| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/24/2022 | Complete | ERIC & NG ELEC'L, INC. | General Wiring |
| Firm | Filings | Most Recent |
|---|---|---|
| 1+1 DESIGN STUDIO LLC | 5 | 04/12/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| G.PLAN DESIGN & CONSULTING INC | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GLOBAL TEAM NY INC | General Contractor | 3 | 03/21/2026 |
| CATMAN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CL ENGINEERING P.C. | 6781 | 3 | 04/12/2023 |
| DY SPECIAL INSPECTION LLC | 7210 | 1 | 05/09/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | CATMAN PLUMBING INC | 05/25/2022 |
| DOB NOW | General Construction | Permit Issued | GLOBAL TEAM NY INC | 05/20/2022 |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/24/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/06/2022 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 07/25/2022 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/27/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/27/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/27/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/21/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/13/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/13/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/18/2023 | Fenestration and door U-factor and product ratings | THOMAS TUNG | energy_progress |
| 04/18/2023 | Fire-Resistant Penetrations and Joints | CHRISTIAN LOZADA | special |
| 04/18/2023 | Structural Stability – Alterations of existing buildings | CHRISTIAN LOZADA | special |
| 04/18/2023 | Energy Code Compliance Inspections | THOMAS TUNG | progress |
| 04/18/2023 | Fire-Resistance Rated Construction | THOMAS TUNG | progress |
| 04/18/2023 | Fenestration areas | THOMAS TUNG | energy_progress |
| 04/18/2023 | Interior lighting power | THOMAS TUNG | energy_progress |
| 04/18/2023 | Fenestration air leakage | THOMAS TUNG | energy_progress |
| 04/18/2023 | Air barrier - visual inspection | THOMAS TUNG | energy_progress |
| 03/20/2023 | Fire-Resistant Penetrations and Joints | CHRISTIAN LOZADA | special |
| 03/20/2023 | Structural Stability – Alterations of existing buildings | CHRISTIAN LOZADA | special |
| 03/20/2023 | Energy Code Compliance Inspections | THOMAS TUNG | progress |
| 03/20/2023 | Fire-Resistance Rated Construction | THOMAS TUNG | progress |
| 03/20/2023 | Air barrier - visual inspection | THOMAS TUNG | energy_progress |
| 03/20/2023 | Fenestration and door U-factor and product ratings | THOMAS TUNG | energy_progress |
| 03/20/2023 | Fenestration areas | THOMAS TUNG | energy_progress |
| 03/20/2023 | Interior lighting power | THOMAS TUNG | energy_progress |
| 03/20/2023 | Fenestration air leakage | THOMAS TUNG | energy_progress |