| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2026 | Permit Issued | RONEY ELECTRIC INC | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| BH26 HOLDINGS | 3 | 09/13/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BANJI AWOSIKA ARCHITECT P.C. | 2 | 05/07/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| YAFE MEOD CORP | General Contractor | 2 | 08/14/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BANJI AWOSIKA ARCHITECT P | 2721 | 1 | 04/01/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | YAFE MEOD CORP | 08/13/2026 |
| DOB NOW | Construction Fence | Permit Issued | YAFE MEOD CORP | 05/12/2026 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/09/2026 | Structural Stability – Alterations of existing buildings | OLABANJI AWOSIKA | special |
| 04/07/2026 | Duct leakage testing, insulation and design | OLABANJI AWOSIKA | energy_progress |
| 03/31/2026 | Concrete - Cast-In-Place | OLABANJI AWOSIKA | special |
| 03/31/2026 | Excavations - Sheeting, Shoring, and Bracing | OLABANJI AWOSIKA | special |
| 03/31/2026 | Fire-Resistant Penetrations and Joints | OLABANJI AWOSIKA | special |
| 03/31/2026 | Heating Systems | OLABANJI AWOSIKA | special |
| 03/31/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | OLABANJI AWOSIKA | special |
| 03/31/2026 | Subgrade Inspections | OLABANJI AWOSIKA | special |
| 03/31/2026 | Final | OLABANJI AWOSIKA | progress |
| 03/31/2026 | Footing and Foundation | OLABANJI AWOSIKA | progress |
| 03/31/2026 | Energy Code Compliance Inspections | OLABANJI AWOSIKA | progress |
| 03/31/2026 | Fire-Resistance Rated Construction | OLABANJI AWOSIKA | progress |
| 03/31/2026 | Structural Wood Frame | OLABANJI AWOSIKA | progress |
| 03/31/2026 | Ventilation and air distribution system | OLABANJI AWOSIKA | energy_progress |
| 03/31/2026 | Fenestration areas | OLABANJI AWOSIKA | energy_progress |
| 03/31/2026 | Insulation placement and R values | OLABANJI AWOSIKA | energy_progress |
| 03/31/2026 | Air barrier - visual inspection | OLABANJI AWOSIKA | energy_progress |
| 03/31/2026 | Air barrier — testing | OLABANJI AWOSIKA | energy_progress |
| 03/31/2026 | HVAC-R and service water heating equipment | OLABANJI AWOSIKA | energy_progress |
| 03/31/2026 | Fenestration air leakage | OLABANJI AWOSIKA | energy_progress |
| 03/31/2026 | Metering | OLABANJI AWOSIKA | energy_progress |
| 03/31/2026 | Fenestration and door U-factor and product ratings | OLABANJI AWOSIKA | energy_progress |
| 03/31/2026 | Interior lighting power | OLABANJI AWOSIKA | energy_progress |
| 03/31/2026 | Permanent certificate | OLABANJI AWOSIKA | energy_progress |
| 03/31/2026 | Maintenance information | OLABANJI AWOSIKA | energy_progress |