| Owner | Filings | Most Recent |
|---|---|---|
| HKS CONSTRUCTION | 11 | 07/08/2026 |
| BRENMAC | 6 | 07/08/2026 |
| D10 GROUP | 51 | 07/08/2026 |
| D1O GROUP INC | 2 | 03/22/2026 |
| DIO GROUP INC | 5 | 03/22/2026 |
| 2343 GROUP | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ENTHINK ENGINEERS LLC | 2 | 04/13/2021 |
| TAN ARCHITECT P.C | 1 | 01/17/2020 |
| HAIDER ENGINEERING, P.E. | 3 | 07/26/2019 |
| BRIAN E. FLYNN, PE, PC | 1 | 02/06/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| SNR EXPEDITING DESIGN | 6 | 03/21/2026 |
| HAIDER ENGINEERING, P.E. | 2 | 03/21/2026 |
| KNA CONSULTING | 2 | 03/21/2026 |
| HAIDER ENGINEERING P E | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HKS CONSTRUCTION CORP | General Contractor | 4 | 07/08/2026 |
| BRENMAC CORP | General Contractor | 2 | 07/08/2026 |
| D10 GROUP INC | General Contractor | 2 | 03/21/2026 |
| JOHN MICHAEL ELEC'L CONTG | Electrical | 1 | 03/22/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | D10 GROUP INC | 08/13/2020 |
| DOB NOW | Supported Scaffold | Signed-off | HKS CONSTRUCTION CORP | 06/26/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | HKS CONSTRUCTION CORP | 06/13/2019 |
| DOB NOW | Supported Scaffold | Signed-off | BRENMAC CORP | 04/25/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | BRENMAC CORP | 02/07/2019 |
| BIS | — | ISSUED | D10 GROUP INC | 03/09/2021 |
| BIS | — | ISSUED | D10 GROUP INC | 01/20/2021 |
| BIS | — | ISSUED | D10 GROUP INC | 06/03/2020 |
| BIS | EQ | ISSUED | D10 GROUP INC | 02/03/2020 |
| BIS | — | ISSUED | D10 GROUP INC | 02/03/2020 |
| BIS | PL | ISSUED | TOWER PLUMBING & HTG CORP | 05/14/2019 |
| BIS | — | ISSUED | D10 GROUP INC | 02/06/2019 |
| BIS | EQ | ISSUED | D10 GROUP INC | 02/06/2019 |
| BIS | PL | ISSUED | TOWER PLUMBING & HTG CORP | 04/04/2018 |
| BIS | — | ISSUED | D10 GROUP INC | 02/12/2018 |
| BIS | — | ISSUED | D10 GROUP INC | 02/12/2018 |
| BIS | EQ | ISSUED | D10 GROUP INC | 02/12/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/08/2021 | Complete | JOHN MICHAEL ELEC'L CONTG | — |
| 12/07/2020 | Complete | JOHN MICHAEL ELEC'L CONTG | General Wiring |
| 06/12/2019 | Complete | RICHARD NEU | — |
| 12/17/2018 | Complete | TUXEDO ELEC'L CONTR'G INC | — |
| 02/09/2018 | Complete | JOHN MICHAEL ELEC'L CONTG | 1 meters, 1 new_meters |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/14/2021 | Final | Sunil Saigal | progress |
| 01/30/2019 | Final | BRIAN FLYNN | progress |