← Back
Two stories - detached, small or mid-size
161 WEST BUCHANAN STREET
STATEN ISLAND · BIN 5001619
💬 Discuss this project
1935Year Built
2Stories
A1Building Class
R3XZoning
1,496 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 5,900 sf lot · 0.25 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Roof3p · 1 filing · 8 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY BUILDING ASSOCIATES INC208/19/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
S R SOLAR DESIGN203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HARVEST POWER LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244208/19/2026
Building Lifecycle
All (9)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (5)
08/24/2026
Signed off — Alteration
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. NO CHANGE IN BULK
S01342042-I1
08/20/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
08/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
08/20/2026
Special inspection requirement — Final
NARESH MAHANGU
08/20/2026
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
08/20/2026
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
08/19/2026
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. NO CHANGE IN BULK
S01342042-P1
02/24/2026
Permit issued — Solar
S01342042-I1-SL
02/04/2026
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. NO CHANGE IN BULK
S01342042-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offHARVEST POWER LLC02/24/2026
1 project · most recent 01/15/2026
FiledStatusContractorScope
01/15/2026CompleteISLAND ELECTRIC CORP—
1 project · most recent 08/19/2026
FiledStatusContractorScope
08/19/2026Signed-offHARVEST POWER LLC17 panels, 7.73 kw, 644 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
08/20/2026Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
08/20/2026Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
08/20/2026FinalNARESH MAHANGUprogress
08/20/2026Energy Code Compliance InspectionsNARESH MAHANGUprogress
08/20/2026Air barrier - visual inspectionNARESH MAHANGUenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026S01342042-P1Request digital key ↗
08/17/2026S01342042-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/17/2026S01342042-P1Open ↗
08/17/2026S01342042-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026S01342042-I1Open ↗
08/23/2026S01342042-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026S01342042-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/17/2026S01342042-I1Open ↗
08/17/2026S01342042-P1Open ↗