| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/22/2025 | Permit Issued | FOUR POINTS P & H CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2025 | Permit Issued | NAS ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/22/2025 | Permit Issued | FOUR POINTS P & H CORP | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/22/2025 | Permit Issued | FOUR POINTS P & H CORP | Fence |
| Owner | Filings | Most Recent |
|---|---|---|
| RECORD GROUP | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/15/2024 | $1.9M | — | Private party → 18117 TUDOR LLC | $1,565/sf building |
| 01/31/2019 | $1.5M | — | Private party → Private party | $1,269/sf building |
| 10/27/2017 | $1.4M | — | Private party → Private party | $1,227/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| AA BLDG & INSP SVC LLC | 7 | 10/22/2025 |
| RAS PE CONSULTING ENGINEERS | 3 | 12/31/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| DMCONSULTING6860 | 18 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RECORD GROUP INC | General Contractor | 8 | 07/08/2026 |
| IMPACT BUILDERS CORP | General Contractor | 4 | 04/09/2026 |
| FOUR POINTS P & H CORP | Plumbing | 2 | 08/25/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| WORLD DESIGN ARCHITECTURE | 9323 | 8 | 10/22/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | FOUR POINTS P & H CORP | 08/24/2026 |
| DOB NOW | Structural | Signed-off | RECORD GROUP INC | 01/27/2026 |
| DOB NOW | Construction Fence | Permit Issued | IMPACT BUILDERS CORP | 01/27/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | RECORD GROUP INC | 01/27/2026 |
| DOB NOW | Plumbing | Permit Issued | FOUR POINTS P & H CORP | 07/10/2025 |
| DOB NOW | Structural | Signed-off | RECORD GROUP INC | 02/25/2025 |
| DOB NOW | Foundation | Signed-off | RECORD GROUP INC | 02/25/2025 |
| DOB NOW | Support of Excavation | Signed-off | RECORD GROUP INC | 02/21/2025 |
| DOB NOW | Construction Fence | Permit Issued | IMPACT BUILDERS CORP | 02/10/2025 |
| DOB NOW | General Construction | Permit Issued | RECORD GROUP INC | 02/10/2025 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/24/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 07/16/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/03/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/18/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/03/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/04/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/04/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/29/2025 | Duct leakage testing, insulation and design | William Alicea | energy_progress |
| 10/29/2025 | Construction Operations Influencing Adjacent Structures | William Alicea | special |
| 10/29/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | William Alicea | special |
| 10/29/2025 | Mechanical Systems | William Alicea | special |
| 10/29/2025 | Subgrade Inspections | William Alicea | special |
| 10/29/2025 | Structural Stability – Alterations of existing buildings | William Alicea | special |
| 10/29/2025 | Fire-Resistant Penetrations and Joints | William Alicea | special |
| 10/29/2025 | Concrete - Cast-In-Place | William Alicea | special |
| 10/29/2025 | Subsurface Investigations (Borings/Test Pits) | FAHAD FATEH | special |
| 10/29/2025 | Final | William Alicea | progress |
| 10/29/2025 | Fire-Resistance Rated Construction | William Alicea | progress |
| 10/29/2025 | Energy Code Compliance Inspections | William Alicea | progress |
| 10/29/2025 | Maintenance information | William Alicea | energy_progress |
| 10/29/2025 | Ventilation and air distribution system | William Alicea | energy_progress |
| 10/29/2025 | Air barrier - visual inspection | William Alicea | energy_progress |
| 10/29/2025 | Fenestration areas | William Alicea | energy_progress |
| 10/29/2025 | Electric vehicle service equipment requirements | William Alicea | energy_progress |
| 10/29/2025 | HVAC-R and service water heating system controls | William Alicea | energy_progress |
| 10/29/2025 | Fenestration and door U-factor and product ratings | William Alicea | energy_progress |
| 10/29/2025 | Fireplaces | William Alicea | energy_progress |
| 10/29/2025 | Permanent certificate | William Alicea | energy_progress |
| 10/29/2025 | Metering | William Alicea | energy_progress |
| 10/29/2025 | HVAC-R and service water piping design and insulation | William Alicea | energy_progress |
| 10/29/2025 | Protection of exposed foundation insulation | William Alicea | energy_progress |
| 10/29/2025 | Fenestration air leakage | William Alicea | energy_progress |