LL97 Covered60 Open Violations 2 unresolved · 58 paperwork only ▸FDNY Report ↗
Bungalow colony - cooperatively owned land · Owner of record: BREEZY POINT COOPERATIVE, INC · 12,253,428 sf lot · 0.13 FAR built · Flood zone AE
Locations of Work
ArchitecturePlumbing
Floor 219p · 1 filing · 20 docs
Floor 119p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BREEZY POINT COOPERATIVE, INC.3207/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CMC DESIGN ARCHITECT, P.C.802/11/2025
GREGORY D. SACHS, PE107/11/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AC BUILDING CONSULTANTS1603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SIMPLY STRONG CONSTRUCTGeneral Contractor1007/08/2026
JOSEPH O'GRADY P & H INCPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CMC DESIGN ARCHITECT, P.C2984702/11/2025
PACIFICO ENGINEERING PC3157107/11/2024
Building Lifecycle
All (98)Filed (9)Permit Issued (7)Signed Off (3)Inspection (7)Objection (42)Special Inspection (30)
02/26/2025
Special inspection requirement — Fenestration air leakage
Gary Lenhart
02/26/2025
Special inspection requirement — Air barrier - visual inspection
Gary Lenhart
02/26/2025
Special inspection requirement — Final
Gary Lenhart
02/26/2025
Special inspection requirement — HVAC-R and service water heating system controls
Gary Lenhart
02/26/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Gary Lenhart
02/26/2025
Special inspection requirement — Fenestration areas
Gary Lenhart
02/26/2025
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
Gary Lenhart
02/26/2025
Special inspection requirement — Structural Wood Frame
Gary Lenhart
02/26/2025
Special inspection requirement — Fireplaces
Gary Lenhart
02/26/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Gary Lenhart
02/26/2025
Special inspection requirement — Insulation placement and R values
Gary Lenhart
02/26/2025
Special inspection requirement — HVAC-R and service water heating equipment
Gary Lenhart
02/26/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Gary Lenhart
02/26/2025
Special inspection requirement — Maintenance information
Gary Lenhart
02/26/2025
Special inspection requirement — Wood – Prefabricated I-Joists
Gary Lenhart
02/26/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Gary Lenhart
02/26/2025
Special inspection requirement — Fire-Resistance Rated Construction
Gary Lenhart
02/26/2025
Special inspection requirement — Lowest Floor Elevation
Gary Lenhart
02/26/2025
Special inspection requirement — Energy Code Compliance Inspections
Gary Lenhart
02/26/2025
Special inspection requirement — Interior lighting power
Gary Lenhart
02/26/2025
Special inspection requirement — Permanent certificate
Gary Lenhart
02/26/2025
Special inspection requirement — Metering
Gary Lenhart
02/26/2025
Special inspection requirement — Air barrier — testing
Gary Lenhart
02/11/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
Fence application related to vertical extension.
Q00509375-P6
01/15/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
Fence application related to vertical extension.
Q00509375-P5
12/10/2024
Signed off — Alteration
Installation of roof mounted solar. No change in use, egress or occupancy.
Q01060229-I1
07/22/2024
Permit issued — Solar
Q01060229-I1-SL
07/11/2024
Filed — Alteration
Installation of roof mounted solar. No change in use, egress or occupancy.
Q01060229-I1
04/25/2024
Signed off — ALT-CO - New Building with Existing Elements to Remain
Fence application related to vertical extension.
Q00509375-S2
02/05/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
02/05/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/15/2023
Permit issued — Plumbing
Q00509375-S2-PL
08/21/2023
Signed off — ALT-CO - New Building with Existing Elements to Remain
Fence application related to vertical extension.
Q00509375-S1
08/02/2023
Filed — ALT-CO - New Building with Existing Elements to Remain
Fence application related to vertical extension.
Q00509375-P4
08/02/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/02/2023
Special inspection requirement — Wood – Prefabricated I-Joists
Gary Lenhart
08/02/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Gary Lenhart
08/02/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Gary Lenhart
08/02/2023
Special inspection requirement — Energy Code Compliance Inspections
Gary Lenhart
08/02/2023
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
Gary Lenhart
08/02/2023
Special inspection requirement — Final
Gary Lenhart
08/02/2023
Special inspection requirement — Fire-Resistance Rated Construction
Gary Lenhart
07/25/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/13/2023
Filed — ALT-CO - New Building with Existing Elements to Remain
Fence application related to vertical extension.
