← Back
One family attached or semi-detached
150-03 77 ROAD
QUEENS · BIN 4144996
💬 Discuss this project
1945Year Built
2Stories
A5Building Class
R4Zoning
2,808 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
One family attached or semi-detached · 1,800 sf lot · 1.56 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneral
Floor 28p · 2 filings · 20 docs
Floor 110p · 1 filing · 20 docs
Basement11p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NEFCO ENTERPRISE INC103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HAYM S. GROSS, ARCHITECT609/11/2024
RIKE TECH ASSOCIATES LLC405/16/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BRITZ ENTERPRISES INC.2003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PRIMROSE SERVICE INCGeneral Contractor1907/08/2026
NEFCO ENTERPRISES INCGeneral Contractor903/21/2026
SPLEN CONSTRUCTION INCGeneral Contractor903/21/2026
CHANDRABALI RAMANANDGeneral Contractor107/08/2026
CROWN PLUMBING INCPlumbing107/08/2026
NEW YORK STANDARD MECH CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
RIKE TECH ASSOCIATES LLC29651409/11/2024
Building Lifecycle
All (80)Filed (10)Permit Issued (16)Signed Off (2)Violation (3)Inspection (11)Objection (8)Special Inspection (30)
11/01/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/25/2024
Special inspection requirement — Air barrier - visual inspection
SYED RIZVI
09/25/2024
Special inspection requirement — Insulation placement and R values
SYED RIZVI
09/25/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
SYED RIZVI
09/25/2024
Special inspection requirement — Protection of exposed foundation insulation
SYED RIZVI
09/25/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
SYED RIZVI
09/25/2024
Special inspection requirement — Fenestration air leakage
SYED RIZVI
09/25/2024
Special inspection requirement — Structural Steel - High Strength Bolting
SYED RIZVI
09/25/2024
Special inspection requirement — Chimneys and vents
SYED RIZVI
09/25/2024
Special inspection requirement — Energy Code Compliance Inspections
SYED RIZVI
09/25/2024
Special inspection requirement — Final
HAYM GROSS
09/25/2024
Special inspection requirement — HVAC-R and service water heating equipment
SYED RIZVI
09/25/2024
Special inspection requirement — HVAC-R and service water heating system controls
SYED RIZVI
09/25/2024
Special inspection requirement — Lighting in dwelling units
SYED RIZVI
09/25/2024
Special inspection requirement — Fenestration areas
SYED RIZVI
09/25/2024
Special inspection requirement — Structural Cold-Formed Steel
SYED RIZVI
09/25/2024
Special inspection requirement — Masonry
SYED RIZVI
09/25/2024
Special inspection requirement — Concrete - Cast-In-Place
SYED RIZVI
09/25/2024
Special inspection requirement — Subgrade Inspections
SYED RIZVI
09/25/2024
Special inspection requirement — Structural Steel - Details
SYED RIZVI
09/25/2024
Special inspection requirement — Structural Wood Frame
SYED RIZVI
09/25/2024
Special inspection requirement — Footing and Foundation
SYED RIZVI
09/25/2024
Special inspection requirement — Fire-Resistance Rated Construction
SYED RIZVI
09/25/2024
Special inspection requirement — Mechanical Systems
SYED RIZVI
09/25/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
SYED RIZVI
09/25/2024
Special inspection requirement — Interior lighting power
SYED RIZVI
09/25/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
SYED RIZVI
09/11/2024
Filed — Alteration CO
application filed herewith to enlarge front and rear; basement,001,002; new co
Q00655422-P6
09/11/2024
Special inspection requirement — Concrete - Cast-In-Place
SYED RIZVI
09/11/2024
Special inspection requirement — Protection of exposed foundation insulation
SYED RIZVI
09/11/2024
Special inspection requirement — Chimneys and vents
SYED RIZVI
09/11/2024
Special inspection requirement — HVAC-R and service water heating equipment
SYED RIZVI
09/03/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/27/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/07/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/01/2024
Permit issued — Mechanical Systems
