| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/04/2026 | — | — | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-5D36NL 3 tons · Vrf Outdoor ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/04/2026 | — | — | Wood |
| Owner | Filings | Most Recent |
|---|---|---|
| 221 JAMAICA AVENUE | 5 | 09/13/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/11/2024 | $790K | — | Private party → 261 & CRAFT AVE CORP. | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| WJY ELECTRIC INC. | 1 | 05/04/2026 |
| JUST CONSULTING ENGINEERING | 2 | 04/02/2026 |
| GERALD CALIENDO ARCHITECTS | 2 | 01/08/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| GERALD J. CALIENDO R.A., P.C. | 2 | 03/21/2026 |
| GERALD J CALIENDO R A P C | 2 | 03/21/2026 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/02/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 04/02/2026 | Subgrade Inspections | — | special |
| 04/02/2026 | Concrete - Cast-In-Place | — | special |
| 03/18/2026 | Footing and Foundation | — | progress |
| 03/18/2026 | Final | — | progress |
| 02/26/2026 | Interior lighting power | — | energy_progress |
| 02/26/2026 | Electric vehicle service equipment requirements | — | energy_progress |
| 02/26/2026 | Metering | — | energy_progress |
| 02/26/2026 | Maintenance information | — | energy_progress |
| 01/08/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 01/08/2026 | Air barrier - visual inspection | — | energy_progress |
| 01/08/2026 | Fenestration air leakage | — | energy_progress |
| 01/08/2026 | Masonry | — | special |
| 01/08/2026 | Fire-Resistance Rated Construction | — | progress |
| 01/08/2026 | Air barrier — testing | — | energy_progress |
| 01/08/2026 | Insulation placement and R values | — | energy_progress |
| 01/08/2026 | Permanent certificate | — | energy_progress |
| 01/08/2026 | Fenestration areas | — | energy_progress |
| 12/28/2025 | Lowest Floor Elevation | — | progress |