| Firm | Filings | Most Recent |
|---|---|---|
| SOLANKI ENGINEERING, PC | 5 | 08/05/2025 |
| MOMENTUM SOLAR | 1 | 06/10/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SHYAM CONSTRUCTION INC | General Contractor | 1 | 04/09/2026 |
| SAFEPIPE PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SOLANKI ENGINEERING, P.C. | 8451 | 4 | 08/05/2025 |
| TRIANGLE INSPECTION & TES | 7495 | 1 | 08/05/2025 |
| MXV SIA LLC | 9281 | 1 | 06/10/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | BELLEROSE PLBG & HTG | 04/01/2026 |
| DOB NOW | General Construction | Signed-off | SHYAM CONSTRUCTION INC | 11/10/2025 |
| DOB NOW | Solar | Permit Issued | MOMENTUM SOLAR | 06/12/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/05/2025 | Permit Issued | BELLEROSE PLBG & HTG | Storm, Water/Sanitary |
| 04/16/2024 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2024 | Permit Issued | ISLAND ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/05/2025 | Permit Issued | BELLEROSE PLBG & HTG | Wood |
| 04/16/2024 | — | — | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2024 | Permit Issued | MOMENTUM SOLAR | 23 panels, 9.43 kw, 405 roof_area_sqft |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/30/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 04/23/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/23/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 04/16/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/16/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/08/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/14/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/08/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/04/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/27/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/17/2025 | Structural Stability – Alterations of existing buildings | — | special |
| 07/17/2025 | Concrete - Cast-In-Place | — | special |
| 07/17/2025 | Final | — | progress |
| 07/17/2025 | Footing and Foundation | — | progress |
| 07/17/2025 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | Rajasekhar Sakhamuri | special |
| 07/17/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Ashray Solanki | special |
| 07/17/2025 | Fire-Resistant Penetrations and Joints | Ashray Solanki | special |
| 04/18/2025 | Insulation placement and R values | Ashray Solanki | energy_progress |
| 04/18/2025 | Fire-Resistance Rated Construction | Ashray Solanki | progress |
| 04/18/2025 | Structural Wood Frame | Ashray Solanki | progress |
| 04/18/2025 | Fenestration areas | Ashray Solanki | energy_progress |
| 04/18/2025 | Air barrier - visual inspection | Ashray Solanki | energy_progress |
| 04/18/2025 | Interior lighting power | Ashray Solanki | energy_progress |
| 04/18/2025 | Fenestration and door U-factor and product ratings | Ashray Solanki | energy_progress |
| 04/18/2025 | Fenestration air leakage | Ashray Solanki | energy_progress |
| 04/10/2025 | Subgrade Inspections | Ashray Solanki | special |
| 04/10/2025 | Final | Ashray Solanki | progress |
| 04/10/2025 | Fire-Resistant Penetrations and Joints | Ashray Solanki | special |
| 04/10/2025 | Concrete - Cast-In-Place | Ashray Solanki | special |
| 04/10/2025 | Structural Stability – Alterations of existing buildings | Ashray Solanki | special |
| 06/10/2024 | Final | Mina Makar | progress |
| 06/10/2024 | Air barrier - visual inspection | Mina Makar | energy_progress |
| 06/10/2024 | Fire-Resistant Penetrations and Joints | Mina Makar | special |
| 06/10/2024 | Structural Stability – Alterations of existing buildings | Mina Makar | special |
| 06/10/2024 | Energy Code Compliance Inspections | Mina Makar | progress |