← Back
One family attached or semi-detached
144-19 71 AVENUE
QUEENS · BIN 4144006
💬 Discuss this project
1940Year Built
2Stories
A5Building Class
R4Zoning
2,159 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
One family attached or semi-detached · 2,667 sf lot · 0.81 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbing
Floor 21p · 1 filing · 20 docs
Floor 11p · 1 filing · 20 docs
Cellar2p · 1 filing · 20 docs
1 job · most recent 02/10/2025
Water/Sanitary
FiledStatusContractorScope
02/10/2025Signed-offJMW PLUMBING, INCWater/Sanitary
1 job · most recent 04/24/2024
General Wiring
FiledStatusContractorScope
04/24/2024CompleteAMOR ELECTRIC CORPGeneral Wiring
1 job · most recent 02/10/2025
FiledStatusContractorScope
02/10/2025Signed-offJMW PLUMBING, INC5 scope_items
Building Lifecycle
All (72)Filed (8)Permit Issued (6)Signed Off (3)Violation (2)Inspection (9)Objection (14)Special Inspection (30)
02/12/2025
Special inspection requirement — Concrete - Cast-In-Place
Shmuel Flaum
02/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shmuel Flaum
02/12/2025
Special inspection requirement — Preliminary
Shmuel Flaum
02/12/2025
Special inspection requirement — Final
NAVEEN KUMAR
02/12/2025
Special inspection requirement — Footing and Foundation
Shmuel Flaum
02/12/2025
Special inspection requirement — Fire-Resistance Rated Construction
Shmuel Flaum
02/12/2025
Special inspection requirement — Energy Code Compliance Inspections
Shmuel Flaum
02/12/2025
Special inspection requirement — Electric vehicle service equipment requirements
Shmuel Flaum
02/12/2025
Special inspection requirement — Interior lighting power
Shmuel Flaum
02/10/2025
Filed — Alteration CO
PLUMBING WORK AS PER PLAN
Q08003087-P4
12/06/2024
Filed — Alteration CO
PLUMBING WORK AS PER PLAN
Q08003087-P3
12/04/2024
Special inspection requirement — Concrete - Cast-In-Place
Shmuel Flaum
12/04/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shmuel Flaum
12/04/2024
Special inspection requirement — Energy Code Compliance Inspections
Shmuel Flaum
12/04/2024
Special inspection requirement — Final
NAVEEN KUMAR
12/04/2024
Special inspection requirement — Fire-Resistance Rated Construction
Shmuel Flaum
12/04/2024
Special inspection requirement — Footing and Foundation
Shmuel Flaum
12/04/2024
Special inspection requirement — Preliminary
Shmuel Flaum
12/04/2024
Special inspection requirement — Interior lighting power
Shmuel Flaum
12/04/2024
Special inspection requirement — Electric vehicle service equipment requirements
Shmuel Flaum
10/15/2024
Signed off — Alteration
Installation of sprinkler system in conjunction with application Q08003087.
Q08049552-I1
09/04/2024
Signed off — Alteration CO
PLUMBING WORK AS PER PLAN
Q08003087-S1
08/02/2024
Filed — Alteration CO
PLUMBING WORK AS PER PLAN
Q08003087-P2
08/01/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shmuel Flaum
08/01/2024
Special inspection requirement — Energy Code Compliance Inspections
Shmuel Flaum
08/01/2024
Special inspection requirement — HVAC-R and service water heating system controls
Shmuel Flaum
08/01/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Shmuel Flaum
08/01/2024
Special inspection requirement — HVAC-R and service water heating equipment
Shmuel Flaum
06/10/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/16/2024
Filed — Alteration CO
PLUMBING WORK AS PER PLAN
Q08003087-P1
05/15/2024
Special inspection requirement — Footing and Foundation
Shmuel Flaum
05/15/2024
Special inspection requirement — Preliminary
Shmuel Flaum
05/15/2024
Special inspection requirement — Concrete - Cast-In-Place
Shmuel Flaum
05/15/2024
Special inspection requirement — Interior lighting power
Shmuel Flaum
05/15/2024
Special inspection requirement — Electric vehicle service equipment requirements
Shmuel Flaum
05/15/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shmuel Flaum
05/15/2024
Special inspection requirement — Energy Code Compliance Inspections
Shmuel Flaum
01/31/2024
Signed off — Alteration
CONSTRUCTION FENCE
Q00807692-I1
01/03/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/01/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/19/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/19/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
11/15/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
11/15/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/15/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
11/13/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/18/2023
Permit issued — Construction Fence
Q00807692-I1-FN
09/11/2023
Permit issued — Plumbing
Q08049552-I1-PL
09/07/2023
Permit issued — Plumbing
Q08003087-S1-PL
09/06/2023
Permit issued — Sprinklers
Q08049552-I1-EW-SP
07/24/2023
Filed — Alteration CO
PLUMBING WORK AS PER PLAN
Q08003087-S1
07/07/2023
Permit issued — Construction Fence
Q00807692-I1-FN
07/07/2023
Permit issued — Foundation
Q08003087-I1-GC-CX
06/14/2023
Objection resolved — Addressed
06/14/2023
Objection resolved — Addressed
06/12/2023
Objection raised — Other
06/12/2023
Objection raised — Structural
06/06/2023
Filed — Alteration
CONSTRUCTION FENCE
Q00807692-I1
12/15/2022
Objection resolved — Addressed
12/06/2022
Filed — Alteration
Installation of sprinkler system in conjunction with application Q08003087.
