← Back
Two stories - detached, small or mid-size
174-15 137 AVENUE
QUEENS · BIN 4270611
💬 Discuss this project
1920Year Built
2Stories
A1Building Class
R3AZoning
1,332 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 3,424 sf lot · 0.39 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC203/01/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACA ASSOCIATES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRINITY SOLAR LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
IKRA CONSULTING LLC7032203/01/2026
Building Lifecycle
All (8)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (4)
03/06/2026
Signed off — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01254374-I1
03/03/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
MD MOSTAFA
03/03/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
03/03/2026
Special inspection requirement — Final
Ayracon Almaraz
03/03/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
03/01/2026
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01254374-P1
07/17/2025
Permit issued — Solar
Q01254374-I1-SL
07/11/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01254374-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTRINITY SOLAR LLC07/17/2025
1 project · most recent 07/08/2025
FiledStatusContractorScope
07/08/2025CompleteREDLINE ELECTRIC INC—
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
03/03/2026Fire-Resistant Penetrations and JointsMD MOSTAFAspecial
03/03/2026Energy Code Compliance InspectionsAyracon Almarazprogress
03/03/2026FinalAyracon Almarazprogress
03/03/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/19/2026Q01254374-P1Request digital key ↗
08/19/2026Q01254374-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/29/2026Q01254374-I1Open ↗
08/29/2026Q01254374-I1Open ↗
08/29/2026Q01254374-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026Q01254374-I1Open ↗
08/13/2026Q01254374-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/29/2026Q01254374-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026Q01254374-P1Open ↗
08/13/2026Q01254374-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01254374-I1Open ↗