| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/15/2026 | Complete | CUNNINGHAM ELECTRIC CORP | General Wiring |
| 06/26/2026 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| 08/21/2023 | Permit Issued | ALL WAYS ELECTRIC CORP.W | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/26/2026 | Signed-off | SUNRUN INSTALLATION SVC | 17 panels, 7.65 kw, 357.39 roof_area_sqft |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/14/2014 | $413K | — | Private party → Private party | $369/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 1 | 06/26/2026 |
| NMI ARCHITECTURE, PLLC | 2 | 03/12/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| NMI ARCHITECTURE PLLC | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ALL WAYS ELECTRIC CORP.W | Electrical | 1 | 03/22/2026 |
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 07/08/2026 |
| THEORY 3 GROUP INC | General Contractor | 1 | 07/08/2026 |
| ALL PRO PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 1 | 06/26/2026 |
| NMI ARCHITECTURE, PLLC | 6825 | 1 | 12/28/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 07/06/2026 |
| DOB NOW | Plumbing | Signed-off | ALL PRO PLBG & HTG INC | 04/19/2024 |
| DOB NOW | General Construction | Signed-off | THEORY 3 GROUP INC | 01/23/2024 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/26/2026 | Air barrier - visual inspection | Walid Abdulla | energy_progress |
| 06/26/2026 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 06/25/2026 | Final | Walid Abdulla | progress |
| 06/25/2026 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 06/25/2026 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 12/07/2023 | Fenestration and door U-factor and product ratings | NASHAT IBRAHIM | energy_progress |
| 12/07/2023 | Fenestration air leakage | NASHAT IBRAHIM | energy_progress |
| 12/07/2023 | Fenestration areas | NASHAT IBRAHIM | energy_progress |
| 12/07/2023 | Fire-Resistant Penetrations and Joints | NASHAT IBRAHIM | special |
| 12/07/2023 | Energy Code Compliance Inspections | NASHAT IBRAHIM | progress |
| 12/07/2023 | Fire-Resistance Rated Construction | NASHAT IBRAHIM | progress |
| 12/07/2023 | Insulation placement and R values | NASHAT IBRAHIM | energy_progress |