| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/01/2025 | Permit Issued | STRUCTURELINE INC | Heating and Air Conditioning Systems, Heating Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric MSZ-EF-09NA 9,000 BTU · Split System ×5 MSZ-EF-18NA 18,000 BTU · Split System ×2 MXZ-4C36NA2 36,000 BTU · Heat Pump Outdoor ×2 Heating Markel E3321TD-RP 2,560 BTU · Electric Heater ×1 Ventilation Air King FRAK-505 50 CFM · Exhaust Fan ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/01/2025 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/01/2025 | Permit Issued | STRUCTURELINE INC | Concrete, Wood |
| Firm | Filings | Most Recent |
|---|---|---|
| DAMORE STUDIO | 3 | 08/01/2025 |
| ACV DESIGN LTD | 2 | 09/06/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| W J PROFESSIONAL EXPEDITING COMPANY | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| STRUCTURELINE INC | General Contractor | 3 | 09/07/2026 |
| BEST DEMO INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ACV DESIGN LTD | 3864 | 1 | 09/06/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | STRUCTURELINE INC | 09/03/2026 |
| DOB NOW | General Construction | Permit Issued | STRUCTURELINE INC | 09/03/2026 |
| DOB NOW | Structural | Permit Issued | STRUCTURELINE INC | 09/03/2026 |
| DOB NOW | Construction Fence | Permit Issued | BEST DEMO INC | 12/01/2021 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/04/2025 | Energy Code Compliance Inspections | — | progress |
| 05/09/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 05/09/2025 | Maintenance information | — | energy_progress |
| 05/09/2025 | Energy Code Compliance Inspections | — | progress |
| 05/09/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 05/09/2025 | HVAC-R and service water heating equipment | — | energy_progress |
| 05/09/2025 | HVAC-R and service water heating system controls | — | energy_progress |
| 02/18/2025 | Final | — | progress |
| 02/18/2025 | Mechanical Systems | — | special |
| 09/24/2024 | Maintenance information | — | energy_progress |
| 09/24/2024 | Permanent certificate | — | energy_progress |
| 09/24/2024 | Protection of exposed foundation insulation | — | energy_progress |
| 09/24/2024 | Air barrier — testing | — | energy_progress |
| 09/24/2024 | Electric vehicle service equipment requirements | — | energy_progress |
| 09/24/2024 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 08/15/2024 | Metering | — | energy_progress |
| 08/15/2024 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 08/15/2024 | Lighting controls | — | energy_progress |
| 08/15/2024 | Exterior lighting power | — | energy_progress |
| 08/15/2024 | Fenestration areas | — | energy_progress |
| 08/15/2024 | Fenestration air leakage | — | energy_progress |
| 08/15/2024 | Lighting in dwelling units | — | energy_progress |
| 08/15/2024 | Insulation placement and R values | — | energy_progress |
| 08/15/2024 | Air barrier - visual inspection | — | energy_progress |
| 08/15/2024 | Interior lighting power | — | energy_progress |