Q08049552-I1
Latest 60 of 72 events.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SHMUEL D. FLAUM, ARCHITECT702/10/2025
ENGINEERING PROFESSIONAL SERVICE P.112/06/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MEP DESIGNS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HARMONY ENTERPRISES NY INGeneral Contractor507/08/2026
DPH PLUMBING & HTG CORPPlumbing207/08/2026
DNA PLUMBING CONTR. INCFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SHMUEL D. FLAUM, ARCHITEC4278602/10/2025
TRIANGLE INSPECTION & TES7495112/06/2022
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FenceSigned-offHARMONY ENTERPRISES NY IN10/18/2023
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP09/11/2023
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP09/07/2023
DOB NOWSprinklersSigned-offDNA PLUMBING CONTR. INC09/06/2023
DOB NOWConstruction FenceSigned-offHARMONY ENTERPRISES NY IN07/07/2023
DOB NOWFoundationPermit IssuedHARMONY ENTERPRISES NY IN07/07/2023
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
06/10/2024Pass-Final CND-Occupancy InspectionPassView ↗
01/03/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/01/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/19/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/19/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
11/15/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/15/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/15/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
11/13/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 32
DateRequirementInspectorRole
02/12/2025Concrete - Cast-In-PlaceShmuel Flaumspecial
02/12/2025Fire-Resistant Penetrations and JointsShmuel Flaumspecial
02/12/2025PreliminaryShmuel Flaumprogress
02/12/2025FinalNAVEEN KUMARprogress
02/12/2025Footing and FoundationShmuel Flaumprogress
02/12/2025Fire-Resistance Rated ConstructionShmuel Flaumprogress
02/12/2025Energy Code Compliance InspectionsShmuel Flaumprogress
02/12/2025Electric vehicle service equipment requirementsShmuel Flaumenergy_progress
02/12/2025Interior lighting powerShmuel Flaumenergy_progress
12/04/2024Concrete - Cast-In-PlaceShmuel Flaumspecial
12/04/2024Fire-Resistant Penetrations and JointsShmuel Flaumspecial
12/04/2024Energy Code Compliance InspectionsShmuel Flaumprogress
12/04/2024FinalNAVEEN KUMARprogress
12/04/2024Fire-Resistance Rated ConstructionShmuel Flaumprogress
12/04/2024Footing and FoundationShmuel Flaumprogress
12/04/2024PreliminaryShmuel Flaumprogress
12/04/2024Interior lighting powerShmuel Flaumenergy_progress
12/04/2024Electric vehicle service equipment requirementsShmuel Flaumenergy_progress
08/01/2024Fire-Resistant Penetrations and JointsShmuel Flaumspecial
08/01/2024Energy Code Compliance InspectionsShmuel Flaumprogress
08/01/2024HVAC-R and service water heating system controlsShmuel Flaumenergy_progress
08/01/2024HVAC-R and service water piping design and insulationShmuel Flaumenergy_progress
08/01/2024HVAC-R and service water heating equipmentShmuel Flaumenergy_progress
05/15/2024Footing and FoundationShmuel Flaumprogress
05/15/2024PreliminaryShmuel Flaumprogress
Latest 25 of 32.
▾Documents — 70 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/25/2026Q08049552-I1Request digital key ↗
08/24/2026Q00807692-I1Request digital key ↗
08/20/2026Q08003087-P2Request digital key ↗
Showing 3 of 8 on file for this type
▸Zoning, Tax Lot & Property Records11
▸DOB NOWRestrictive Declaration/Easement 16
08/20/2026Q08003087-P1Open ↗
08/20/2026Q08003087-P2Open ↗
08/20/2026Q08003087-P4Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWZD1: DOB Zoning Diagram4
08/20/2026Q08003087-P1Open ↗
08/20/2026Q08003087-P4Open ↗
08/20/2026Q08003087-P3Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/15/2026Q08003087-I1Open ↗
▸Seals & Professional Certifications22
▸DOB NOWProgress Inspector Seal & Signature10
09/02/2026Q08003087-I1Open ↗
09/02/2026Q08003087-I1Open ↗
09/02/2026Q08003087-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/20/2026Q08003087-S1Open ↗
08/20/2026Q08003087-P2Open ↗
08/20/2026Q08003087-P1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/02/2026Q08003087-I1Open ↗
08/27/2026Q08003087-P3Open ↗
08/26/2026Q08003087-P1Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist4
08/20/2026Q08003087-P1Open ↗
08/20/2026Q08003087-P4Open ↗
08/20/2026Q08003087-P3Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/15/2026Q08003087-I1Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/20/2026Q08003087-P1Open ↗
08/20/2026Q08003087-S1Open ↗
08/20/2026Q08003087-P4Open ↗
Showing 3 of 7 on file for this type
▸Other Documents17
▸DOB NOWSite Survey: Initial4
08/20/2026Q08003087-P1Open ↗
08/20/2026Q08003087-P4Open ↗
08/20/2026Q08003087-P3Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlot Diagram4
08/20/2026Q08003087-P1Open ↗
08/20/2026Q08003087-P4Open ↗
08/20/2026Q08003087-P3Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone4
08/20/2026Q08003087-P1Open ↗
08/20/2026Q08003087-P4Open ↗
08/20/2026Q08003087-P3Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProperty Ownership Certification4
08/20/2026Q08003087-P1Open ↗
08/20/2026Q08003087-P4Open ↗
08/20/2026Q08003087-P3Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWFinal Survey1
08/15/2026Q08003087-I1Open ↗