One story - permanent living quarter
65-31 171 STREET
QUEENS · BIN 4149297
💬 Discuss this project
1955Year Built
1Stories
A2Building Class
R2Zoning
1,264 sfGross Floor Area
1Units
One story - permanent living quarter · 5,000 sf lot · 0.25 FAR built · Flood zone X
Locations of Work
Architecture
Permit Issued — active, not yet Signed-off
RoofUnder Construction1p · 1 filing · 7 docs
CellarUnder Construction1p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AMINOV DESIGN ENGINEER, PC208/19/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FORTRESS FORCE CONST. CORGeneral Contractor108/30/2026
Building Lifecycle
All (23)Filed (2)Permit Issued (1)Special Inspection (20)
08/28/2026
Permit issued — Construction Fence
Q01440531-S1-FN
08/19/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
HORIZONTAL & VERTICAL ENLARGEMENTS TO AN EXISTING ONE FAMILY DWELLING ALONG WITH INTERIOR RENOVATION
Q01440531-S1
08/14/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
HORIZONTAL & VERTICAL ENLARGEMENTS TO AN EXISTING ONE FAMILY DWELLING ALONG WITH INTERIOR RENOVATION
Q01440531-I1
08/04/2026
Special inspection requirement — Mechanical Systems
08/04/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/04/2026
Special inspection requirement — Energy Code Compliance Inspections
08/04/2026
Special inspection requirement — Fire-Resistance Rated Construction
08/04/2026
Special inspection requirement — Final
08/04/2026
Special inspection requirement — Air barrier — testing
08/04/2026
Special inspection requirement — Insulation placement and R values
08/04/2026
Special inspection requirement — Fenestration air leakage
08/04/2026
Special inspection requirement — HVAC-R and service water heating equipment
08/04/2026
Special inspection requirement — Air barrier - visual inspection
08/04/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
08/04/2026
Special inspection requirement — Interior lighting power
08/04/2026
Special inspection requirement — HVAC-R and service water heating system controls
08/04/2026
Special inspection requirement — Electric vehicle service equipment requirements
08/04/2026
Special inspection requirement — Maintenance information
08/04/2026
Special inspection requirement — Fenestration areas
08/04/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
08/04/2026
Special inspection requirement — Permanent certificate
08/04/2026
Special inspection requirement — Protection of exposed foundation insulation
08/04/2026
Special inspection requirement — Ventilation and air distribution system
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FencePermit IssuedFORTRESS FORCE CONST. COR08/28/2026
1 project · most recent 08/19/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/19/2026Permit IssuedFORTRESS FORCE CONST. CORHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric MXZ-SM48NL 48,000 BTU · Heat Pump Outdoor ×3
Ventilation
Panasonic FV-10VEC2 100 CFM · Erv ×1
1 project · most recent 08/19/2026
Fence
FiledStatusContractorScope
08/19/2026Permit IssuedFORTRESS FORCE CONST. CORFence
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
08/04/2026Mechanical Systems—special
08/04/2026Fire-Resistant Penetrations and Joints—special
08/04/2026Energy Code Compliance Inspections—progress
08/04/2026Fire-Resistance Rated Construction—progress
08/04/2026Final—progress
08/04/2026Air barrier — testing —energy_progress
08/04/2026Insulation placement and R values—energy_progress
08/04/2026Fenestration air leakage—energy_progress
08/04/2026HVAC-R and service water heating equipment—energy_progress
08/04/2026Air barrier - visual inspection—energy_progress
08/04/2026Fenestration and door U-factor and product ratings—energy_progress
08/04/2026Interior lighting power—energy_progress
08/04/2026HVAC-R and service water heating system controls—energy_progress
08/04/2026Electric vehicle service equipment requirements—energy_progress
08/04/2026Maintenance information—energy_progress
08/04/2026Fenestration areas—energy_progress
08/04/2026HVAC-R and service water piping design and insulation—energy_progress
08/04/2026Permanent certificate—energy_progress
08/04/2026Protection of exposed foundation insulation—energy_progress
08/04/2026Ventilation and air distribution system—energy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/16/2026Q01440531-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
08/16/2026Q01440531-I1Open ↗
▸Seals & Professional Certifications1
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/16/2026Q01440531-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/16/2026Q01440531-I1Open ↗
▸Other Documents3
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/16/2026Q01440531-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/16/2026Q01440531-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/16/2026Q01440531-I1Open ↗