| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/27/2025 | Permit Issued | ANGELITO CONSTRUCTION INC | Ventilation Systems | Ventilation Maxlite Model#: MLFPDE1030S-V1 75 CFM · Exhaust Fan ×3 General Electric Model#: JVM3160RF9SS 110 CFM · Kitchen Exhaust ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/24/2024 | Complete | KJK ELECTRIC INC | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| ANGELITO CONSTRUCTION | 29 | 04/09/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/19/2023 | $640K | — | Private party → Private party | $515/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| OAMS ARCHITECTURAL DESIGN P.L.L.C. | 8 | 05/27/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| OAMS ARCHITECTURAL DESIGN | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ANGELITO CONSTRUCTION INC | General Contractor | 5 | 04/09/2026 |
| TRI STATE PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| IP CONCRETE TESTING AND I | 6252 | 7 | 05/27/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | ANGELITO CONSTRUCTION | 06/17/2025 |
| DOB NOW | General Construction | Permit Issued | ANGELITO CONSTRUCTION | 03/21/2025 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 09/24/2024 |
| DOB NOW | Structural | Permit Issued | ANGELITO CONSTRUCTION | 08/23/2024 |
| DOB NOW | General Construction | Permit Issued | ANGELITO CONSTRUCTION | 08/08/2024 |
| DOB NOW | Construction Fence | Signed-off | ANGELITO CONSTRUCTION | 05/09/2024 |
| BIS | PL | ISSUED | TEAL PLG CORP | 08/30/1993 |
| BIS | — | ISSUED | GOLDEN CITY DEVELOPMENT CORP | 06/14/1993 |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/17/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/22/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/11/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 02/26/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 11/22/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 11/22/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 11/22/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/30/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/30/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/30/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/20/2025 | Subsurface Investigations (Borings/Test Pits) | DAVID WASHINGTON | special |
| 08/20/2025 | Permanent certificate | INDARDEO PARBHUNATH | energy_progress |
| 08/20/2025 | Structural Wood Frame | INDARDEO PARBHUNATH | progress |
| 08/20/2025 | Footing and Foundation | INDARDEO PARBHUNATH | progress |
| 08/20/2025 | Fire-Resistance Rated Construction | INDARDEO PARBHUNATH | progress |
| 08/20/2025 | Energy Code Compliance Inspections | INDARDEO PARBHUNATH | progress |
| 08/20/2025 | Final | NAVEEN KUMAR | progress |
| 08/20/2025 | Concrete - Cast-In-Place | INDARDEO PARBHUNATH | special |
| 08/20/2025 | Subgrade Inspections | INDARDEO PARBHUNATH | special |
| 08/20/2025 | Structural Stability – Alterations of existing buildings | INDARDEO PARBHUNATH | special |
| 08/20/2025 | Fenestration areas | INDARDEO PARBHUNATH | energy_progress |
| 08/20/2025 | Metering | INDARDEO PARBHUNATH | energy_progress |
| 08/20/2025 | Protection of exposed foundation insulation | INDARDEO PARBHUNATH | energy_progress |
| 08/20/2025 | Electric vehicle service equipment requirements | INDARDEO PARBHUNATH | energy_progress |
| 08/20/2025 | Fenestration air leakage | INDARDEO PARBHUNATH | energy_progress |
| 08/20/2025 | Fenestration and door U-factor and product ratings | INDARDEO PARBHUNATH | energy_progress |
| 08/20/2025 | Air barrier - visual inspection | INDARDEO PARBHUNATH | energy_progress |
| 08/20/2025 | Insulation placement and R values | INDARDEO PARBHUNATH | energy_progress |
| 08/20/2025 | Interior lighting power | INDARDEO PARBHUNATH | energy_progress |
| 03/20/2025 | HVAC-R and service water heating system controls | — | energy_progress |
| 03/20/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 03/20/2025 | HVAC-R and service water heating equipment | — | energy_progress |
| 11/15/2024 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 11/15/2024 | HVAC-R and service water piping design and insulation | INDARDEO PARBHUNATH | energy_progress |
| 11/15/2024 | HVAC-R and service water heating equipment | INDARDEO PARBHUNATH | energy_progress |