Q00655422-I1-ST
07/24/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/18/2024
Permit issued — Mechanical Systems
Q00655422-I1-EA
07/18/2024
Permit issued — General Construction
Q00655422-I1-FO
06/20/2024
Signed off — Alteration
PLUMBING WORK THRU OUT; INCONJUNCTION WITH ALT Q00655422
Q00671681-I1
05/29/2024
Objection raised — Admin
05/29/2024
Objection resolved — Addressed
05/28/2024
Objection resolved — Addressed
05/24/2024
Objection raised — Scope
05/16/2024
Filed — Alteration
PLUMBING WORK THRU OUT; INCONJUNCTION WITH ALT Q00655422
Q00671681-P3
05/14/2024
Filed — Alteration CO
application filed herewith to enlarge front and rear; basement,001,002; new co
Q00655422-P4
05/01/2024
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
04/17/2024
Inspection — Fail-Final PL - Underground
Fail
View inspection ↗
03/06/2024
Permit issued — Structural
Q00655422-I1-GC
01/26/2024
Signed off — Alteration
Q00691984-I1
01/04/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/27/2023
Objection resolved — Addressed
12/22/2023
Objection raised — Scope
12/13/2023
Filed — Alteration CO
application filed herewith to enlarge front and rear; basement,001,002; new co
Q00655422-P3
12/12/2023
Filed — Alteration
PLUMBING WORK THRU OUT; INCONJUNCTION WITH ALT Q00655422
Q00671681-P2
12/05/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/30/2023
Permit issued — Plumbing
Q00671681-I1-PL
08/17/2023
Inspection — Pass-Final Fence Non-Directive 14
Pass
View inspection ↗
03/10/2023
Permit issued — Construction Fence
Q00691984-I1-FN
03/02/2023
Permit issued — Mechanical Systems
Q00655422-I1-GC
Latest 60 of 80 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offPRIMROSE SERVICE INC08/01/2024
DOB NOWMechanical SystemsSigned-offPRIMROSE SERVICE INC07/18/2024
DOB NOWGeneral ConstructionSigned-offPRIMROSE SERVICE INC07/18/2024
DOB NOWStructuralPermit IssuedPRIMROSE SERVICE INC03/06/2024
DOB NOWPlumbingSigned-offCROWN PLUMBING INC11/30/2023
DOB NOWConstruction FenceSigned-offPRIMROSE SERVICE INC03/10/2023
DOB NOWMechanical SystemsPermit IssuedPRIMROSE SERVICE INC03/02/2023
DOB NOWStructuralSigned-offPRIMROSE SERVICE INC03/01/2023
DOB NOWPlumbingSigned-offNEW YORK STANDARD MECH CORP10/27/2022
DOB NOWEarth WorkPermit IssuedSPLEN CONSTRUCTION INC09/16/2022
DOB NOWMechanical SystemsPermit IssuedSPLEN CONSTRUCTION INC07/30/2022
DOB NOWConstruction FenceSigned-offSPLEN CONSTRUCTION INC07/29/2022
DOB NOWEarth WorkSigned-offNEFCO ENTERPRISES INC05/04/2022
DOB NOWStructuralSigned-offNEFCO ENTERPRISES INC05/04/2022
DOB NOWFoundationPermit IssuedNEFCO ENTERPRISES INC05/04/2022
DOB NOWConstruction FenceSigned-offCHANDRABALI RAMANAND04/01/2022
1 project · most recent 09/11/2024
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
09/11/2024Signed-offPRIMROSE SERVICE INCAir Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Mitsubishi Electric MXZ-4C36NA3 108,000 BTU · Condensing Unit ×15
Heating
Navien NCB-240 108,000 BTU · Boiler ×10
Ventilation
Broan L300E 108,000 BTU · Exhaust Fan ×35
Carrier ×21
1 project · most recent 10/27/2022
General Wiring
FiledStatusContractorScope
10/27/2022CompleteR & T ELECTRICAL CORPGeneral Wiring
1 project · most recent 09/11/2024
Steel Concrete Masonry Wood
FiledStatusContractorScope
09/11/2024Signed-offPRIMROSE SERVICE INCSteel, Concrete, Masonry, Wood
1 project · most recent 09/11/2024
Earthwork
FiledStatusContractorScope
09/11/2024Signed-offPRIMROSE SERVICE INCEarthwork
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
11/01/2024Pass-Final CND-Occupancy InspectionPassView ↗
09/03/2024Pass-Final CND-Occupancy InspectionPassView ↗
08/27/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/07/2024Pass-Final CND-Occupancy InspectionPassView ↗
07/24/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/01/2024Pass-Final PL - UndergroundPassView ↗
04/17/2024Fail-Final PL - UndergroundFailView ↗
01/04/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/05/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/17/2023Pass-Final Fence Non-Directive 14PassView ↗
