| Owner | Filings | Most Recent |
|---|---|---|
| LOGAN PROPERTY | 20 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| LEONARD J. STRANDBERG & ASSOCAITES | 2 | 03/10/2026 |
| H2M ARCHITECTS + ENGINEERS | 3 | 02/03/2026 |
| HIGH POINT ENGINEERING | 2 | 06/25/2025 |
| JMV CONSULTING ENGINEERING | 2 | 03/04/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| Casino Development Group, Inc | 2 | 03/21/2026 |
| GEORGE E BERGER ASS | 14 | 03/21/2026 |
| HIGH POINT ENGINEERING | 1 | 03/21/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| BIS | — | ISSUED | SUPER EAGLE CONTRACTING | 08/22/2013 |
| BIS | — | ISSUED | QUEDAN CONSTRUCTION SERVICES | 06/06/2011 |
| BIS | — | ISSUED | BRUNO FRUSTACI CONTRACTING INC | 05/06/2011 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 02/03/2026 | — | — | Air Conditioning Systems, Heating Systems, Ventilation Systems | Cooling Mitsubishi Electric MUY-GL18NA 18,000 BTU · Condensing Unit ×1 MUYGL18NA 18,000 BTU · Condensing Unit ×1 PUHYHP72TNU-A1 72,000 BTU · Vrf Outdoor ×1 SUZ-KA18NA2 17,700 BTU · Condensing Unit ×1 Heating Modine ×1 Ventilation Greenheck CUE-90-VG (1), CUE-070-VG (1), VUE-180-VG (5), CUE-120-VG (3) 17,200 CFM · Exhaust Fan ×10 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/03/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/10/2026 | — | — | Storm, Water/Sanitary |
| 02/03/2026 | — | — | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/10/2026 | — | — | 2 scope_items |
| 02/03/2026 | — | — | Steel, Concrete, Masonry |
| 06/25/2025 | — | — | Concrete |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/26/2026 | Air barrier — testing | — | energy_progress |
| 01/26/2026 | Protection of exposed foundation insulation | — | energy_progress |
| 10/01/2025 | Energy Code Compliance Inspections | — | progress |
| 10/01/2025 | Exterior lighting power | — | energy_progress |
| 09/18/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 09/17/2025 | Final | — | progress |
| 09/17/2025 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 09/17/2025 | Subgrade Inspections | — | special |
| 06/26/2025 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 06/26/2025 | Concrete - Cast-In-Place | — | special |
| 06/26/2025 | Final | — | progress |
| 06/18/2025 | Concrete - Cast-In-Place | — | special |
| 06/18/2025 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 06/18/2025 | Final | — | progress |
| 01/12/2025 | Masonry | — | special |
| 01/12/2025 | Concrete - Cast-In-Place | — | special |
| 01/12/2025 | Fire-Resistance Rated Construction | — | progress |
| 01/12/2025 | Energy Code Compliance Inspections | — | progress |
| 01/12/2025 | Subgrade Inspections | — | special |
| 01/12/2025 | Deep Foundation Elements | — | special |
| 01/12/2025 | Exterior lighting power | — | energy_progress |
| 01/12/2025 | Interior lighting power | — | energy_progress |
| 01/12/2025 | Lighting controls | — | energy_progress |
| 12/27/2024 | Footing and Foundation | — | progress |
| 12/27/2024 | Final | — | progress |