← Back
Two stories - detached, small or mid-size
156-01 110 AVENUE
QUEENS · BIN 4263324
💬 Discuss this project
1925Year Built
2.5Stories
A1Building Class
R4AZoning
1,622 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 2,500 sf lot · 0.65 FAR built · Flood zone X
Locations of Work
Electrical
Permit Issued — active, not yet Signed-off
RoofUnder Construction1 filing · 8 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC108/17/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRINITY SOLAR LLCGeneral Contractor108/20/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BITOPI CONSULTANTS LLC7036108/17/2026
Building Lifecycle
All (7)Filed (1)Permit Issued (1)Special Inspection (5)
08/19/2026
Permit issued — Solar
Q01444047-I1-SL
08/17/2026
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01444047-I1
08/11/2026
Special inspection requirement — Structural Steel - Details
KAMRUL AHSAN
08/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
08/11/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
08/11/2026
Special inspection requirement — Final
Ayracon Almaraz
08/11/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedTRINITY SOLAR LLC08/19/2026
1 project · most recent 08/10/2026
FiledStatusContractorScope
08/10/2026Permit IssuedREDLINE ELECTRIC INC—
1 project · most recent 08/17/2026
FiledStatusContractorScope
08/17/2026Permit IssuedTRINITY SOLAR LLC30 panels, 12.3 kw, 980 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
08/11/2026Structural Steel - DetailsKAMRUL AHSANspecial
08/11/2026Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
08/11/2026Energy Code Compliance InspectionsAyracon Almarazprogress
08/11/2026FinalAyracon Almarazprogress
08/11/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/18/2026Q01444047-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
09/01/2026Q01444047-I1Open ↗
09/01/2026Q01444047-I1Open ↗
09/01/2026Q01444047-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026Q01444047-I1Open ↗
09/01/2026Q01444047-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/18/2026Q01444047-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/18/2026Q01444047-I1Open ↗