1945Year Built
1.5Stories
A0Building Class
R2AZoning
1,140 sfGross Floor Area
1Units
Cape Cod · 5,000 sf lot · 0.23 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Roof1p · 1 filing · 20 docs
Floor 210p · 1 filing · 20 docs
Floor 110p · 1 filing · 20 docs
Cellar10p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
URENA CONSTRUCTION & DESIGN1004/09/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
FANG ARCHITECT405/12/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
FANG ARCHITECT303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
URENA CONST & DESIGN INCGeneral Contractor204/09/2026
INFINITI ESC PLUMBING CORPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
FANG ARCHITECT5513405/12/2026
Building Lifecycle
All (77)Filed (4)Permit Issued (3)Signed Off (2)Inspection (8)Objection (30)Special Inspection (30)
05/28/2026
Signed off — Alteration CO
CONVERT ATTIC TO PART OF 1-FAMILY DWELLING. TO OBTAIN NEW C OF O.
Q01209782-I1
05/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
DEZHANG FANG
05/14/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
DEZHANG FANG
05/14/2026
Special inspection requirement — Fire-Resistance Rated Construction
DEZHANG FANG
05/14/2026
Special inspection requirement — Energy Code Compliance Inspections
DEZHANG FANG
05/14/2026
Special inspection requirement — Structural Wood Frame
DEZHANG FANG
05/14/2026
Special inspection requirement — Final
DEZHANG FANG
05/14/2026
Special inspection requirement — Maintenance information
DEZHANG FANG
05/14/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
DEZHANG FANG
05/14/2026
Special inspection requirement — Fenestration areas
DEZHANG FANG
05/14/2026
Special inspection requirement — Insulation placement and R values
DEZHANG FANG
05/14/2026
Special inspection requirement — Air barrier - visual inspection
DEZHANG FANG
05/14/2026
Special inspection requirement — Metering
DEZHANG FANG
05/14/2026
Special inspection requirement — Interior lighting power
DEZHANG FANG
05/14/2026
Special inspection requirement — Fenestration air leakage
DEZHANG FANG
05/12/2026
Filed — Alteration CO
CONVERT ATTIC TO PART OF 1-FAMILY DWELLING. TO OBTAIN NEW C OF O.
Q01209782-P4
05/12/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
DEZHANG FANG
05/12/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
DEZHANG FANG
05/12/2026
Special inspection requirement — Energy Code Compliance Inspections
DEZHANG FANG
05/12/2026
Special inspection requirement — Final
DEZHANG FANG
05/12/2026
Special inspection requirement — Fire-Resistance Rated Construction
DEZHANG FANG
05/12/2026
Special inspection requirement — Structural Wood Frame
DEZHANG FANG
05/12/2026
Special inspection requirement — Metering
DEZHANG FANG
05/12/2026
Special inspection requirement — Fenestration air leakage
DEZHANG FANG
05/12/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
DEZHANG FANG
05/12/2026
Special inspection requirement — Insulation placement and R values
DEZHANG FANG
05/12/2026
Special inspection requirement — Fenestration areas
DEZHANG FANG
05/12/2026
Special inspection requirement — Air barrier - visual inspection
DEZHANG FANG
05/12/2026
Special inspection requirement — Interior lighting power
DEZHANG FANG
05/12/2026
Special inspection requirement — Maintenance information
DEZHANG FANG
02/18/2026
Permit issued — Structural
Q01209782-I1-ST
02/13/2026
Signed off — Alteration CO
CONVERT ATTIC TO PART OF 1-FAMILY DWELLING. TO OBTAIN NEW C OF O.
Q01209782-S1
02/13/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/19/2026
Filed — Alteration CO
CONVERT ATTIC TO PART OF 1-FAMILY DWELLING. TO OBTAIN NEW C OF O.
Q01209782-P1
01/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
DEZHANG FANG
01/14/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
DEZHANG FANG
01/13/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/24/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/18/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/16/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
09/11/2025
Permit issued — Plumbing
Q01209782-S1-PL
09/11/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/19/2025
Objection resolved — Addressed
08/19/2025
Objection resolved — Addressed
08/06/2025
Permit issued — General Construction
Q01209782-I1-GC
08/05/2025
Objection resolved — Addressed
07/28/2025
Objection resolved — Addressed
07/24/2025
Objection raised — Cost
07/19/2025
Objection resolved — Addressed
07/19/2025
Objection resolved — Addressed
07/19/2025
Objection resolved — Addressed
07/16/2025
Objection raised — Cost
07/16/2025
Objection raised — Admin
07/16/2025
Objection raised — Other
07/11/2025
Objection raised — Zoning
07/11/2025
Objection raised — Zoning
07/07/2025
Filed — Alteration CO
CONVERT ATTIC TO PART OF 1-FAMILY DWELLING. TO OBTAIN NEW C OF O.
