Locations of Work
ArchitectureStructuralPlumbingGeneral
Roof20p · 1 filing · 20 docs
Floor 219p · 1 filing · 20 docs
Floor 121p · 1 filing · 20 docs
Basement1p · 1 filing · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
LASM1507/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/18/2023$612K—Private party → Private party$331/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
DEMERARA ENGINEERING, PLLC603/30/2026
PARKER AND WEST ENGINEERING, PLLC107/15/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CDEM803/21/2026
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
K.W.MCINTOSH CONSTRUCTIONGeneral Contractor1007/08/2026
SUNRUN INSTALLATION SVCGeneral Contractor203/21/2026
C.R.P PLUMBING & HTG INCPlumbing207/08/2026
INFINITI ELECTRIC CORPElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DEMERARA ENGINEERING, PLL4248203/30/2026
PARKER AND WEST ENGINEERI5272107/15/2025
Building Lifecycle
All (64)Filed (7)Permit Issued (6)Signed Off (1)Inspection (4)Objection (16)Special Inspection (30)
07/30/2026
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
07/20/2026
Special inspection requirement — Final
Oscar Walters Jr
07/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Oscar Walters Jr
07/20/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Oscar Walters Jr
07/20/2026
Special inspection requirement — Structural Cold-Formed Steel
Oscar Walters Jr
07/20/2026
Special inspection requirement — Wood – Prefabricated I-Joists
Oscar Walters Jr
07/20/2026
Special inspection requirement — Structural Steel - Details
Oscar Walters Jr
07/20/2026
Special inspection requirement — Structural Steel - High Strength Bolting
Oscar Walters Jr
07/20/2026
Special inspection requirement — Structural Wood Frame
Oscar Walters Jr
07/20/2026
Special inspection requirement — Fenestration air leakage
Oscar Walters Jr
07/20/2026
Special inspection requirement — Lighting controls
Oscar Walters Jr
07/20/2026
Special inspection requirement — Permanent certificate
Oscar Walters Jr
07/20/2026
Special inspection requirement — Interior lighting power
Oscar Walters Jr
07/20/2026
Special inspection requirement — Protection of exposed foundation insulation
Oscar Walters Jr
07/20/2026
Special inspection requirement — Maintenance information
Oscar Walters Jr
07/20/2026
Special inspection requirement — Air barrier continuity plan testing
Oscar Walters Jr
07/20/2026
Special inspection requirement — Lighting in dwelling units
Oscar Walters Jr
07/20/2026
Special inspection requirement — Insulation placement and R values
Oscar Walters Jr
07/20/2026
Special inspection requirement — Electric vehicle service equipment requirements
Oscar Walters Jr
07/20/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Oscar Walters Jr
07/20/2026
Special inspection requirement — Air barrier - visual inspection
Oscar Walters Jr
07/20/2026
Special inspection requirement — Metering
Oscar Walters Jr
07/20/2026
Special inspection requirement — Fenestration areas
Oscar Walters Jr
07/01/2026
Special inspection requirement — Interior lighting power
Oscar Walters Jr
07/01/2026
Special inspection requirement — Maintenance information
Oscar Walters Jr
06/29/2026
Special inspection requirement — Electric vehicle service equipment requirements
Oscar Walters Jr
06/29/2026
Special inspection requirement — Air barrier continuity plan testing
Oscar Walters Jr
06/29/2026
Special inspection requirement — Air barrier - visual inspection
Oscar Walters Jr
06/29/2026
Special inspection requirement — Metering
Oscar Walters Jr
06/29/2026
Special inspection requirement — Permanent certificate
Oscar Walters Jr
06/29/2026
Special inspection requirement — Protection of exposed foundation insulation
Oscar Walters Jr
03/30/2026
Filed — Alteration CO
Plumbing work in conjunction with vertical Enlargement of 1 Single Family Home
Q00975584-P3
12/16/2025
Signed off — Alteration
Construction Fence around site
Q00949360-I1
10/15/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/25/2025
Filed — Alteration CO
Plumbing work in conjunction with vertical Enlargement of 1 Single Family Home
Q00975584-P2
08/25/2025
Permit issued — Plumbing
Q00975584-S1-PL
08/22/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/11/2025
Permit issued — General Construction
Q00975584-I1-GC-CX
07/17/2025
Permit issued — Solar
Q01255440-I1-SL
07/15/2025
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01255440-I1
12/26/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/08/2024
Filed — Alteration CO
Plumbing work in conjunction with vertical Enlargement of 1 Single Family Home
Q00975584-P1
10/31/2024
Permit issued — Construction Fence
Q00949360-I1-FN
08/21/2024
Permit issued — Plumbing
Q00975584-S1-PL
08/06/2024
Filed — Alteration CO
Plumbing work in conjunction with vertical Enlargement of 1 Single Family Home
Q00975584-S1
04/25/2024
Permit issued — Structural
Q00975584-I1-GC-CX
04/17/2024
Objection resolved — Addressed
04/16/2024
Objection resolved — Addressed
04/10/2024
Objection resolved — Addressed
04/04/2024
Objection raised — Zoning
04/04/2024
Objection resolved — Addressed
02/26/2024
Objection resolved — Addressed
01/31/2024
