| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/04/2022 | Permit Issued | PMZ CONSTRUCTION CORP | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric PVFY-P54NAMU-E1 54,000 BTU · Vrf Indoor ×5 PKFY-P12NLMU-E 12,000 BTU · Vrf Indoor ×3 PUMY-P60NKMU3(-BS) 60,000 BTU · Vrf Outdoor ×3 PKFY-P08NLMU-E 8,000 BTU · Vrf Indoor ×1 PUMY-P36NKMU3(-BS) 36,000 BTU · Vrf Outdoor ×1 PUMY-P48NKMU3(-BS) 48,000 BTU · Vrf Outdoor ×1 Runtal UF-4 930 BTU · Radiant ×1 Warmly Yours TEMP ZONE FLEX ROLLS 15 kW · Radiant ×1 Ventilation Ccb Innovations RMAS12 1 BTU · Makeup Air ×1 Greenheck SP-B90 50 CFM · Exhaust Fan ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/08/2024 | Permit Issued | PMZ CONSTRUCTION CORP | 1 scope_items |
| Owner | Filings | Most Recent |
|---|---|---|
| 551 39TH STREET | 45 | 09/24/2026 |
| INDV | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KELLY BARLOW ARCHITECT, PLLC | 2 | 04/08/2024 |
| CELIN MUNOZ CONSULTING ENGINEER, PC | 2 | 09/14/2023 |
| VASILIOS ARTEMIOU PE | 2 | 11/04/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| CODE | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PMZ CONSTRUCTION CORP | General Contractor | 41 | 09/24/2026 |
| HENRY MYERS P & H, INC | Plumbing | 2 | 07/08/2026 |
| BILLY SERVULUS | Electrical | 1 | 03/21/2026 |
| SERVULUS BILLY | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BLUE SKY DESIGN, INC. | 1908 | 2 | 04/08/2024 |
| S&S CONCRETE & SOIL TESTI | 1008 | 2 | 09/14/2023 |
| EC SPECIAL INSPECTIONS | 8355 | 2 | 11/04/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | PMZ CONSTRUCTION CORP | 09/23/2026 |
| DOB NOW | Foundation | Permit Issued | PMZ CONSTRUCTION CORP | 03/13/2026 |
| DOB NOW | Support of Excavation | Permit Issued | PMZ CONSTRUCTION CORP | 03/11/2026 |
| DOB NOW | Structural | Permit Issued | PMZ CONSTRUCTION CORP | 03/11/2026 |
| DOB NOW | General Construction | Permit Issued | PMZ CONSTRUCTION CORP | 03/10/2026 |
| DOB NOW | Structural | Permit Issued | PMZ CONSTRUCTION CORP | 03/10/2026 |
| DOB NOW | Plumbing | Permit Issued | HENRY MYERS P & H, INC | 09/22/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | PMZ CONSTRUCTION CORP | 09/19/2025 |
| DOB NOW | General Construction | Permit Issued | PMZ CONSTRUCTION CORP | 03/26/2025 |
| DOB NOW | General Construction | Permit Issued | PMZ CONSTRUCTION CORP | 03/26/2025 |
| DOB NOW | Support of Excavation | Permit Issued | PMZ CONSTRUCTION CORP | 03/26/2025 |
| DOB NOW | Structural | Permit Issued | PMZ CONSTRUCTION CORP | 03/25/2025 |
| DOB NOW | Structural | Permit Issued | PMZ CONSTRUCTION CORP | 03/25/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | PMZ CONSTRUCTION CORP | 09/24/2024 |
| DOB NOW | Plumbing | Permit Issued | HENRY MYERS P & H, INC | 08/06/2024 |
| DOB NOW | General Construction | Permit Issued | PMZ CONSTRUCTION CORP | 04/30/2024 |
| DOB NOW | General Construction | Permit Issued | PMZ CONSTRUCTION CORP | 04/23/2024 |
| DOB NOW | Support of Excavation | Permit Issued | PMZ CONSTRUCTION CORP | 04/23/2024 |
| DOB NOW | Foundation | Permit Issued | PMZ CONSTRUCTION CORP | 04/23/2024 |
| DOB NOW | General Construction | Permit Issued | PMZ CONSTRUCTION CORP | 04/23/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | PMZ CONSTRUCTION CORP | 09/18/2023 |
| BIS | — | ISSUED | HENRY MYERS PLUMBING & H | 02/04/2004 |
| BIS | — | ISSUED | HENRY MYERS PLUMBING & H | 11/06/2003 |
| BIS | — | ISSUED | ROBERT FRANCIS | 10/29/1998 |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/17/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/12/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/25/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/25/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 09/25/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 09/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/24/2024 | Insulation placement and R values | ABDALLAH ELCHERBINI | energy_progress |
| 04/24/2024 | Fenestration air leakage | ABDALLAH ELCHERBINI | energy_progress |
| 04/24/2024 | Permanent certificate | ABDALLAH ELCHERBINI | energy_progress |
| 04/24/2024 | Air barrier - visual inspection | ABDALLAH ELCHERBINI | energy_progress |
| 04/24/2024 | Subsurface Investigations (Borings/Test Pits) | Gregory Pillori | special |
| 04/24/2024 | Structural Stability – Alterations of existing buildings | ANDREW RENFROE | special |
| 04/24/2024 | Energy Code Compliance Inspections | ABDALLAH ELCHERBINI | progress |
| 04/24/2024 | Lowest Floor Elevation | ABDALLAH ELCHERBINI | progress |
| 04/24/2024 | Lighting in dwelling units | ABDALLAH ELCHERBINI | energy_progress |
| 04/24/2024 | Air barrier — testing | ABDALLAH ELCHERBINI | energy_progress |
| 04/24/2024 | Air barrier continuity plan testing | ABDALLAH ELCHERBINI | energy_progress |
| 04/24/2024 | Metering | ABDALLAH ELCHERBINI | energy_progress |
| 04/24/2024 | Fenestration areas | ABDALLAH ELCHERBINI | energy_progress |
| 04/24/2024 | Fenestration and door U-factor and product ratings | ABDALLAH ELCHERBINI | energy_progress |
| 04/24/2024 | Maintenance information | ABDALLAH ELCHERBINI | energy_progress |
| 04/24/2024 | Interior lighting power | ABDALLAH ELCHERBINI | energy_progress |
| 04/08/2024 | Fenestration air leakage | ABDALLAH ELCHERBINI | energy_progress |
| 04/08/2024 | Lighting in dwelling units | ABDALLAH ELCHERBINI | energy_progress |
| 04/08/2024 | Permanent certificate | ABDALLAH ELCHERBINI | energy_progress |
| 04/08/2024 | Insulation placement and R values | ABDALLAH ELCHERBINI | energy_progress |
| 04/08/2024 | Air barrier continuity plan testing | ABDALLAH ELCHERBINI | energy_progress |
| 04/08/2024 | Structural Stability – Alterations of existing buildings | ANDREW RENFROE | special |
| 04/08/2024 | Subsurface Investigations (Borings/Test Pits) | Gregory Pillori | special |
| 04/08/2024 | Energy Code Compliance Inspections | ABDALLAH ELCHERBINI | progress |
| 04/08/2024 | Lowest Floor Elevation | ABDALLAH ELCHERBINI | progress |