| Owner | Filings | Most Recent |
|---|---|---|
| HM BUILDING AND UPLIFT CO | 2 | 03/22/2026 |
| EAAA INC | 2 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| B&Z ENGINEERING CONSULTANTS | 3 | 03/05/2026 |
| BAALBAKI & ASSOCIATES ENGINEERING P | 2 | 01/15/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| B A INSPECTIONS | 6 | 03/21/2026 |
| B Z ENGINEERING CONSULTANTS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JFR CONSTRUCTION CORP | Plumbing | 9 | 07/08/2026 |
| HM BUILD AND UPLIFT CORP | General Contractor | 5 | 07/08/2026 |
| VITO LOPA | Electrical | 1 | 03/21/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | JFR CONSTRUCTION CORP | 05/14/2026 |
| DOB NOW | Construction Fence | Permit Issued | HM BUILD UPLIFT | 09/29/2025 |
| DOB NOW | Plumbing | Signed-off | JFR CONSTRUCTION CORP | 04/25/2025 |
| DOB NOW | Plumbing | Signed-off | JFR CONSTRUCTION CORP | 10/15/2024 |
| DOB NOW | Construction Fence | Permit Issued | HM BUILD UPLIFT | 08/09/2024 |
| DOB NOW | Construction Fence | Permit Issued | HM BUILD UPLIFT | 04/05/2024 |
| DOB NOW | Construction Fence | Permit Issued | HM BUILD UPLIFT | 05/02/2023 |
| DOB NOW | Construction Fence | Permit Issued | HM BUILD UPLIFT | 11/18/2020 |
| BIS | — | ISSUED | HM BUILD AND UPLIFT CORP | 07/14/2025 |
| BIS | — | ISSUED | HM BUILD AND UPLIFT CORP | 08/22/2024 |
| BIS | — | ISSUED | HM BUILD AND UPLIFT CORP | 04/09/2024 |
| BIS | — | ISSUED | HM BUILD AND UPLIFT CORP | 04/09/2024 |
| BIS | — | ISSUED | HM BUILD AND UPLIFT CORP | 07/05/2023 |
| BIS | — | ISSUED | HM BUILD AND UPLIFT CORP | 07/05/2023 |
| BIS | — | ISSUED | HM BUILD AND UPLIFT CORP | 02/10/2022 |
| BIS | — | ISSUED | HM BUILD AND UPLIFT CORP | 02/10/2022 |
| BIS | — | ISSUED | HM BUILD AND UPLIFT CORP | 09/15/2021 |
| BIS | — | ISSUED | HM BUILD AND UPLIFT CORP | 12/23/2020 |
| BIS | — | ISSUED | HM BUILD AND UPLIFT CORP | 12/21/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/05/2026 | Signed-off | JFR CONSTRUCTION CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Permit Issued | HIGH BEAM ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/31/2019 | Permit Issued | HM BUILD AND UPLIFT CORP | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/24/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/01/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 05/20/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 10/23/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/23/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/23/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/05/2026 | Energy Code Compliance Inspections | Mohammad Baalbaki | progress |
| 03/05/2026 | Maintenance information | Mohammad Baalbaki | energy_progress |
| 02/02/2026 | Energy Code Compliance Inspections | Mohammad Baalbaki | progress |
| 02/02/2026 | Maintenance information | Mohammad Baalbaki | energy_progress |