← Back
Shopping center, with or without parking
212-15 26 AVENUE
QUEENS · BIN 4595516
💬 Discuss this project
1961Year Built
2Stories
K6Building Class
C4-1Zoning
198,298 sfGross Floor Area
47Units
LL97 Covered4 Open Violations 0 unresolved · 4 paperwork only ▸FDNY Report ↗
Shopping center, with or without parking · Owner of record: 21245 26 AVE LLC · 606,761 sf lot · 0.33 FAR built · Flood zone X
Locations of Work
Mechanical
Floor 21p · 1 filing · 3 docs
Floor 11p · 1 filing · 5 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
DESIGN GROUP IN H&K LLC107/25/2024
GERALD CALIENDO ARCHITECTS101/19/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
GERALD J. CALIENDO R.A., P.C.103/21/2026
DESIGN GROUP IN H K203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
IMPACT BUILDERS CORPGeneral Contractor107/08/2026
URBAN GC INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DESIGN GROUP IN H&K LLC1363107/25/2024
DOYUN KIM; RA7415101/19/2023
Building Lifecycle
All (9)Filed (2)Permit Issued (2)Signed Off (2)Inspection (1)Special Inspection (2)
03/26/2025
Signed off — Alteration
INSTALLATION OF MECHANICAL VENTILATION AT EXISTING NAL SHOP ON THE GROUND FLOOR. NO CHANGE IN USE, EGRESS, AND OCCUPANCY UNDER THIS APPLICATION.
Q01081441-I1
08/02/2024
Permit issued — Mechanical Systems
Q01081441-I1-MS
07/25/2024
Filed — Alteration
INSTALLATION OF MECHANICAL VENTILATION AT EXISTING NAL SHOP ON THE GROUND FLOOR. NO CHANGE IN USE, EGRESS, AND OCCUPANCY UNDER THIS APPLICATION.
Q01081441-I1
07/16/2024
Special inspection requirement — Mechanical Systems
SUKHWAN KIM
07/16/2024
Special inspection requirement — Final
SUKHWAN KIM
05/15/2024
Signed off — Alteration
Q00809823-I1
03/13/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
02/08/2023
Permit issued — General Construction
Q00809823-I1-GC
01/19/2023
Filed — Alteration
Q00809823-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offURBAN GC INC08/02/2024
DOB NOWGeneral ConstructionSigned-offIMPACT BUILDERS CORP02/08/2023
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
03/13/2024Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 2
DateRequirementInspectorRole
07/16/2024Mechanical SystemsSUKHWAN KIMspecial
07/16/2024FinalSUKHWAN KIMprogress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/25/2026Q00809823-I1Request digital key ↗
08/21/2026Q01081441-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/25/2026Q00809823-I1Open ↗
08/13/2026Q01081441-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/22/2026Q01081441-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/22/2026Q01081441-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/25/2026Q00809823-I1Open ↗
08/13/2026Q01081441-I1Open ↗