← Back
Two family converted from one family
156-04 132 AVENUE
QUEENS · BIN 4266256
💬 Discuss this project
1950Year Built
2Stories
B3Building Class
R3XZoning
2,400 sfGross Floor Area
2Units
Two family converted from one family · 4,000 sf lot · 0.6 FAR built · Flood zone X
Locations of Work
ArchitectureGeneral
Roof2p · 1 filing · 15 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ETRECTE LLC206/19/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PATRIOT ENERGY SOLUTIONS CORP403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PATRIOT ENERGY SOL COGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ETRECTE LLC8116206/19/2025
Building Lifecycle
All (14)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (10)
03/13/2026
Signed off — Alteration
ROOFTOP SOLAR PANEL INSTALLATION
Q01151399-I1
06/20/2025
Special inspection requirement — Air barrier - visual inspection
VYACHESLAV NECHAYEV
06/20/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
VYACHESLAV NECHAYEV
06/20/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
VYACHESLAV NECHAYEV
06/20/2025
Special inspection requirement — Energy Code Compliance Inspections
VYACHESLAV NECHAYEV
06/20/2025
Special inspection requirement — Final
VYACHESLAV NECHAYEV
06/19/2025
Filed — Alteration
ROOFTOP SOLAR PANEL INSTALLATION
Q01151399-P1
03/21/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
VYACHESLAV NECHAYEV
03/21/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
VYACHESLAV NECHAYEV
03/21/2025
Special inspection requirement — Energy Code Compliance Inspections
VYACHESLAV NECHAYEV
03/21/2025
Special inspection requirement — Final
VYACHESLAV NECHAYEV
03/21/2025
Special inspection requirement — Air barrier - visual inspection
VYACHESLAV NECHAYEV
12/17/2024
Permit issued — Solar
Q01151399-I1-SL
12/13/2024
Filed — Alteration
ROOFTOP SOLAR PANEL INSTALLATION
Q01151399-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offPATRIOT ENERGY SOL CO12/17/2024
BISPLISSUEDWAGNER ZIV PLUMBING02/01/2007
BISEQISSUEDUNIVERSAL CONTRUCT & BUILD INC01/25/2007
BIS—ISSUEDUNIVERSAL CONTRUCT & BUILD INC01/25/2007
1 project · most recent 12/01/2024
FiledStatusContractorScope
12/01/2024CompleteMAK ELECTRICAL CONTR CORP2 meters
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
06/20/2025Air barrier - visual inspectionVYACHESLAV NECHAYEVenergy_progress
06/20/2025Structural Stability – Alterations of existing buildingsVYACHESLAV NECHAYEVspecial
06/20/2025Fire-Resistant Penetrations and JointsVYACHESLAV NECHAYEVspecial
06/20/2025Energy Code Compliance InspectionsVYACHESLAV NECHAYEVprogress
06/20/2025FinalVYACHESLAV NECHAYEVprogress
03/21/2025Fire-Resistant Penetrations and JointsVYACHESLAV NECHAYEVspecial
03/21/2025Structural Stability – Alterations of existing buildingsVYACHESLAV NECHAYEVspecial
03/21/2025Energy Code Compliance InspectionsVYACHESLAV NECHAYEVprogress
03/21/2025FinalVYACHESLAV NECHAYEVprogress
03/21/2025Air barrier - visual inspectionVYACHESLAV NECHAYEVenergy_progress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/19/2026Q01151399-I1Request digital key ↗
08/19/2026Q01151399-P1Request digital key ↗
▸Seals & Professional Certifications12
▸DOB NOWProgress Inspector Seal & Signature6
09/01/2026Q01151399-I1Open ↗
09/01/2026Q01151399-I1Open ↗
09/01/2026Q01151399-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/01/2026Q01151399-I1Open ↗
09/01/2026Q01151399-I1Open ↗
08/23/2026Q01151399-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/19/2026Q01151399-I1Open ↗
08/13/2026Q01151399-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01151399-I1Open ↗