TES | 7495 | 2 | 08/22/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | PRIMROSE SERVICE INC | 12/12/2025 |
| DOB NOW | Solar | Signed-off | ACCORD POWER INC | 11/17/2025 |
| DOB NOW | Earth Work | Signed-off | PRIMROSE SERVICE INC | 04/28/2025 |
| DOB NOW | Structural | Signed-off | PRIMROSE SERVICE INC | 04/28/2025 |
| DOB NOW | Sprinklers | Signed-off | CITYWIDE PLBG, HTG &SPRKL | 04/25/2025 |
| DOB NOW | Sprinklers | Signed-off | WASOFF PLBG & UTILITY CO | 04/24/2025 |
| DOB NOW | Mechanical Systems | Signed-off | PRIMROSE SERVICE INC | 04/23/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | PRIMROSE SERVICE INC | 04/23/2025 |
| DOB NOW | Construction Fence | Signed-off | PRIMROSE SERVICE INC | 04/21/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/24/2025 | Signed-off | PRIMROSE SERVICE INC | Heating and Air Conditioning Systems | Heat / Cool Goodman GSZH504810 48,000 BTU · Heat Pump Outdoor ×3 Cooper & Hunter CH-N48LCU-230VO 48,000 BTU · Heat Pump Outdoor ×3 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/24/2025 | Signed-off | WASOFF PLBG & UTILITY CO | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/17/2025 | Complete | ACCORD POWER ELECTRIC LLC | — |
| 05/23/2025 | Complete | KJK ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/24/2025 | Signed-off | PRIMROSE SERVICE INC | 1 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/27/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 01/21/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 01/06/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/05/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/03/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/28/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/09/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/25/2025 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | Rajasekhar Sakhamuri | special |
| 08/25/2025 | Fire-Resistant Penetrations and Joints | MEHDI GHAZI | special |
| 08/25/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | MEHDI GHAZI | special |
| 08/25/2025 | Sprinkler Systems | MEHDI GHAZI | special |
| 08/25/2025 | Energy Code Compliance Inspections | MEHDI GHAZI | progress |
| 08/25/2025 | HVAC-R and service water heating system controls | MEHDI GHAZI | energy_progress |
| 08/25/2025 | HVAC-R and service water piping design and insulation | MEHDI GHAZI | energy_progress |
| 08/25/2025 | HVAC-R and service water heating equipment | MEHDI GHAZI | energy_progress |
| 08/22/2025 | HVAC-R and service water heating equipment | MEHDI GHAZI | energy_progress |
| 08/22/2025 | Fire-Resistant Penetrations and Joints | MEHDI GHAZI | special |
| 08/22/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | MEHDI GHAZI | special |
| 08/22/2025 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | Rajasekhar Sakhamuri | special |
| 08/22/2025 | Sprinkler Systems | MEHDI GHAZI | special |
| 08/22/2025 | Energy Code Compliance Inspections | MEHDI GHAZI | progress |
| 08/22/2025 | HVAC-R and service water piping design and insulation | MEHDI GHAZI | energy_progress |
| 08/22/2025 | HVAC-R and service water heating system controls | MEHDI GHAZI | energy_progress |
| 04/14/2025 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 04/14/2025 | Energy Code Compliance Inspections | MEHDI GHAZI | progress |
| 04/14/2025 | Structural Wood Frame | MEHDI GHAZI | progress |
| 04/14/2025 | Structural Steel - High Strength Bolting | MEHDI GHAZI | special |
| 04/14/2025 | Structural Steel - Welding | MEHDI GHAZI | special |
| 04/14/2025 | Subgrade Inspections | MEHDI GHAZI | special |
| 04/14/2025 | Insulation placement and R values | MEHDI GHAZI | energy_progress |
| 04/14/2025 | Fenestration areas | MEHDI GHAZI | energy_progress |
| 04/14/2025 | Fenestration air leakage | MEHDI GHAZI | energy_progress |