| Firm | Filings | Most Recent |
|---|---|---|
| KENNY LEE ARCHITECT | 6 | 08/06/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| KORMAN DESIGN & BUILD | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BLACK HAMMER CONSTRUCTION | General Contractor | 2 | 06/17/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| IP CONCRETE TESTING AND I | 6252 | 4 | 08/06/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | BLACK HAMMER CONSTRUCTION | 06/15/2026 |
| DOB NOW | Construction Fence | Permit Issued | BLACK HAMMER CONSTRUCTION | 05/27/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/06/2026 | — | — | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/06/2026 | Permit Issued | BLACK HAMMER CONSTRUCTION | Steel, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/06/2026 | Permit Issued | BLACK HAMMER CONSTRUCTION | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/08/2026 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 07/08/2026 | HVAC-R and service water heating system controls | INDARDEO PARBHUNATH | energy_progress |
| 07/08/2026 | HVAC-R and service water piping design and insulation | INDARDEO PARBHUNATH | energy_progress |
| 07/08/2026 | HVAC-R and service water heating equipment | INDARDEO PARBHUNATH | energy_progress |
| 07/08/2026 | Energy Code Compliance Inspections | INDARDEO PARBHUNATH | progress |
| 07/08/2026 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | — | special |
| 07/08/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | INDARDEO PARBHUNATH | special |
| 06/15/2026 | Structural Wood Frame | INDARDEO PARBHUNATH | progress |
| 06/15/2026 | Concrete - Cast-In-Place | INDARDEO PARBHUNATH | special |
| 06/15/2026 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 06/15/2026 | Masonry | INDARDEO PARBHUNATH | special |
| 06/15/2026 | Structural Stability – Alterations of existing buildings | INDARDEO PARBHUNATH | special |
| 06/15/2026 | Structural Steel - Details | INDARDEO PARBHUNATH | special |
| 06/15/2026 | Energy Code Compliance Inspections | INDARDEO PARBHUNATH | progress |
| 06/15/2026 | Final | NAVEEN KUMAR | progress |
| 06/15/2026 | Footing and Foundation | INDARDEO PARBHUNATH | progress |
| 06/15/2026 | Air barrier — testing | INDARDEO PARBHUNATH | energy_progress |
| 06/15/2026 | Fenestration air leakage | INDARDEO PARBHUNATH | energy_progress |
| 06/15/2026 | Permanent certificate | INDARDEO PARBHUNATH | energy_progress |
| 06/15/2026 | Fenestration and door U-factor and product ratings | INDARDEO PARBHUNATH | energy_progress |
| 06/15/2026 | Air barrier - visual inspection | INDARDEO PARBHUNATH | energy_progress |
| 06/15/2026 | Electric vehicle service equipment requirements | INDARDEO PARBHUNATH | energy_progress |
| 06/15/2026 | Insulation placement and R values | INDARDEO PARBHUNATH | energy_progress |
| 06/15/2026 | Interior lighting power | INDARDEO PARBHUNATH | energy_progress |
| 06/15/2026 | Fenestration areas | INDARDEO PARBHUNATH | energy_progress |