01/30/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 112
DateRequirementInspectorRole
09/25/2024Fenestration areasSYED RIZVIenergy_progress
09/25/2024Mechanical SystemsSYED RIZVIspecial
09/25/2024Structural Cold-Formed SteelSYED RIZVIspecial
09/25/2024Fire-Resistant Penetrations and JointsSYED RIZVIspecial
09/25/2024MasonrySYED RIZVIspecial
09/25/2024Structural Steel - High Strength BoltingSYED RIZVIspecial
09/25/2024Concrete - Cast-In-PlaceSYED RIZVIspecial
09/25/2024Subgrade InspectionsSYED RIZVIspecial
09/25/2024Chimneys and ventsSYED RIZVIspecial
09/25/2024Structural Stability – Alterations of existing buildingsSYED RIZVIspecial
09/25/2024Structural Steel - DetailsSYED RIZVIspecial
09/25/2024Structural Wood FrameSYED RIZVIprogress
09/25/2024Energy Code Compliance InspectionsSYED RIZVIprogress
09/25/2024Footing and FoundationSYED RIZVIprogress
09/25/2024Fire-Resistance Rated ConstructionSYED RIZVIprogress
09/25/2024FinalHAYM GROSSprogress
09/25/2024Protection of exposed foundation insulationSYED RIZVIenergy_progress
09/25/2024Air barrier - visual inspectionSYED RIZVIenergy_progress
09/25/2024HVAC-R and service water heating equipmentSYED RIZVIenergy_progress
09/25/2024Interior lighting powerSYED RIZVIenergy_progress
09/25/2024HVAC-R and service water piping design and insulationSYED RIZVIenergy_progress
09/25/2024HVAC-R and service water heating system controlsSYED RIZVIenergy_progress
09/25/2024Fenestration and door U-factor and product ratingsSYED RIZVIenergy_progress
09/25/2024Insulation placement and R valuesSYED RIZVIenergy_progress
09/25/2024Fenestration air leakageSYED RIZVIenergy_progress
Latest 25 of 112.
▾Documents — 180 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch10
08/26/2026Q00671681-I1Request digital key ↗
08/26/2026Q00671681-P3Request digital key ↗
08/26/2026Q00671681-P1Request digital key ↗
Showing 3 of 10 on file for this type
▸Zoning, Tax Lot & Property Records6
▸DOB NOWZD1: DOB Zoning Diagram5
08/21/2026Q00655422-I1Open ↗
08/13/2026Q00655422-P6Open ↗
08/13/2026Q00655422-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/21/2026Q00655422-I1Open ↗
▸Seals & Professional Certifications122
▸DOB NOWProgress Inspector Seal & Signature68
09/26/2026Q00655422-P6Open ↗
09/26/2026Q00655422-P6Open ↗
09/26/2026Q00655422-P6Open ↗
Showing 3 of 68 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature44
09/26/2026Q00655422-P6Open ↗
09/26/2026Q00655422-P6Open ↗
09/26/2026Q00655422-P6Open ↗
Showing 3 of 44 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/21/2026Q00655422-P3Open ↗
08/21/2026Q00655422-P4Open ↗
08/21/2026Q00655422-P6Open ↗
Showing 3 of 10 on file for this type
▸Trade Schedules & Equipment5
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)5
08/21/2026Q00655422-I1Open ↗
08/13/2026Q00655422-P4Open ↗
08/13/2026Q00655422-P3Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist5
08/21/2026Q00655422-P6Open ↗
08/21/2026Q00655422-I1Open ↗
08/21/2026Q00655422-P3Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos9
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/21/2026Q00655422-P6Open ↗
08/21/2026Q00655422-P3Open ↗
08/21/2026Q00655422-I1Open ↗
Showing 3 of 9 on file for this type
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
08/21/2026Q00655422-I1Open ↗
▸Other Documents22
▸DOB NOWPlot Diagram5
08/21/2026Q00655422-I1Open ↗
08/13/2026Q00655422-P4Open ↗
08/13/2026Q00655422-P6Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone5
08/21/2026Q00655422-I1Open ↗
08/13/2026Q00655422-P3Open ↗
08/13/2026Q00655422-P6Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProperty Ownership Certification5
08/21/2026Q00655422-P3Open ↗
08/21/2026Q00655422-P6Open ↗
08/21/2026Q00655422-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSite Survey: Initial4
08/21/2026Q00655422-I1Open ↗
08/13/2026Q00655422-P6Open ↗
08/13/2026Q00655422-P3Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProject Specific General Liability (PGL1)1
08/21/2026Q00655422-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/21/2026Q00655422-I1Open ↗
▸DOB NOWFinal Survey1
08/21/2026Q00655422-I1Open ↗