Two stories - detached, small or mid-size
82-15 234 STREET
QUEENS · BIN 4166174
💬 Discuss this project
1930Year Built
2Stories
A1Building Class
R1-2AZoning
4,000 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 6,000 sf lot · 0.67 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbingGeneral
Floor 645p · 1 filing · 20 docs
Floor 63
Floor 62
Floor 61
Floor 60
Floor 59
Floor 58
Floor 57
Floor 56
Floor 55
Floor 54
Floor 53
Floor 52
Floor 51
Floor 50
Floor 49
Floor 48
Floor 47
Floor 46
Floor 45
Floor 44
Floor 43
Floor 42
Floor 41
Floor 40
Floor 39
Floor 38
Floor 37
Floor 36
Floor 35
Floor 34
Floor 33
Floor 32
Floor 31
Floor 30
Floor 29
Floor 28
Floor 27
Floor 26
Floor 25
Floor 24
Floor 23
Floor 22
Floor 21
Floor 20
Floor 19
Floor 18
Floor 17
Floor 16
Floor 15
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
Cellar2p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SONS S CONSTRUCTION1807/08/2026
TO THE OWNER OF 82-15 234103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GRACE ENGINEERING PLLC.702/17/2025
MOMENTUM SOLAR106/10/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARCHITECTUAL CONCEPT1403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MARK CONTRACTING NY INCGeneral Contractor207/08/2026
ALL WAYS ELECTRIC CORP.WElectrical103/22/2026
BR ELECTRICAL INCElectrical103/22/2026
JOHNNY'S P&H CONTRAC INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GRACE ENGINEERING PLLC.2176702/17/2025
MXV SIA LLC9281106/10/2024
Building Lifecycle
All (40)Filed (8)Permit Issued (4)Signed Off (3)Violation (1)Inspection (6)Special Inspection (18)
05/09/2025
Signed off — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 31 Panels, 12.71 kW
Q01063307-I1
03/11/2025
Signed off — Alteration
APPLICATION FILING FOR INTERIOR RENOVATION TO CONVERT EXISTING HALF BATHROOM INTO THREE FIXTURES BATHROOM IN THE CELLAR, REPLACEMENT OF BATHTUB WITH SHOWER AT FIRST FLOOR. INSTALLATION OF NEW WASHER, GAS DRYER AND BBQ FIXTURE AS PER DRAWING.
Q01053940-I1
03/11/2025
Signed off — Alteration
Interior renovation to convert half bath in cellar to full bathroom, replace existing 1st floor bathroom fixtures and smoked damage existing first floor joist.
Q01053932-I1
03/05/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
02/28/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
02/17/2025
Filed — Alteration
Interior renovation to convert half bath in cellar to full bathroom, replace existing 1st floor bathroom fixtures and smoked damage existing first floor joist.
Q01053932-P1
02/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TARIQ SIDDIQUI
02/17/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
TARIQ SIDDIQUI
02/17/2025
Special inspection requirement — Energy Code Compliance Inspections
TARIQ SIDDIQUI
02/17/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
TARIQ SIDDIQUI
02/17/2025
Special inspection requirement — Fire-Resistance Rated Construction
TARIQ SIDDIQUI
02/17/2025
Special inspection requirement — Final
TARIQ SIDDIQUI
02/13/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
01/23/2025
Filed — Alteration
APPLICATION FILING FOR INTERIOR RENOVATION TO CONVERT EXISTING HALF BATHROOM INTO THREE FIXTURES BATHROOM IN THE CELLAR, REPLACEMENT OF BATHTUB WITH SHOWER AT FIRST FLOOR. INSTALLATION OF NEW WASHER, GAS DRYER AND BBQ FIXTURE AS PER DRAWING.
Q01053940-P4
01/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TARIQ SIDDIQUI
01/08/2025
Special inspection requirement — Energy Code Compliance Inspections
TARIQ SIDDIQUI
01/08/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
TARIQ SIDDIQUI
12/17/2024
Filed — Alteration
APPLICATION FILING FOR INTERIOR RENOVATION TO CONVERT EXISTING HALF BATHROOM INTO THREE FIXTURES BATHROOM IN THE CELLAR, REPLACEMENT OF BATHTUB WITH SHOWER AT FIRST FLOOR. INSTALLATION OF NEW WASHER, GAS DRYER AND BBQ FIXTURE AS PER DRAWING.
Q01053940-P3
12/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TARIQ SIDDIQUI
12/17/2024
Special inspection requirement — Energy Code Compliance Inspections
TARIQ SIDDIQUI
12/17/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
TARIQ SIDDIQUI
11/21/2024
Filed — Alteration
APPLICATION FILING FOR INTERIOR RENOVATION TO CONVERT EXISTING HALF BATHROOM INTO THREE FIXTURES BATHROOM IN THE CELLAR, REPLACEMENT OF BATHTUB WITH SHOWER AT FIRST FLOOR. INSTALLATION OF NEW WASHER, GAS DRYER AND BBQ FIXTURE AS PER DRAWING.
Q01053940-P2
11/21/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TARIQ SIDDIQUI
11/21/2024
Special inspection requirement — Energy Code Compliance Inspections
TARIQ SIDDIQUI
11/21/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
TARIQ SIDDIQUI
08/30/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
08/19/2024
Filed — Alteration
APPLICATION FILING FOR INTERIOR RENOVATION TO CONVERT EXISTING HALF BATHROOM INTO THREE FIXTURES BATHROOM IN THE CELLAR, REPLACEMENT OF BATHTUB WITH SHOWER AT FIRST FLOOR. INSTALLATION OF NEW WASHER, GAS DRYER AND BBQ FIXTURE AS PER DRAWING.