Q00509375-P3
07/13/2023
Filed — ALT-CO - New Building with Existing Elements to Remain
Fence application related to vertical extension.
Q00509375-P1
04/11/2023
Permit issued — Construction Fence
Q00509375-S1-FN
04/11/2023
Permit issued — General Construction
Q00509375-I1-GC-CX
01/26/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/26/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/26/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
11/01/2022
Permit issued — Plumbing
Q00509375-S2-PL
09/22/2022
Permit issued — General Construction
Q00509375-I1-GC-CX
09/22/2022
Permit issued — Construction Fence
Q00509375-S1-FN
09/07/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
Fence application related to vertical extension.
Q00509375-S2
09/07/2022
Objection resolved — Addressed
09/01/2022
Objection resolved — Addressed
08/30/2022
Objection resolved — Addressed
08/30/2022
Objection resolved — Addressed
08/30/2022
Objection resolved — Addressed
08/30/2022
Objection resolved — Addressed
Latest 60 of 98 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offGREGORY D. SACHS, PE07/22/2024
DOB NOWPlumbingSigned-offJOSEPH O'GRADY P & H INC12/15/2023
DOB NOWConstruction FenceSigned-offSIMPLY STRONG CONSTRUCT04/11/2023
DOB NOWGeneral ConstructionPermit IssuedSIMPLY STRONG CONSTRUCT04/11/2023
DOB NOWPlumbingSigned-offJOSEPH O'GRADY P & H INC11/01/2022
DOB NOWGeneral ConstructionPermit IssuedSIMPLY STRONG CONSTRUCT09/22/2022
DOB NOWConstruction FenceSigned-offSIMPLY STRONG CONSTRUCT09/22/2022
BISPLISSUEDNORTON MECHANICAL II INC04/28/2016
BISPLISSUEDNORTON MECHANICAL II INC03/24/2014
BISMHISSUEDI'LL GO INC12/16/2013
1 project · most recent 02/11/2025
Gas Water/Sanitary
FiledStatusContractorScope
02/11/2025Signed-offJOSEPH O'GRADY P & H INCGas, Water/Sanitary
2 projects · most recent 09/20/2024
General Wiring
FiledStatusContractorScope
09/20/2024CompleteISLAND ELECTRIC CORP—
01/24/2023CompletePAPPAS & FODERA ELECT'LGeneral Wiring
1 project · most recent 02/11/2025
Wood
FiledStatusContractorScope
02/11/2025Signed-offJOSEPH O'GRADY P & H INCWood
1 project · most recent 02/11/2025
Fence
FiledStatusContractorScope
02/11/2025Signed-offJOSEPH O'GRADY P & H INCFence
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
02/05/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/05/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/02/2023Pass-Final CND-Occupancy InspectionPassView ↗
07/25/2023Pass-Final CND-Occupancy InspectionPassView ↗
01/26/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/26/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/26/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 81
DateRequirementInspectorRole
02/26/2025Fire-Resistant Penetrations and JointsGary Lenhartspecial
02/26/2025HVAC-R and service water piping design and insulationGary Lenhartenergy_progress
02/26/2025HVAC-R and service water heating equipmentGary Lenhartenergy_progress
02/26/2025Maintenance informationGary Lenhartenergy_progress
02/26/2025Fenestration areasGary Lenhartenergy_progress
02/26/2025Insulation placement and R valuesGary Lenhartenergy_progress
02/26/2025Air barrier - visual inspectionGary Lenhartenergy_progress
02/26/2025Air barrier — testing Gary Lenhartenergy_progress
02/26/2025Fenestration air leakageGary Lenhartenergy_progress
02/26/2025HVAC-R and service water heating system controlsGary Lenhartenergy_progress
02/26/2025Fenestration and door U-factor and product ratingsGary Lenhartenergy_progress
02/26/2025MeteringGary Lenhartenergy_progress
02/26/2025Permanent certificateGary Lenhartenergy_progress
02/26/2025FireplacesGary Lenhartenergy_progress
02/26/2025Interior lighting powerGary Lenhartenergy_progress
02/26/2025Energy Code Compliance InspectionsGary Lenhartprogress
02/26/2025FinalGary Lenhartprogress
02/26/2025Structural Wood FrameGary Lenhartprogress
02/26/2025Lowest Floor ElevationGary Lenhartprogress
02/26/2025Fire-Resistance Rated ConstructionGary Lenhartprogress
02/26/2025Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Gary Lenhartspecial
02/26/2025Structural Stability – Alterations of existing buildingsGary Lenhartspecial
02/26/2025Wood – Prefabricated I-JoistsGary Lenhartspecial
08/02/2023Structural Wood FrameGary Lenhartprogress
08/02/2023Fire-Resistant Penetrations and JointsGary Lenhartspecial
Latest 25 of 81.