Q01209782-S1
07/02/2025
Objection resolved — Addressed
07/02/2025
Objection resolved — Addressed
07/02/2025
Objection resolved — Addressed
Latest 60 of 77 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offURENA CONST & DESIGN INC02/18/2026
DOB NOWPlumbingSigned-offINFINITI ESC PLUMBING COR09/11/2025
DOB NOWGeneral ConstructionPermit IssuedURENA CONST & DESIGN INC08/06/2025
1 project · most recent 05/12/2026
Gas Water/Sanitary
FiledStatusContractorScope
05/12/2026Signed-offINFINITI ESC PLUMBING CORGas, Water/Sanitary
2 projects · most recent 09/16/2025
General Wiring
FiledStatusContractorScope
09/16/2025CompleteSAMMY ELECTRIC SVCS CORPGeneral Wiring
10/09/2024CompleteALL WAYS ELECTRIC CORP.W—
1 project · most recent 05/12/2026
Wood
FiledStatusContractorScope
05/12/2026Signed-offURENA CONST & DESIGN INCWood
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
02/13/2026Pass-Final CND-Occupancy InspectionPassView ↗
01/13/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/24/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/18/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/16/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/11/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/14/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/02/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 43
DateRequirementInspectorRole
05/14/2026Fire-Resistant Penetrations and JointsDEZHANG FANGspecial
05/14/2026Structural Stability – Alterations of existing buildingsDEZHANG FANGspecial
05/14/2026Fire-Resistance Rated ConstructionDEZHANG FANGprogress
05/14/2026Energy Code Compliance InspectionsDEZHANG FANGprogress
05/14/2026Structural Wood FrameDEZHANG FANGprogress
05/14/2026FinalDEZHANG FANGprogress
05/14/2026Maintenance informationDEZHANG FANGenergy_progress
05/14/2026Fenestration and door U-factor and product ratingsDEZHANG FANGenergy_progress
05/14/2026Fenestration areasDEZHANG FANGenergy_progress
05/14/2026Insulation placement and R valuesDEZHANG FANGenergy_progress
05/14/2026Air barrier - visual inspectionDEZHANG FANGenergy_progress
05/14/2026MeteringDEZHANG FANGenergy_progress
05/14/2026Interior lighting powerDEZHANG FANGenergy_progress
05/14/2026Fenestration air leakageDEZHANG FANGenergy_progress
05/12/2026Fire-Resistant Penetrations and JointsDEZHANG FANGspecial
05/12/2026Structural Stability – Alterations of existing buildingsDEZHANG FANGspecial
05/12/2026Energy Code Compliance InspectionsDEZHANG FANGprogress
05/12/2026FinalDEZHANG FANGprogress
05/12/2026Fire-Resistance Rated ConstructionDEZHANG FANGprogress
05/12/2026Structural Wood FrameDEZHANG FANGprogress
05/12/2026MeteringDEZHANG FANGenergy_progress
05/12/2026Fenestration air leakageDEZHANG FANGenergy_progress
05/12/2026Fenestration and door U-factor and product ratingsDEZHANG FANGenergy_progress
05/12/2026Insulation placement and R valuesDEZHANG FANGenergy_progress
05/12/2026Fenestration areasDEZHANG FANGenergy_progress
Latest 25 of 43.
▾Documents — 27 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/16/2026Q01209782-I1Request digital key ↗
08/16/2026Q01209782-P1Request digital key ↗
08/16/2026Q01209782-P4Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications14
▸DOB NOWProgress Inspector Seal & Signature6
08/28/2026Q01209782-P1Open ↗
08/28/2026Q01209782-P1Open ↗
08/25/2026Q01209782-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/16/2026Q01209782-I1Open ↗
08/16/2026Q01209782-P1Open ↗
08/16/2026Q01209782-P4Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/28/2026Q01209782-P1Open ↗
08/25/2026Q01209782-I1Open ↗
08/25/2026Q01209782-S1Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist3
08/16/2026Q01209782-P4Open ↗
08/13/2026Q01209782-I1Open ↗
08/13/2026Q01209782-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
08/16/2026Q01209782-I1Open ↗
08/16/2026Q01209782-S1Open ↗
▸Other Documents4
▸DOB NOWProperty Ownership Certification3
08/16/2026Q01209782-I1Open ↗
08/16/2026Q01209782-P1Open ↗
08/16/2026Q01209782-P4Open ↗
▸DOB NOWFinal Survey1
08/13/2026Q01209782-I1Open ↗