Q01053940-P1
08/02/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/02/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
07/30/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
TARIQ SIDDIQUI
07/30/2024
Special inspection requirement — Energy Code Compliance Inspections
TARIQ SIDDIQUI
07/30/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TARIQ SIDDIQUI
07/22/2024
Permit issued — Plumbing
Q01053940-I1-PL
07/12/2024
Permit issued — General Construction
Q01053932-I1-ST
07/12/2024
Permit issued — Structural
Q01053932-I1-GC
07/01/2024
Filed — Alteration
APPLICATION FILING FOR INTERIOR RENOVATION TO CONVERT EXISTING HALF BATHROOM INTO THREE FIXTURES BATHROOM IN THE CELLAR, REPLACEMENT OF BATHTUB WITH SHOWER AT FIRST FLOOR. INSTALLATION OF NEW WASHER, GAS DRYER AND BBQ FIXTURE AS PER DRAWING.
Q01053940-I1
07/01/2024
Filed — Alteration
Interior renovation to convert half bath in cellar to full bathroom, replace existing 1st floor bathroom fixtures and smoked damage existing first floor joist.
Q01053932-I1
06/12/2024
Permit issued — Solar
Q01063307-I1-SL
06/10/2024
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 31 Panels, 12.71 kW
Q01063307-I1
11/13/2001
Violation issued (ECB, closed)
Site Safety
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offJOHNNY NANHU07/22/2024
DOB NOWGeneral ConstructionSigned-offMARK CONTRACTING NY INC07/12/2024
DOB NOWStructuralSigned-offMARK CONTRACTING NY INC07/12/2024
DOB NOWSolarSigned-offMOMENTUM SOLAR06/12/2024
BISPLISSUEDJOHNNY'S P&H CONTRAC INC02/05/2001
BIS—ISSUEDSHELL & B CONST01/11/2001
BISEQISSUEDSHELL & B CONST01/11/2001
BIS—ISSUEDSHELL & B CONSTRUCTION INC.12/11/2000
BISEQISSUEDSHELL & B CONSTRUCTION INC.12/11/2000
3 projects · most recent 09/09/2024
General Wiring Lighting
FiledStatusContractorScope
09/09/2024CompleteBR ELECTRICAL INCGeneral Wiring, Lighting
06/07/2024CompleteISLAND ELECTRIC CORP—
03/13/2024Permit IssuedALL WAYS ELECTRIC CORP.W—
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
03/05/2025Pass-Final General Construction Non-Directive 14PassView ↗
02/28/2025Fail-Final General Construction Non-Directive 14FailView ↗
02/13/2025Fail-Final General Construction Non-Directive 14FailView ↗
08/30/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
08/02/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/02/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
02/17/2025Fire-Resistant Penetrations and JointsTARIQ SIDDIQUIspecial
02/17/2025Structural Stability – Alterations of existing buildingsTARIQ SIDDIQUIspecial
02/17/2025Energy Code Compliance InspectionsTARIQ SIDDIQUIprogress
02/17/2025HVAC-R and service water piping design and insulationTARIQ SIDDIQUIenergy_progress
02/17/2025Fire-Resistance Rated ConstructionTARIQ SIDDIQUIprogress
02/17/2025FinalTARIQ SIDDIQUIprogress
01/08/2025Fire-Resistant Penetrations and JointsTARIQ SIDDIQUIspecial
01/08/2025Energy Code Compliance InspectionsTARIQ SIDDIQUIprogress
01/08/2025HVAC-R and service water piping design and insulationTARIQ SIDDIQUIenergy_progress
12/17/2024Fire-Resistant Penetrations and JointsTARIQ SIDDIQUIspecial
12/17/2024Energy Code Compliance InspectionsTARIQ SIDDIQUIprogress
12/17/2024HVAC-R and service water piping design and insulationTARIQ SIDDIQUIenergy_progress
11/21/2024Fire-Resistant Penetrations and JointsTARIQ SIDDIQUIspecial
11/21/2024Energy Code Compliance InspectionsTARIQ SIDDIQUIprogress
11/21/2024HVAC-R and service water piping design and insulationTARIQ SIDDIQUIenergy_progress
07/30/2024HVAC-R and service water piping design and insulationTARIQ SIDDIQUIenergy_progress
07/30/2024Energy Code Compliance InspectionsTARIQ SIDDIQUIprogress
07/30/2024Fire-Resistant Penetrations and JointsTARIQ SIDDIQUIspecial
▾Documents — 40 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/22/2026Q01063307-I1Request digital key ↗
08/22/2026Q01053940-P3Request digital key ↗
08/22/2026Q01053940-P2Request digital key ↗
Showing 3 of 8 on file for this type
▸Zoning, Tax Lot & Property Records7
▸DOB NOWRestrictive Declaration/Easement 17
08/13/2026Q01053940-P2Open ↗
08/13/2026Q01053940-P4Open ↗
08/13/2026Q01053932-P1Open ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications23
▸DOB NOWProgress Inspector Seal & Signature10
09/29/2026Q01053940-P1Open ↗
09/29/2026Q01053940-P1Open ↗
08/29/2026Q01053940-P4Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/22/2026Q01063307-I1Open ↗
08/22/2026Q01053940-P4Open ↗
08/22/2026Q01053940-P3Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/29/2026Q01053940-P1Open ↗
08/29/2026Q01053940-P4Open ↗
08/28/2026Q01053932-P1Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/22/2026Q01063307-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01063307-I1Open ↗