| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/16/2026 | Signed-off | WEXLER PLUMBING LLC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Permit Issued | ELECTRICWORXNY CORP | General Wiring |
| Firm | Filings | Most Recent |
|---|---|---|
| OAMS ARCHITECTURAL DESIGN P.L.L.C. | 5 | 07/16/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| OAMS ARCHITECTURAL DESIGN | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MC FLEMING GROUP INC | General Contractor | 1 | 07/08/2026 |
| WEXLER PLUMBING LLC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| IP CONCRETE TESTING AND I | 6252 | 5 | 07/16/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | METRO KORT P & H LLC | 03/26/2026 |
| DOB NOW | General Construction | Signed-off | MC FLEMING GROUP INC | 08/01/2025 |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/23/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/21/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/21/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 04/17/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/15/2026 | Concrete - Cast-In-Place | INDARDEO PARBHUNATH | special |
| 07/15/2026 | Final | Ozmar Martinez Suarez | progress |
| 07/15/2026 | Air barrier - visual inspection | INDARDEO PARBHUNATH | energy_progress |
| 07/15/2026 | Fenestration areas | INDARDEO PARBHUNATH | energy_progress |
| 07/15/2026 | Fenestration and door U-factor and product ratings | INDARDEO PARBHUNATH | energy_progress |
| 07/15/2026 | Interior lighting power | INDARDEO PARBHUNATH | energy_progress |
| 07/15/2026 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 07/15/2026 | Subgrade Inspections | INDARDEO PARBHUNATH | special |
| 12/16/2025 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 11/25/2025 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 11/25/2025 | Concrete - Cast-In-Place | INDARDEO PARBHUNATH | special |
| 11/25/2025 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 11/25/2025 | Subgrade Inspections | INDARDEO PARBHUNATH | special |
| 11/25/2025 | Final | Ozmar Martinez Suarez | progress |
| 11/25/2025 | Interior lighting power | INDARDEO PARBHUNATH | energy_progress |
| 11/25/2025 | Fenestration areas | INDARDEO PARBHUNATH | energy_progress |
| 11/25/2025 | Fenestration and door U-factor and product ratings | INDARDEO PARBHUNATH | energy_progress |
| 11/25/2025 | Air barrier - visual inspection | INDARDEO PARBHUNATH | energy_progress |