Two family converted from one family · 0.45 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR207/22/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ISLAND ELECTRIC CORPElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281207/22/2026
Building Lifecycle
All (9)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (5)
08/04/2026
Signed off — Alteration
Installation of solar panels, rooftop, grid tied, railed, 22 modules, 9.02 KW
Q01347916-I1
07/24/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
07/24/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
07/24/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
07/24/2026
Special inspection requirement — Final
Mina Makar
07/24/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
07/22/2026
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 22 modules, 9.02 KW
Q01347916-P1
01/22/2026
Permit issued — Solar
Q01347916-I1-SL
01/16/2026
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 22 modules, 9.02 KW
Q01347916-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR01/22/2026
BIS—ISSUEDV.C CONSTRUCTION CO OF QUEENS,IN01/13/2005
1 project · most recent 03/17/2026
FiledStatusContractorScope
03/17/2026CompleteISLAND ELECTRIC CORP—
1 project · most recent 07/22/2026
FiledStatusContractorScope
07/22/2026Signed-offMOMENTUM SOLAR66 panels, 27.06 kw, 387 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
07/24/2026Fire-Resistant Penetrations and JointsMina Makarspecial
07/24/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
07/24/2026Energy Code Compliance InspectionsMina Makarprogress
07/24/2026FinalMina Makarprogress
07/24/2026Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 10 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026Q01347916-P1Request digital key ↗
08/17/2026Q01347916-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/17/2026Q01347916-P1Open ↗
08/13/2026Q01347916-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/22/2026Q01347916-I1Open ↗
08/22/2026Q01347916-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/22/2026Q01347916-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/17/2026Q01347916-P1Open ↗
08/13/2026Q01347916-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/17/2026Q01347916-I1Open ↗