| Firm | Filings | Most Recent |
|---|---|---|
| SHENKER ARCHITECT, PC | 6 | 11/18/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| Shenker Architects | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KOSTYANTYN GARKUSHA | General Contractor | 6 | 03/21/2026 |
| VSP MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SHENKER ARCHITECT, PC | 756 | 6 | 11/18/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | EMR MECHANICAL CORP | 03/01/2022 |
| DOB NOW | General Construction | Signed-off | KOSTYANTYN GARKUSHA | 02/15/2022 |
| DOB NOW | General Construction | Signed-off | KOSTYANTYN GARKUSHA | 11/17/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/01/2022 | Complete | KINGS ELECTRIC CO., INC. | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/21/2022 | Electric vehicle service equipment requirements | DMITRIY SHENKER | energy_progress |
| 11/21/2022 | Insulation placement and R values | DMITRIY SHENKER | energy_progress |
| 11/21/2022 | Lighting in dwelling units | DMITRIY SHENKER | energy_progress |
| 11/21/2022 | Fenestration air leakage | DMITRIY SHENKER | energy_progress |
| 11/21/2022 | Metering | DMITRIY SHENKER | energy_progress |
| 11/21/2022 | Fire-Resistant Penetrations and Joints | DMITRIY SHENKER | special |
| 11/21/2022 | Structural Stability – Alterations of existing buildings | DMITRIY SHENKER | special |
| 11/21/2022 | Final | DMITRIY SHENKER | progress |
| 11/21/2022 | Energy Code Compliance Inspections | DMITRIY SHENKER | progress |
| 11/21/2022 | Fenestration areas | DMITRIY SHENKER | energy_progress |
| 11/21/2022 | Permanent certificate | DMITRIY SHENKER | energy_progress |
| 11/21/2022 | Fenestration and door U-factor and product ratings | DMITRIY SHENKER | energy_progress |
| 11/17/2022 | Fire-Resistant Penetrations and Joints | DMITRIY SHENKER | special |
| 11/17/2022 | Final | DMITRIY SHENKER | progress |
| 11/17/2022 | Fenestration areas | DMITRIY SHENKER | energy_progress |
| 11/17/2022 | Insulation placement and R values | DMITRIY SHENKER | energy_progress |
| 11/17/2022 | Fenestration and door U-factor and product ratings | DMITRIY SHENKER | energy_progress |
| 11/17/2022 | Lighting in dwelling units | DMITRIY SHENKER | energy_progress |
| 11/17/2022 | Fenestration air leakage | DMITRIY SHENKER | energy_progress |
| 11/17/2022 | Fire-Resistant Penetrations and Joints | DMITRIY SHENKER | special |
| 11/17/2022 | Structural Stability – Alterations of existing buildings | DMITRIY SHENKER | special |
| 11/17/2022 | Energy Code Compliance Inspections | DMITRIY SHENKER | progress |
| 11/17/2022 | Final | DMITRIY SHENKER | progress |
| 11/17/2022 | Insulation placement and R values | DMITRIY SHENKER | energy_progress |
| 11/17/2022 | Electric vehicle service equipment requirements | DMITRIY SHENKER | energy_progress |