| Owner | Filings | Most Recent |
|---|---|---|
| WOW ENTERPRISES, LLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| IVAN SHCHERBAKOV | 1 | 08/18/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| BIS | PL | ISSUED | NAT'L MECH. SVCS PLBG LLC | 10/15/1997 |
| BIS | BL | ISSUED | STUART ISER INC. | 10/15/1997 |
| BIS | FP | ISSUED | IDEAL FIRE CONTROL | 04/07/1995 |
| BIS | PL | ISSUED | CHINATOWN PLBG & HTG INC | 02/14/1995 |
| BIS | OT | ISSUED | KEYSTONE CONSTRUCTION MANAGEMENT | 09/02/1994 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2026 | Complete | KWONG MING ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | — | — | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | — | — | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/14/2026 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | — | special |
| 08/14/2026 | Exterior Insulation and Finish Systems (EIFS) | — | special |
| 08/14/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 08/14/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 08/14/2026 | Energy Code Compliance Inspections | — | progress |
| 08/14/2026 | Fire-Resistance Rated Construction | — | progress |
| 08/14/2026 | Air barrier - visual inspection | — | energy_progress |
| 08/14/2026 | Air barrier — testing | — | energy_progress |
| 08/14/2026 | Interior lighting power | — | energy_progress |
| 08/14/2026 | Maintenance information | — | energy_progress |
| 08/14/2026 | Fenestration air leakage | — | energy_progress |
| 08/14/2026 | Exterior lighting power | — | energy_progress |
| 08/14/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 08/14/2026 | Metering | — | energy_progress |
| 08/14/2026 | Lighting controls | — | energy_progress |
| 08/14/2026 | Fenestration areas | — | energy_progress |
| 08/14/2026 | Insulation placement and R values | — | energy_progress |