← Back
Cape Cod
145-02 109 AVENUE
QUEENS · BIN 4582235
💬 Discuss this project
1945Year Built
1.5Stories
A0Building Class
R4Zoning
1,159 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Cape Cod · 4,542 sf lot · 0.26 FAR built · Flood zone X
Locations of Work
Architecture
Permit Issued — active, not yet Signed-off
Floor 1Under Construction3p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
KATARIA407/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AFM INSPECTIONS & ENGINEERING, PLLC407/28/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GEREBUZZA CONSTRUCTION INGeneral Contractor107/08/2026
PLUMB-IT MECHANICAL INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AFM INSPECTIONS & ENGINEE4675307/28/2026
EMILIO SUSA ARCHITECT3605105/14/2026
Building Lifecycle
All (47)Filed (4)Permit Issued (2)Inspection (3)Objection (8)Special Inspection (30)
09/08/2026
Objection resolved — Addressed
08/11/2026
Objection raised — Other
07/28/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
FILING HEREWITH PLANS AND APPLICATION TO ENLARGE EXISTING MASONRY CAR GARAGE. REQUESTING NEW CERTIFICATE OF OCCUPANCY. VIEW SEPARATE APPLICATION FOR PLUMBING.
Q01199408-P2
07/28/2026
Special inspection requirement — Concrete - Cast-In-Place
Anthony Marmo
07/28/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Anthony Marmo
07/28/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Anthony Marmo
07/28/2026
Special inspection requirement — Subgrade Inspections
Anthony Marmo
07/28/2026
Special inspection requirement — Energy Code Compliance Inspections
Anthony Marmo
07/28/2026
Special inspection requirement — Fire-Resistance Rated Construction
Anthony Marmo
07/28/2026
Special inspection requirement — Interior lighting power
Anthony Marmo
07/28/2026
Special inspection requirement — Exterior lighting power
Anthony Marmo
07/28/2026
Special inspection requirement — Masonry
Anthony Marmo
07/21/2026
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
07/17/2026
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
07/17/2026
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
06/03/2026
Permit issued — Plumbing
Q01199408-S1-PL
05/14/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
FILING HEREWITH PLANS AND APPLICATION TO ENLARGE EXISTING MASONRY CAR GARAGE. REQUESTING NEW CERTIFICATE OF OCCUPANCY. VIEW SEPARATE APPLICATION FOR PLUMBING.
Q01199408-S1
05/14/2026
Permit issued — General Construction
Q01199408-I1-GC
05/14/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Anthony Marmo
05/04/2026
Special inspection requirement — Masonry
Anthony Marmo
05/04/2026
Special inspection requirement — Concrete - Cast-In-Place
Anthony Marmo
05/04/2026
Special inspection requirement — Subgrade Inspections
Anthony Marmo
05/04/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Anthony Marmo
05/04/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Anthony Marmo
05/04/2026
Special inspection requirement — Fire-Resistance Rated Construction
Anthony Marmo
05/04/2026
Special inspection requirement — Energy Code Compliance Inspections
Anthony Marmo
05/04/2026
Special inspection requirement — Interior lighting power
Anthony Marmo
05/04/2026
Special inspection requirement — Exterior lighting power
Anthony Marmo
04/07/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Emilio Susa
04/07/2026
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
Emilio Susa
04/03/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
FILING HEREWITH PLANS AND APPLICATION TO ENLARGE EXISTING MASONRY CAR GARAGE. REQUESTING NEW CERTIFICATE OF OCCUPANCY. VIEW SEPARATE APPLICATION FOR PLUMBING.
Q01199408-P1
04/03/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Anthony Marmo
04/03/2026
Special inspection requirement — Subgrade Inspections
Anthony Marmo
04/03/2026
Special inspection requirement — Energy Code Compliance Inspections
Anthony Marmo
04/03/2026
Special inspection requirement — Masonry
Anthony Marmo
04/03/2026
Special inspection requirement — Exterior lighting power
Anthony Marmo
04/03/2026
Special inspection requirement — Interior lighting power
Anthony Marmo
04/03/2026
Special inspection requirement — Concrete - Cast-In-Place
Anthony Marmo
04/03/2026
Special inspection requirement — Fire-Resistance Rated Construction
Anthony Marmo
04/03/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Anthony Marmo
10/28/2025
Objection resolved — Addressed
10/28/2025
Objection resolved — Addressed
10/28/2025
Objection resolved — Addressed
04/04/2025
Objection raised — Energy
04/04/2025
Objection raised — Zoning
04/04/2025
Objection raised — Admin
03/22/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
FILING HEREWITH PLANS AND APPLICATION TO ENLARGE EXISTING MASONRY CAR GARAGE. REQUESTING NEW CERTIFICATE OF OCCUPANCY. VIEW SEPARATE APPLICATION FOR PLUMBING.