Objection resolved — Addressed
01/31/2024
Objection resolved — Addressed
01/31/2024
Objection resolved — Addressed
01/11/2024
Objection raised — Admin
01/11/2024
Objection raised — Structural
01/11/2024
Objection raised — Zoning
01/11/2024
Objection raised — Inspections
01/11/2024
Objection raised — Zoning
Latest 60 of 64 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedC.R.P PLUMBING & HTG INC08/25/2025
DOB NOWGeneral ConstructionPermit IssuedK.W.MCINTOSH CONSTRUCTION08/11/2025
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC07/17/2025
DOB NOWConstruction FenceSigned-offK.W.MCINTOSH CONSTRUCTION10/31/2024
DOB NOWPlumbingPermit IssuedC.R.P PLUMBING & HTG INC08/21/2024
DOB NOWStructuralPermit IssuedK.W.MCINTOSH CONSTRUCTION04/25/2024
1 project · most recent 03/30/2026
Gas Water/Sanitary
FiledStatusContractorScope
03/30/2026Permit IssuedC.R.P PLUMBING & HTG INCGas, Water/Sanitary
2 projects · most recent 07/15/2025
General Wiring
FiledStatusContractorScope
07/15/2025CompleteSUNRUN SOLAR ELECTL CORP—
09/15/2024CompleteINFINITI ELECTRIC CORPGeneral Wiring
1 project · most recent 03/30/2026
Wood
FiledStatusContractorScope
03/30/2026Permit IssuedC.R.P PLUMBING & HTG INCWood
1 project · most recent 07/15/2025
FiledStatusContractorScope
07/15/2025Signed-offSUNRUN INSTALLATION SVC19 panels, 7.69 kw, 399.43 roof_area_sqft
1 project · most recent 03/30/2026
Fence
FiledStatusContractorScope
03/30/2026Permit IssuedC.R.P PLUMBING & HTG INCFence
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
07/30/2026Fail-Final CND-Occupancy InspectionFailView ↗
10/15/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/22/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/26/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 49
DateRequirementInspectorRole
07/20/2026FinalOscar Walters Jrprogress
07/20/2026Fire-Resistant Penetrations and JointsOscar Walters Jrspecial
07/20/2026Structural Stability – Alterations of existing buildingsOscar Walters Jrspecial
07/20/2026Structural Cold-Formed SteelOscar Walters Jrspecial
07/20/2026Wood – Prefabricated I-JoistsOscar Walters Jrspecial
07/20/2026Structural Steel - DetailsOscar Walters Jrspecial
07/20/2026Structural Steel - High Strength BoltingOscar Walters Jrspecial
07/20/2026Structural Wood FrameOscar Walters Jrprogress
07/20/2026Fenestration air leakageOscar Walters Jrenergy_progress
07/20/2026Lighting controlsOscar Walters Jrenergy_progress
07/20/2026Permanent certificateOscar Walters Jrenergy_progress
07/20/2026Interior lighting powerOscar Walters Jrenergy_progress
07/20/2026Protection of exposed foundation insulationOscar Walters Jrenergy_progress
07/20/2026Maintenance informationOscar Walters Jrenergy_progress
07/20/2026Air barrier continuity plan testingOscar Walters Jrenergy_progress
07/20/2026Lighting in dwelling unitsOscar Walters Jrenergy_progress
07/20/2026Insulation placement and R valuesOscar Walters Jrenergy_progress
07/20/2026Electric vehicle service equipment requirementsOscar Walters Jrenergy_progress
07/20/2026Fenestration and door U-factor and product ratingsOscar Walters Jrenergy_progress
07/20/2026Air barrier - visual inspectionOscar Walters Jrenergy_progress
07/20/2026MeteringOscar Walters Jrenergy_progress
07/20/2026Fenestration areasOscar Walters Jrenergy_progress
07/01/2026Interior lighting powerOscar Walters Jrenergy_progress
07/01/2026Maintenance informationOscar Walters Jrenergy_progress
06/29/2026Electric vehicle service equipment requirementsOscar Walters Jrenergy_progress
Latest 25 of 49.
▾Documents — 48 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/24/2026Q00949360-I1Request digital key ↗
08/19/2026Q01255440-I1Request digital key ↗
08/17/2026Q00975584-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸Zoning, Tax Lot & Property Records7
▸DOB NOWRestrictive Declaration/Easement 15
08/13/2026Q00975584-P3Open ↗
08/13/2026Q00975584-S1Open ↗
08/13/2026Q00975584-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026Q00975584-P3Open ↗
08/13/2026Q00975584-I1Open ↗
▸Seals & Professional Certifications18
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/24/2026Q00949360-I1Open ↗
08/19/2026Q01255440-I1Open ↗
08/17/2026Q00975584-P3Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
08/26/2026Q00975584-I1Open ↗
08/26/2026Q00975584-I1Open ↗
08/25/2026Q01255440-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/26/2026Q00975584-I1Open ↗
08/25/2026Q01255440-I1Open ↗
08/25/2026Q01255440-I1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/19/2026Q01255440-I1Open ↗
08/17/2026Q00975584-P3Open ↗
08/17/2026Q00975584-P2Open ↗
Showing 3 of 6 on file for this type
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01255440-I1Open ↗
▸Other Documents9
▸DOB NOWPlot Diagram2
08/13/2026Q00975584-P3Open ↗
08/13/2026Q00975584-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/17/2026Q00975584-I1Open ↗
08/17/2026Q00975584-P3Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026Q00975584-P3Open ↗
08/13/2026Q00975584-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026Q00975584-P3Open ↗
08/13/2026Q00975584-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026Q00975584-I1Open ↗