← Back
Walk-up cooperative
166-02 17 ROAD
QUEENS · BIN 4443705
💬 Discuss this project
1951Year Built
2Stories
C6Building Class
R3-2Zoning
169,702 sfGross Floor Area
192Units
LL97 CoveredRent Stabilized3 Open Violations ▸FDNY Report ↗
Walk-up cooperative · Owner of record: CLEARVIEW GARDNS 3RD CORP · 390,209 sf lot · 0.43 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Permit Issued — active, not yet Signed-off
RoofUnder Construction2p · 1 filing · 12 docs
Floor 2Under Construction8p · 1 filing · 12 docs
Floor 1Under Construction8p · 1 filing · 12 docs
1 job · most recent 03/25/2025
Wood
FiledStatusContractorScope
03/25/2025Permit IssuedCOMPASS CONSTRUCTION OF NWood
Building Lifecycle
All (31)Filed (1)Permit Issued (2)Inspection (5)Objection (10)Special Inspection (13)
07/17/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/29/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
02/26/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
02/20/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/20/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
02/12/2026
Permit issued — Structural
Q01192817-I1-GC-CX
04/24/2025
Permit issued — General Construction
Q01192817-I1-GC-CX
04/21/2025
Objection resolved — Addressed
04/21/2025
Objection resolved — Addressed
04/08/2025
Objection resolved — Addressed
04/08/2025
Objection resolved — Addressed
04/08/2025
Objection resolved — Addressed
04/08/2025
Special inspection requirement — Energy Code Compliance Inspections
Solomon Rosenzweig
04/08/2025
Special inspection requirement — Fire-Resistance Rated Construction
Solomon Rosenzweig
04/07/2025
Objection raised — Structural
04/07/2025
Objection raised — Structural
04/07/2025
Objection raised — Scope
04/07/2025
Objection raised — Structural
04/07/2025
Objection raised — Structural
03/25/2025
Filed — Alteration
repair fire damage to second floor and attic, replace roofing shingles partially melted by fire, replace second floor sheathing damaged by fire fighting, repair water damage to first floor
Q01192817-I1
03/10/2025
Special inspection requirement — Masonry
Solomon Rosenzweig
03/10/2025
Special inspection requirement — Final
Max Lee
03/10/2025
Special inspection requirement — Structural Wood Frame
Solomon Rosenzweig
03/10/2025
Special inspection requirement — Air barrier - visual inspection
Solomon Rosenzweig
03/10/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Solomon Rosenzweig
03/10/2025
Special inspection requirement — Fenestration air leakage
Solomon Rosenzweig
03/10/2025
Special inspection requirement — Insulation placement and R values
Solomon Rosenzweig
03/10/2025
Special inspection requirement — Interior lighting power
Solomon Rosenzweig
03/10/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Solomon Rosenzweig
03/10/2025
Special inspection requirement — Lighting in dwelling units
Solomon Rosenzweig
03/10/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Solomon Rosenzweig
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SOLOMON ROSENZWEIG P.E P.C.103/25/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
COMPASS CONSTRUCTION OF NGeneral Contractor204/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SOLOMON ROSENZWEIG P.E. P1801103/25/2025
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralPermit IssuedCOMPASS CONSTRUCTION OF N02/12/2026
DOB NOWGeneral ConstructionPermit IssuedCOMPASS CONSTRUCTION OF N04/24/2025
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
07/17/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/29/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/26/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/20/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/20/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
04/08/2025Energy Code Compliance InspectionsSolomon Rosenzweigprogress
04/08/2025Fire-Resistance Rated ConstructionSolomon Rosenzweigprogress
03/10/2025MasonrySolomon Rosenzweigspecial
03/10/2025FinalMax Leeprogress
03/10/2025Structural Wood FrameSolomon Rosenzweigprogress
03/10/2025Air barrier - visual inspectionSolomon Rosenzweigenergy_progress
03/10/2025Fenestration and door U-factor and product ratingsSolomon Rosenzweigenergy_progress
03/10/2025Fenestration air leakageSolomon Rosenzweigenergy_progress
03/10/2025Insulation placement and R valuesSolomon Rosenzweigenergy_progress
03/10/2025Interior lighting powerSolomon Rosenzweigenergy_progress
03/10/2025Structural Stability – Alterations of existing buildingsSolomon Rosenzweigspecial
03/10/2025Lighting in dwelling unitsSolomon Rosenzweigenergy_progress
03/10/2025Fire-Resistant Penetrations and JointsSolomon Rosenzweigspecial
▾Documents — 12 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026Q01192817-I1Request digital key ↗
▸Seals & Professional Certifications9
▸DOB NOWProgress Inspector Seal & Signature5
08/29/2026Q01192817-I1Open ↗
08/29/2026Q01192817-I1Open ↗
08/29/2026Q01192817-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/29/2026Q01192817-I1Open ↗
08/29/2026Q01192817-I1Open ↗
08/29/2026Q01192817-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01192817-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01192817-I1Open ↗
▸Other Documents1
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026Q01192817-I1Open ↗