| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/02/2024 | Permit Issued | HUNTER ROBERTS CONSTRUCTI | Air Conditioning Systems, Heating Systems, Ventilation Systems | Cooling Lg ARNU243SKA4 25,600 BTU · Vrf Indoor ×6 ARUM241BTE5 233,100 BTU · Vrf Outdoor ×3 ARDE-212-58-30L-15A 89,400 BTU · Vrf Outdoor ×2 ARNU183SKA4 19,100 BTU · Vrf Indoor ×2 ARNU363SVA4 24,200 BTU · Vrf Indoor ×2 ARUM121BTE5 135,000 BTU · Vrf Outdoor ×1 ARUM216BTE5 135,000 BTU · Vrf Outdoor ×1 LSN363HLV3 37,500 BTU · Fan Coil Indoor ×1 LSU363HLV3 36,000 BTU · Condensing Unit ×1 Heating Lg ARNH963K2A4 107,500 BTU · Vrf Outdoor ×2 ARNH423K2A4 107,500 BTU · Vrf Indoor ×1 ARNH963K2A4, 107,500 BTU · Vrf Indoor ×1 Ventilation Greenheck 240AW24A11DD 4,000 CFM · Exhaust Fan ×3 100SQNLEV100SQN17DLVF 150 CFM ×1 120ACRU120R17D0R80VF 420 CFM · Exhaust Fan ×1 150ACRUH2150RH17DVF2 6,725 CFM · Exhaust Fan ×1 90SQNHEV90SQN17DEC 150 CFM · Exhaust Fan ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/02/2024 | Signed-off | VANGUARD FIRE SUPP., LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/02/2024 | Signed-off | CARDOZA PLUMBING CORP | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/24/2025 | Permit Issued | HELLMAN ELECTRIC LLC | 1 meters |
| 02/12/2025 | Complete | TOP SHELF ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/02/2024 | Permit Issued | HUNTER ROBERTS CONSTRUCTI | Steel, Concrete, Masonry |
| Owner | Filings | Most Recent |
|---|---|---|
| SKYLINE SCAFFOLDING GROUP | 3 | 07/08/2026 |
| NYC DEPARTMENT OF DESIGN AND CONSTR | 13 | 03/22/2026 |
| TULLY CONSTRUCTION | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KN3 ENGINEERING LLC | 1 | 03/05/2025 |
| RIGID STRUCTURAL DESIGN, LLC | 1 | 02/18/2025 |
| PLAN B ENGINEERING | 1 | 02/05/2025 |
| TAREK M. ZEID, PE, PLLC | 1 | 09/10/2024 |
| URBAHN ARCHITECTS | 2 | 05/02/2024 |
| JOHN BARRY | 1 | 10/01/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| ARCHETYPE CONSULTANTS | 8 | 03/21/2026 |
| Rigid Structural Design, LLC | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| JMV ASSOCIATES | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HUNTER ROBERTS CONSTRUCTION | General Contractor | 8 | 03/21/2026 |
| LEON D. DEMATTEIS CONST | General Contractor | 1 | 07/08/2026 |
| SKYLINE SCAFFOLDING GROUP | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| LEO Y LEE ASSOCIATES | 2481 | 1 | 03/05/2025 |
| TECTONIC ENGINEERING CONS | 106 | 4 | 02/05/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Suspended Scaffold | Signed-off | SKYTRAC ACCESS GROUP LLC | 03/06/2025 |
| DOB NOW | General Construction | Signed-off | HUNTER ROBERTS CONSTRUCTION | 02/21/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | SKYLINE SCAFFOLDING GROUP | 02/19/2025 |
| DOB NOW | Construction Fence | Permit Issued | LEON D. DEMATTEIS CONST | 10/09/2024 |
| DOB NOW | General Construction | Permit Issued | HUNTER ROBERTS CONSTRUCTION | 01/09/2024 |
| DOB NOW | General Construction | Permit Issued | HUNTER ROBERTS CONSTRUCTION | 12/28/2022 |
| DOB NOW | General Construction | Permit Issued | HUNTER ROBERTS CONSTRUCTION | 01/12/2022 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/04/2025 | Alternative Materials - OTCR Buildings Bulletin Number | Leo Lee | special |
| 03/04/2025 | Post-installed Anchors | Leo Lee | special |
| 01/27/2025 | Structural Steel - High Strength Bolting | GEORGE GHEBRYAL | special |
| 01/27/2025 | Structural Steel - Details | GEORGE GHEBRYAL | special |
| 12/12/2024 | Final | GEORGE GHEBRYAL | progress |
| 05/02/2024 | Fire-Resistance Rated Construction | GEORGE GHEBRYAL | progress |
| 05/02/2024 | Vestibules | GEORGE GHEBRYAL | energy_progress |
| 05/02/2024 | Exterior lighting power | GEORGE GHEBRYAL | energy_progress |
| 05/02/2024 | Fenestration and door U-factor and product ratings | GEORGE GHEBRYAL | energy_progress |
| 05/02/2024 | Air barrier continuity plan testing | GEORGE GHEBRYAL | energy_progress |
| 05/02/2024 | Interior lighting power | GEORGE GHEBRYAL | energy_progress |
| 05/02/2024 | Lighting controls | GEORGE GHEBRYAL | energy_progress |
| 05/02/2024 | Fenestration areas | GEORGE GHEBRYAL | energy_progress |
| 05/02/2024 | Air barrier - visual inspection | GEORGE GHEBRYAL | energy_progress |
| 05/02/2024 | Insulation placement and R values | GEORGE GHEBRYAL | energy_progress |
| 05/02/2024 | Air barrier — testing | GEORGE GHEBRYAL | energy_progress |
| 05/02/2024 | Protection of exposed foundation insulation | GEORGE GHEBRYAL | energy_progress |
| 05/02/2024 | Fenestration air leakage | GEORGE GHEBRYAL | energy_progress |
| 05/02/2024 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 05/02/2024 | Sprayed fire-resistant materials | GEORGE GHEBRYAL | special |
| 05/02/2024 | Masonry | GEORGE GHEBRYAL | special |
| 05/02/2024 | Concrete - Cast-In-Place | GEORGE GHEBRYAL | special |
| 05/02/2024 | Wall Panels, Curtain Walls, and Veneers | GEORGE GHEBRYAL | special |
| 05/02/2024 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 05/02/2024 | Energy Code Compliance Inspections | GEORGE GHEBRYAL | progress |