← Back
Two stories - detached, small or mid-size
42-09 222 STREET
QUEENS · BIN 4138727
💬 Discuss this project
1930Year Built
2.5Stories
A1Building Class
R2AZoning
1,496 sfGross Floor Area
1Units
2 Open Violations 0 unresolved · 2 paperwork only ▸FDNY Report ↗
Two stories - detached, small or mid-size · 4,000 sf lot · 0.37 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
H G LEE ARCHITECT PC205/16/2025
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HG LEE ARCHITECT PC2554205/16/2025
Building Lifecycle
All (13)Filed (2)Violation (2)Objection (6)Special Inspection (3)
06/16/2025
Objection resolved — Addressed
06/16/2025
Objection resolved — Addressed
06/16/2025
Objection resolved — Addressed
06/10/2025
Objection raised — Admin
06/10/2025
Objection raised — Plumbing
06/10/2025
Objection raised — Cost
05/16/2025
Filed — Alteration
REMOVE ECB VIOLATIONS.#39124954Z,#39124953R 1)REMOVE INTERIOR PARTITION WALLS ON CELLAR FLOOR. 2)LEGALIZE BATHROOM WALLS. NO CHANGE IN USE, EGRESS, OCCUPANCY AND BULK.
Q01217055-I1
05/16/2025
Filed — Alteration
PLUMBING WORKS ONLY" CELLAR FLOOR 1.LEGALIZE 3-PIC. BATH 1-SHOWER, 1-SINK, 1-W.C, 1-MOP SINK, & 1 WASHER NO CHANGE IN USE, EGRESS AND OCCUPANCY.
Q01217239-I1
04/30/2025
Special inspection requirement — Fire-Resistance Rated Construction
He Gin Lee
04/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
He Gin Lee
04/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
He Gin Lee
09/16/2024
Violation issued (ECB, open)
Construction
09/16/2024
Violation issued (ECB, open)
Construction
Nothing on file for this building.
1 project · most recent 05/16/2025
Water/Sanitary
FiledStatusContractorScope
05/16/2025——Water/Sanitary
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
04/30/2025Fire-Resistance Rated ConstructionHe Gin Leeprogress
04/28/2025Fire-Resistant Penetrations and JointsHe Gin Leespecial
04/28/2025Fire-Resistant Penetrations and JointsHe Gin Leespecial
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026Q01217055-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWRestrictive Declaration/Easement 12
08/13/2026Q01217055-I1Open ↗
08/13/2026Q01217239-I1Open ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/20/2026Q01217055-I1Open ↗
08/13/2026Q01217239-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026Q01217239-I1Open ↗
08/27/2026Q01217055-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/27/2026Q01217055-I1Open ↗