← Back
Bungalow colony - cooperatively owned land
217-02 BREEZY POINT BLVD
QUEENS · BIN 4465647
💬 Discuss this project
1938Year Built
1Stories
A8Building Class
R4Zoning
1,600,000 sfGross Floor Area
1,906Units
LL97 Covered60 Open Violations 2 unresolved · 58 paperwork only ▸FDNY Report ↗
Bungalow colony - cooperatively owned land · Owner of record: BREEZY POINT COOPERATIVE, INC · 12,253,428 sf lot · 0.13 FAR built · Flood zone AE
Locations of Work
Architecture
Roof1p · 1 filing · 14 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BREEZY POINT COOPERATIVE, INC.603/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CMC DESIGN ARCHITECT, P.C.308/20/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AC BUILDING CONSULTANTS603/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CMC DESIGN ARCHITECT, P.C2984108/20/2021
Building Lifecycle
All (57)Filed (3)Objection (24)Special Inspection (30)
08/20/2021
Filed — New Building
Proposed 3 story, 1 family New Building.
Q00518831-S2
08/20/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Gary Lenhart
08/20/2021
Special inspection requirement — On-Site Private Sewage Disposal Systems Installation
Gary Lenhart
08/20/2021
Special inspection requirement — Energy Code Compliance Inspections
Gary Lenhart
08/20/2021
Special inspection requirement — HVAC-R and service water heating equipment
Gary Lenhart
08/20/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
Gary Lenhart
08/20/2021
Special inspection requirement — HVAC-R and service water heating system controls
Gary Lenhart
07/10/2021
Objection raised — Other
07/10/2021
Objection resolved — Addressed
07/10/2021
Objection raised — Other
07/10/2021
Objection resolved — Addressed
07/10/2021
Objection raised — Other
07/10/2021
Objection resolved — Addressed
07/10/2021
Objection raised — Other
07/10/2021
Objection resolved — Addressed
07/10/2021
Objection raised — Other
07/10/2021
Objection resolved — Addressed
06/30/2021
Objection raised — Scope
06/30/2021
Objection resolved — Addressed
06/30/2021
Objection raised — Structural
06/30/2021
Objection resolved — Addressed
06/30/2021
Objection raised — Inspections
06/30/2021
Objection resolved — Addressed
06/29/2021
Filed — New Building
Proposed 3 story, 1 family New Building.
Q00518831-S1
06/21/2021
Objection raised — Energy
06/21/2021
Objection resolved — Addressed
06/21/2021
Objection raised — Energy
06/21/2021
Objection resolved — Addressed
06/21/2021
Objection raised — Energy
06/21/2021
Objection resolved — Addressed
06/21/2021
Objection raised — Energy
06/21/2021
Objection resolved — Addressed
06/17/2021
Filed — New Building
Proposed 3 story, 1 family New Building.
Q00518831-I1
05/09/2021
Special inspection requirement — Lowest Floor Elevation
05/09/2021
Special inspection requirement — Concrete - Cast-In-Place
05/09/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/09/2021
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
05/09/2021
Special inspection requirement — Structural Cold-Formed Steel
05/09/2021
Special inspection requirement — Subgrade Inspections
05/09/2021
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
05/09/2021
Special inspection requirement — Wood – Prefabricated I-Joists
05/09/2021
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
05/09/2021
Special inspection requirement — Final
05/09/2021
Special inspection requirement — Footing and Foundation
05/09/2021
Special inspection requirement — Energy Code Compliance Inspections
05/09/2021
Special inspection requirement — Fire-Resistance Rated Construction
05/09/2021
Special inspection requirement — Metering
05/09/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
05/09/2021
Special inspection requirement — Air barrier — testing
05/09/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
05/09/2021
Special inspection requirement — Permanent certificate
05/09/2021
Special inspection requirement — Interior lighting power
05/09/2021
Special inspection requirement — Air barrier - visual inspection
05/09/2021
Special inspection requirement — Insulation placement and R values
05/09/2021
Special inspection requirement — Maintenance information
05/09/2021
Special inspection requirement — Fenestration areas
05/09/2021
Special inspection requirement — Fenestration air leakage
Nothing on file for this building.
1 project · most recent 08/20/2021
Gas Plumbing-Sprinkler Water/Sanitary
FiledStatusContractorScope
08/20/2021——Gas, Plumbing-Sprinkler, Water/Sanitary
1 project · most recent 08/20/2021
FiledStatusContractorScope
08/20/2021——1 scope_items
1 project · most recent 08/20/2021
Fence
FiledStatusContractorScope
08/20/2021——Fence
▾Special Inspection Requirements (DOB NOW) — 31
DateRequirementInspectorRole
08/20/2021Fire-Resistant Penetrations and JointsGary Lenhartspecial
08/20/2021On-Site Private Sewage Disposal Systems InstallationGary Lenhartspecial
08/20/2021Energy Code Compliance InspectionsGary Lenhartprogress
08/20/2021HVAC-R and service water heating equipmentGary Lenhartenergy_progress
08/20/2021HVAC-R and service water piping design and insulationGary Lenhartenergy_progress
08/20/2021HVAC-R and service water heating system controlsGary Lenhartenergy_progress
05/09/2021Lowest Floor Elevation—progress
05/09/2021Concrete - Cast-In-Place—special
05/09/2021Fire-Resistant Penetrations and Joints—special
05/09/2021Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)—special
05/09/2021Structural Cold-Formed Steel—special
05/09/2021Subgrade Inspections—special
05/09/2021Subsurface Conditions – Fill Placement & In-Place Density—special
05/09/2021Wood – Prefabricated I-Joists—special
05/09/2021Subsurface Investigations (Borings/Test Pits)—special
05/09/2021Final—progress
05/09/2021Footing and Foundation—progress
05/09/2021Energy Code Compliance Inspections—progress
05/09/2021Fire-Resistance Rated Construction—progress
05/09/2021Metering—energy_progress
05/09/2021HVAC-R and service water piping design and insulation—energy_progress
05/09/2021Air barrier — testing —energy_progress
05/09/2021Fenestration and door U-factor and product ratings—energy_progress
05/09/2021Permanent certificate—energy_progress
05/09/2021Interior lighting power—energy_progress
Latest 25 of 31.
▾Documents — 14 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/27/2026Q00518831-S2Request digital key ↗
08/15/2026Q00518831-I1Request digital key ↗
08/14/2026Q00518831-S1Request digital key ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026Q00518831-I1Open ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/13/2026Q00518831-S2Open ↗
08/13/2026Q00518831-S1Open ↗
08/13/2026Q00518831-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/26/2026Q00518831-S2Open ↗
08/26/2026Q00518831-S2Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/26/2026Q00518831-S2Open ↗
▸Inspections & Test Reports3
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q00518831-I1Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026Q00518831-I1Open ↗
▸DOB NOWTR4 Plot Diagram1
08/13/2026Q00518831-I1Open ↗
▸Other Documents1
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026Q00518831-I1Open ↗