| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/01/2026 | Permit Issued | WING JAY CONSTRUCTION INC | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/01/2026 | Permit Issued | WHITESTONE PLUMBING CORP | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/01/2026 | Permit Issued | WHITESTONE PLUMBING CORP | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/22/2026 | Permit Issued | NY FOREVER ELECTRIC LLC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/01/2026 | Permit Issued | WHITESTONE PLUMBING CORP | Steel, Concrete |
| 07/24/2025 | Permit Issued | WING JAY CONSTRUCTION INC | 2 scope_items |
| Owner | Filings | Most Recent |
|---|---|---|
| IDEATE 76TH STREET | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BAYSIDE ENGINEERING PC | 4 | 07/01/2026 |
| YANG ENGINEERING LLC | 5 | 08/01/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| SD DESIGN STUDIO | 10 | 03/21/2026 |
| WING JAY CONSTRUCTION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| WING JAY CONSTRUCTION INC | General Contractor | 5 | 07/08/2026 |
| WHITESTONE PLUMBING CORP | Fire Protection | 1 | 07/08/2026 |
| WHITESTONE PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SD TESTING & INSPECTION S | 7010 | 5 | 07/01/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | WHITESTONE PLUMBING CORP | 05/22/2026 |
| DOB NOW | Plumbing | Permit Issued | WHITESTONE PLUMBING CORP | 05/19/2026 |
| DOB NOW | Structural | Permit Issued | WING JAY CONSTRUCTION INC | 04/23/2026 |
| DOB NOW | Construction Fence | Permit Issued | WING JAY CONSTRUCTION INC | 03/23/2026 |
| DOB NOW | General Construction | Permit Issued | WING JAY CONSTRUCTION INC | 02/17/2026 |
| DOB NOW | Support of Excavation | Permit Issued | WING JAY CONSTRUCTION INC | 02/11/2026 |
| DOB NOW | Construction Fence | Permit Issued | WING JAY CONSTRUCTION INC | 12/10/2024 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/01/2026 | Insulation placement and R values | XIUCHENG LI | energy_progress |
| 07/01/2026 | Structural Steel - Details | XIUCHENG LI | special |
| 07/01/2026 | Final | XIUCHENG LI | progress |
| 07/01/2026 | Footing and Foundation | XIUCHENG LI | progress |
| 07/01/2026 | Fenestration areas | XIUCHENG LI | energy_progress |
| 07/01/2026 | Fenestration air leakage | XIUCHENG LI | energy_progress |
| 07/01/2026 | Permanent certificate | XIUCHENG LI | energy_progress |
| 07/01/2026 | Air barrier — testing | XIUCHENG LI | energy_progress |
| 07/01/2026 | Fenestration and door U-factor and product ratings | XIUCHENG LI | energy_progress |
| 07/01/2026 | Structural Cold-Formed Steel | XIUCHENG LI | special |
| 07/01/2026 | Air barrier - visual inspection | XIUCHENG LI | energy_progress |
| 05/01/2026 | Structural Cold-Formed Steel | XIUCHENG LI | special |
| 05/01/2026 | Air barrier — testing | XIUCHENG LI | energy_progress |
| 05/01/2026 | Footing and Foundation | XIUCHENG LI | progress |
| 05/01/2026 | Final | XIUCHENG LI | progress |
| 05/01/2026 | Structural Steel - Details | XIUCHENG LI | special |
| 05/01/2026 | Fenestration and door U-factor and product ratings | XIUCHENG LI | energy_progress |
| 05/01/2026 | Permanent certificate | XIUCHENG LI | energy_progress |
| 05/01/2026 | Insulation placement and R values | XIUCHENG LI | energy_progress |
| 05/01/2026 | Fenestration air leakage | XIUCHENG LI | energy_progress |
| 05/01/2026 | Fenestration areas | XIUCHENG LI | energy_progress |
| 05/01/2026 | Air barrier - visual inspection | XIUCHENG LI | energy_progress |
| 08/04/2025 | Energy Code Compliance Inspections | XIUCHENG LI | progress |
| 08/04/2025 | Fire-Resistant Penetrations and Joints | XIUCHENG LI | special |
| 08/04/2025 | Sprinkler Systems | XIUCHENG LI | special |