| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2026 | Signed-off | TRI CITY MECHANICAL GROUP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/02/2019 | Complete | BREEN ELEC'L CONTR'S INC | 1 meters |
| Firm | Filings | Most Recent |
|---|---|---|
| ASKON ARCHITECTS, P.C. | 4 | 07/02/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SFFTS INC | General Contractor | 3 | 03/21/2026 |
| PM MECHANICAL GROUP CORP | General Contractor | 1 | 07/08/2026 |
| TRI CITY MECHANICAL GROUP CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ASKON ARCHITECT, P.C. | 3596 | 4 | 07/02/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | PM MECHANICAL GROUP CORP | 04/17/2026 |
| DOB NOW | Plumbing | Signed-off | FLAVIO MECHANICAL CORP | 05/09/2025 |
| DOB NOW | General Construction | Permit Issued | SFFTS INC | 08/12/2024 |
| BIS | OT | ISSUED | TOM PETERSEN ARCHITECT, LLC | 08/12/2015 |
| BIS | OT | ISSUED | TOM PETERSEN ARCHITECT, LLC | 05/01/2015 |
| BIS | EQ | ISSUED | SCHERILLO & SONS CONSTRUCTION | 06/09/2010 |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/14/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/18/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/16/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/11/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/24/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 09/27/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/13/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/14/2026 | Fire-Resistant Penetrations and Joints | Akeeb Shekoni | special |
| 08/14/2026 | Energy Code Compliance Inspections | Akeeb Shekoni | progress |
| 08/14/2026 | Fire-Resistance Rated Construction | Akeeb Shekoni | progress |
| 08/14/2026 | Fenestration air leakage | Akeeb Shekoni | energy_progress |
| 08/14/2026 | Fenestration areas | Akeeb Shekoni | energy_progress |
| 08/14/2026 | Interior lighting power | Akeeb Shekoni | energy_progress |
| 08/14/2026 | Air barrier - visual inspection | Akeeb Shekoni | energy_progress |
| 08/14/2026 | Fenestration and door U-factor and product ratings | Akeeb Shekoni | energy_progress |
| 07/02/2026 | Fenestration areas | Akeeb Shekoni | energy_progress |
| 07/02/2026 | Fire-Resistant Penetrations and Joints | Akeeb Shekoni | special |
| 07/02/2026 | Energy Code Compliance Inspections | Akeeb Shekoni | progress |
| 07/02/2026 | Fire-Resistance Rated Construction | Akeeb Shekoni | progress |
| 07/02/2026 | Fenestration air leakage | Akeeb Shekoni | energy_progress |
| 07/02/2026 | Interior lighting power | Akeeb Shekoni | energy_progress |
| 07/02/2026 | Fenestration and door U-factor and product ratings | Akeeb Shekoni | energy_progress |
| 07/02/2026 | Air barrier - visual inspection | Akeeb Shekoni | energy_progress |
| 08/06/2025 | Fire-Resistant Penetrations and Joints | Akeeb Shekoni | special |