Two stories - detached, small or mid-size
259-03 149 ROAD
QUEENS · BIN 4291128
💬 Discuss this project
1960Year Built
2Stories
A1Building Class
R3XZoning
1,666 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 3,800 sf lot · 0.44 FAR built · Flood zone X500
Locations of Work
Architecture
Floor 11p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SQUARE ARCH, LLC107/22/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUSTAINABLE STRATEGIESGeneral Contractor104/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SQ. ARCH, LLC4802107/22/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
09/29/2025
Signed off — Alteration
INSTALLATION OF SOLAR ELECTRIC GENERATION SYSTEM FOR UTILITY INTERCONNECTION
Q01259626-I1
07/22/2025
Filed — Alteration
INSTALLATION OF SOLAR ELECTRIC GENERATION SYSTEM FOR UTILITY INTERCONNECTION
Q01259626-I1
07/22/2025
Permit issued — Solar
Q01259626-I1-SL
07/22/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Chun Feng
07/22/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Chun Feng
07/22/2025
Special inspection requirement — Energy Code Compliance Inspections
Chun Feng
07/22/2025
Special inspection requirement — Final
Chun Feng
07/22/2025
Special inspection requirement — Air barrier - visual inspection
Chun Feng
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUSTAINABLE STRATEGIES07/22/2025
1 project · most recent 07/14/2025
FiledStatusContractorScope
07/14/2025CompleteSOURCE ELECTRIC INC1 meters
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
07/22/2025Fire-Resistant Penetrations and JointsChun Fengspecial
07/22/2025Structural Stability – Alterations of existing buildingsChun Fengspecial
07/22/2025Energy Code Compliance InspectionsChun Fengprogress
07/22/2025FinalChun Fengprogress
07/22/2025Air barrier - visual inspectionChun Fengenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/19/2026Q01259626-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/27/2026Q01259626-I1Open ↗
08/27/2026Q01259626-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/19/2026Q01259626-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/27/2026Q01259626-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/19/2026Q01259626-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01259626-I1Open ↗