Q01199408-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offPLUMB-IT MECHANICAL INC06/03/2026
DOB NOWGeneral ConstructionPermit IssuedGEREBUZZA CONSTRUCTION IN05/14/2026
1 project · most recent 06/02/2026
General Wiring
FiledStatusContractorScope
06/02/2026CompleteMETROPOLITAN ELEC OF NY IGeneral Wiring
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
07/21/2026Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
07/17/2026Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
07/17/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 30
DateRequirementInspectorRole
07/28/2026Concrete - Cast-In-PlaceAnthony Marmospecial
07/28/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationAnthony Marmospecial
07/28/2026Structural Stability – Alterations of existing buildingsAnthony Marmospecial
07/28/2026Subgrade InspectionsAnthony Marmospecial
07/28/2026Energy Code Compliance InspectionsAnthony Marmoprogress
07/28/2026Fire-Resistance Rated ConstructionAnthony Marmoprogress
07/28/2026Interior lighting powerAnthony Marmoenergy_progress
07/28/2026Exterior lighting powerAnthony Marmoenergy_progress
07/28/2026MasonryAnthony Marmospecial
05/14/2026Subsurface Investigations (Borings/Test Pits)Anthony Marmospecial
05/04/2026MasonryAnthony Marmospecial
05/04/2026Concrete - Cast-In-PlaceAnthony Marmospecial
05/04/2026Subgrade InspectionsAnthony Marmospecial
05/04/2026Structural Stability – Alterations of existing buildingsAnthony Marmospecial
05/04/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationAnthony Marmospecial
05/04/2026Fire-Resistance Rated ConstructionAnthony Marmoprogress
05/04/2026Energy Code Compliance InspectionsAnthony Marmoprogress
05/04/2026Interior lighting powerAnthony Marmoenergy_progress
05/04/2026Exterior lighting powerAnthony Marmoenergy_progress
04/07/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationEmilio Susaspecial
04/07/2026Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesEmilio Susaspecial
04/03/2026Structural Stability – Alterations of existing buildingsAnthony Marmospecial
04/03/2026Subgrade InspectionsAnthony Marmospecial
04/03/2026Energy Code Compliance InspectionsAnthony Marmoprogress
04/03/2026MasonryAnthony Marmospecial
Latest 25 of 30.
▾Documents — 58 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/16/2026Q01199408-S1Request digital key ↗
08/16/2026Q01199408-I1Request digital key ↗
08/16/2026Q01199408-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram3
08/16/2026Q01199408-P1Open ↗
08/15/2026Q01199408-P2Open ↗
08/13/2026Q01199408-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q01199408-I1Open ↗
▸Seals & Professional Certifications33
▸DOB NOWSpecial Inspector Seal & Signature18
09/21/2026Q01199408-P2Open ↗
09/21/2026Q01199408-P2Open ↗
09/21/2026Q01199408-P2Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWProgress Inspector Seal & Signature11
09/21/2026Q01199408-P2Open ↗
09/21/2026Q01199408-P2Open ↗
09/21/2026Q01199408-P2Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/16/2026Q01199408-P1Open ↗
08/16/2026Q01199408-S1Open ↗
08/16/2026Q01199408-P2Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection1
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q01199408-I1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/16/2026Q01199408-P1Open ↗
08/16/2026Q01199408-S1Open ↗
08/16/2026Q01199408-I1Open ↗
Showing 3 of 4 on file for this type
▸Inspections & Test Reports2
▸DOB NOWTR4 Test Report and Plot Diagram1
08/16/2026Q01199408-S1Open ↗
▸DOB NOWSOIL REPORT1
08/16/2026Q01199408-S1Open ↗
▸Other Documents10
▸DOB NOWSite Survey: Initial3
08/16/2026Q01199408-P1Open ↗
08/15/2026Q01199408-P2Open ↗
08/13/2026Q01199408-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/16/2026Q01199408-P1Open ↗
08/15/2026Q01199408-P2Open ↗
08/13/2026Q01199408-I1Open ↗
▸DOB NOWProperty Ownership Certification3
08/16/2026Q01199408-P1Open ↗
08/15/2026Q01199408-P2Open ↗
08/13/2026Q01199408-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026Q01199408-I1Open ↗