0Year Built
—Stories
R2Building Class
R4Zoning
109,572 sfGross Floor Area
150Units
Rent Stabilized46 Open Violations ▸FDNY Report ↗
Condo, residential unit in walk-up building · 173,906 sf lot · 0.63 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOPOS DESIGNS, INC.209/11/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GEAR INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BADALY ARCHITECT PLLC7137209/11/2024
Building Lifecycle
All (12)Filed (2)Permit Issued (1)Signed Off (1)Objection (4)Special Inspection (4)
10/24/2024
Signed off — Alteration
WE PROPOSE TO INSTALL NEW SPLIT UNIT. THERE WILL BE NO CHANGE IN EGRESS, OCCUPANCY OR USE UNDER THIS APPLICATION. NO PLUMBING TO BE INVOLVED, NO WATER TO BE INVOLVED.
Q00994841-I1
09/24/2024
Special inspection requirement — Mechanical Systems
SHAHIN BADALY
09/24/2024
Special inspection requirement — Final
Amalia Bournias
09/19/2024
Objection resolved — Addressed
09/18/2024
Objection raised — Scope
09/11/2024
Filed — Alteration
WE PROPOSE TO INSTALL NEW SPLIT UNIT. THERE WILL BE NO CHANGE IN EGRESS, OCCUPANCY OR USE UNDER THIS APPLICATION. NO PLUMBING TO BE INVOLVED, NO WATER TO BE INVOLVED.
Q00994841-P1
09/10/2024
Special inspection requirement — Mechanical Systems
SHAHIN BADALY
09/10/2024
Special inspection requirement — Final
Amalia Bournias
05/17/2024
Permit issued — Mechanical Systems
Q00994841-I1-MS
02/29/2024
Objection resolved — Addressed
02/02/2024
Objection raised — Scope
01/23/2024
Filed — Alteration
WE PROPOSE TO INSTALL NEW SPLIT UNIT. THERE WILL BE NO CHANGE IN EGRESS, OCCUPANCY OR USE UNDER THIS APPLICATION. NO PLUMBING TO BE INVOLVED, NO WATER TO BE INVOLVED.
Q00994841-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offGEAR INC05/17/2024
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
09/24/2024Mechanical SystemsSHAHIN BADALYspecial
09/24/2024FinalAmalia Bourniasprogress
09/10/2024Mechanical SystemsSHAHIN BADALYspecial
09/10/2024FinalAmalia Bourniasprogress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/23/2026Q00994841-I1Request digital key ↗
08/15/2026Q00994841-P1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/23/2026Q00994841-I1Open ↗
08/13/2026Q00994841-P1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/23/2026Q00994841-I1Open ↗
08/27/2026Q00994841-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/23/2026Q00994841-I1Open ↗
08/27/2026Q00994841-P1Open ↗