| Owner | Filings | Most Recent |
|---|---|---|
| RICHORD COUNTY DEVEL LLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| RYAN DESIGN ARCHITECTURE | 5 | 10/22/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| GRINBERG MANAGEMENT | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RICHMOND COUNTY DEVEL LLC | General Contractor | 11 | 07/08/2026 |
| CHOICEPRO INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RYAN DESIGN ARCHITECTURE | 7159 | 3 | 10/22/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | RICHMOND COUNTY DEVEL LLC | 06/22/2026 |
| DOB NOW | General Construction | Permit Issued | RICHMOND COUNTY DEVEL LLC | 01/27/2026 |
| DOB NOW | General Construction | Permit Issued | RICHMOND COUNTY DEVEL LLC | 06/17/2025 |
| DOB NOW | General Construction | Permit Issued | RICHMOND COUNTY DEVEL LLC | 03/26/2025 |
| DOB NOW | General Construction | Permit Issued | RICHMOND COUNTY DEVEL LLC | 06/21/2024 |
| DOB NOW | Plumbing | Signed-off | CHOICEPRO INC | 06/07/2024 |
| DOB NOW | Construction Fence | Signed-off | RICHMOND COUNTY DEVEL LLC | 12/12/2023 |
| DOB NOW | General Construction | Permit Issued | RICHMOND COUNTY DEVEL LLC | 09/18/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/22/2024 | Signed-off | CHOICEPRO INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/22/2024 | Permit Issued | RICHMOND COUNTY DEVEL LLC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/06/2024 | Fire-Resistant Penetrations and Joints | Daniel Ryan | special |
| 11/06/2024 | HVAC-R and service water heating system controls | Daniel Ryan | energy_progress |
| 11/06/2024 | HVAC-R and service water heating equipment | Daniel Ryan | energy_progress |
| 11/06/2024 | Maintenance information | Daniel Ryan | energy_progress |
| 11/06/2024 | HVAC-R and service water piping design and insulation | Daniel Ryan | energy_progress |
| 10/11/2024 | Fire-Resistant Penetrations and Joints | Daniel Ryan | special |
| 10/11/2024 | HVAC-R and service water heating system controls | Daniel Ryan | energy_progress |
| 10/11/2024 | HVAC-R and service water piping design and insulation | Daniel Ryan | energy_progress |
| 10/11/2024 | HVAC-R and service water heating equipment | Daniel Ryan | energy_progress |
| 10/11/2024 | Maintenance information | Daniel Ryan | energy_progress |
| 08/23/2023 | Air barrier - visual inspection | Daniel Ryan | energy_progress |
| 08/23/2023 | Fenestration areas | Daniel Ryan | energy_progress |
| 08/23/2023 | Energy Code Compliance Inspections | Daniel Ryan | progress |
| 08/23/2023 | Fenestration and door U-factor and product ratings | Daniel Ryan | energy_progress |
| 08/23/2023 | Interior lighting power | Daniel Ryan | energy_progress |
| 08/23/2023 | Fenestration air leakage | Daniel Ryan | energy_progress |
| 08/23/2023 | Insulation placement and R values | Daniel Ryan | energy_progress |
| 06/26/2023 | Fire-Resistance Rated Construction | Daniel Ryan | progress |
| 06/26/2023 | Fire-Resistant Penetrations and Joints | Daniel Ryan | special |