▾Documents — 113 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/24/2026Q00509375-P3Request digital key ↗
08/24/2026Q00509375-P6Request digital key ↗
08/24/2026Q00509375-P5Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits7
▸BISPLAN / WORK APPROVAL APPLICATION5
05/22/2024420896579Open ↗
11/17/2014420896579Open ↗
07/26/2014420896579Open ↗
Showing 3 of 5 on file for this type
▸BISWORK PERMIT APPLICATION2
05/02/2016420896579Open ↗
03/27/2014420896579Open ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZD1: DOB Zoning Diagram5
08/15/2026Q00509375-I1Open ↗
08/13/2026Q00509375-P6Open ↗
08/13/2026Q00509375-P1Open ↗
Showing 3 of 5 on file for this type
▸BISZoning Diagram (ZD1)1
11/30/2013420896579Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/15/2026Q00509375-I1Open ↗
▸Seals & Professional Certifications39
▸DOB NOWProgress Inspector Seal & Signature16
09/01/2026Q00509375-S2Open ↗
09/01/2026Q00509375-S2Open ↗
09/01/2026Q00509375-P4Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/24/2026Q00509375-P6Open ↗
08/24/2026Q00509375-P5Open ↗
08/24/2026Q00509375-P4Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
09/01/2026Q00509375-S2Open ↗
09/01/2026Q00509375-P4Open ↗
09/01/2026Q00509375-P4Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION6
10/25/2016420896579Open ↗
10/03/2016420896579Open ↗
07/13/2016420896579Open ↗
Showing 3 of 6 on file for this type
▸Trade Schedules & Equipment7
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
11/17/2014420896579Open ↗
07/26/2014420896579Open ↗
04/14/2014420896579Open ↗
▸BISSELF-CERT PLUMBING NOTICE2
07/30/2014420896579Open ↗
07/11/2014420896579Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
09/23/2016420896579Open ↗
▸BISSCHEDULE B - PLUMBING1
09/27/2013420896579Open ↗
▸Safety & Tenant Protection1
▸BISSTREET TREE CHECKLIST1
09/27/2013420896579Open ↗
▸Environmental & Asbestos11
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/24/2026Q00509375-P6Open ↗
08/24/2026Q00509375-P5Open ↗
08/24/2026Q00509375-P4Open ↗
Showing 3 of 9 on file for this type
▸BISASBESTOS-EXEMPTION (ASB4)1
12/07/2013420896579Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
11/30/2013420896579Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
07/13/2016420896579Open ↗
12/07/2013420896579Open ↗
09/27/2013420896579Open ↗
▸BISAS-BUILT ENERGY ANALYSIS2
10/25/2016420896579Open ↗
09/19/2016420896579Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
08/15/2026Q00509375-I1Open ↗
08/13/2026Q00509375-S2Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: SOIL INSPECTION1
10/25/2016420896579Open ↗
▸Approvals, Objections & Sign-offs4
▸BISLETTERS - SUPPORTING DOCUMENTATION3
12/23/2013420896579Open ↗
12/06/2013420896579Open ↗
12/06/2013420896579Open ↗
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01060229-I1Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
10/26/2016420896579Open ↗
09/27/2013420896579Open ↗
▸Filing & Intake Forms7
▸BISADDITIONAL INFORMATION6
05/04/2015420896579Open ↗
12/18/2013420896579Open ↗
12/18/2013420896579Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET1
09/27/2013420896579Open ↗
▸Other Documents12
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone5
08/15/2026Q00509375-I1Open ↗
08/13/2026Q00509375-P5Open ↗
08/13/2026Q00509375-P6Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSite Survey: Initial5
08/15/2026Q00509375-I1Open ↗
08/13/2026Q00509375-P6Open ↗
08/13/2026Q00509375-P5Open ↗
Showing 3 of 5 on file for this type
▸BISFEMA ELEVATION CERT (086-0-33)/ FLOODPROOFING CERT (086-0-34)1
10/03/2016420896579Open ↗
▸DOB NOWFinal Survey1
08/15/2026Q00509375-I1Open ↗