← Back
Two stories - detached, small or mid-size
211-28 90 AVENUE
QUEENS · BIN 4225382
💬 Discuss this project
1925Year Built
2Stories
A1Building Class
R2Zoning
1,690 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 3,800 sf lot · 0.44 FAR built · Flood zone X
Locations of Work
General
Roof1p · 1 filing · 12 docs
1 job · most recent 02/06/2025
FiledStatusContractorScope
02/06/2025CompleteMAK ELECTRICAL CONTR CORP1 meters
Building Lifecycle
All (9)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (5)
03/12/2026
Signed off — Alteration
ROOFTOP SOLAR PANEL INSTALLATION
Q01175930-I1
08/27/2025
Filed — Alteration
ROOFTOP SOLAR PANEL INSTALLATION
Q01175930-P1
04/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
VYACHESLAV NECHAYEV
04/29/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
VYACHESLAV NECHAYEV
04/29/2025
Special inspection requirement — Energy Code Compliance Inspections
VYACHESLAV NECHAYEV
04/29/2025
Special inspection requirement — Final
VYACHESLAV NECHAYEV
04/29/2025
Special inspection requirement — Air barrier - visual inspection
VYACHESLAV NECHAYEV
02/14/2025
Permit issued — Solar
Q01175930-I1-SL
02/07/2025
Filed — Alteration
ROOFTOP SOLAR PANEL INSTALLATION
Q01175930-I1
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ETRECTE LLC208/27/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PATRIOT ENERGY SOLUTIONS CORP403/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ETRECTE LLC8116208/27/2025
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offPATRIOT ENERGY SOL CO02/14/2025
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
04/29/2025Fire-Resistant Penetrations and JointsVYACHESLAV NECHAYEVspecial
04/29/2025Structural Stability – Alterations of existing buildingsVYACHESLAV NECHAYEVspecial
04/29/2025Energy Code Compliance InspectionsVYACHESLAV NECHAYEVprogress
04/29/2025FinalVYACHESLAV NECHAYEVprogress
04/29/2025Air barrier - visual inspectionVYACHESLAV NECHAYEVenergy_progress
▾Documents — 12 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/21/2026Q01175930-P1Request digital key ↗
08/21/2026Q01175930-I1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWProgress Inspector Seal & Signature3
09/01/2026Q01175930-P1Open ↗
09/01/2026Q01175930-P1Open ↗
09/01/2026Q01175930-P1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/21/2026Q01175930-P1Open ↗
08/21/2026Q01175930-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026Q01175930-P1Open ↗
09/01/2026Q01175930-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/21/2026Q01175930-P1Open ↗
08/21/2026Q01175930-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01175930-I1Open ↗