| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | — | — | 2 scope_items |
| Firm | Filings | Most Recent |
|---|---|---|
| H & O ENGINEERING, DPC | 1 | 08/06/2026 |
| LEANDRO NILS DICKSON ARCHITECT, LLC | 1 | 07/29/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| BIS | — | ISSUED | MRMD NY CORP | 06/18/2013 |
| BIS | EQ | ISSUED | MRMD NY CORP | 06/18/2013 |
| BIS | PL | ISSUED | BEST MECHANICAL SVCS INC | 02/17/2006 |
| BIS | — | ISSUED | DONAT DESIGNS INC | 10/17/2005 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/06/2026 | Structural Stability – Alterations of existing Buildings | — | special |
| 08/06/2026 | Demolition | — | special |
| 07/29/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/29/2026 | Energy Code Compliance Inspections | — | progress |
| 07/29/2026 | Fire-Resistance Rated Construction | — | progress |
| 07/29/2026 | Air barrier - visual inspection | — | energy_progress |
| 07/29/2026 | Fenestration areas | — | energy_progress |
| 07/29/2026 | Exterior lighting power | — | energy_progress |
| 07/29/2026 | Air barrier continuity plan testing | — | energy_progress |
| 07/29/2026 | Lighting controls | — | energy_progress |
| 07/29/2026 | Alternative Materials - OTCR Buildings Bulletin Number | — | special |
| 07/29/2026 | Fenestration air leakage | — | energy_progress |
| 07/29/2026 | Electrical motors and elevators | — | energy_progress |
| 07/29/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 07/29/2026 | Metering | — | energy_progress |
| 07/29/2026 | Interior lighting power | — | energy_progress |
| 07/29/2026 | Lighting in dwelling units | — | energy_progress |
| 07/29/2026 | Protection of exposed foundation insulation | — | energy_progress |
| 07/29/2026 | Maintenance information | — | energy_progress |
| 07/29/2026 | Insulation placement and R values | — | energy_progress |
| 07/29/2026 | Exterior Insulation and Finish Systems (EIFS) | — | special |