| Owner | Filings | Most Recent |
|---|---|---|
| OVER DEVELOPMENT | 31 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JAMES V MORRI | 4 | 09/26/2024 |
| ISLAND ENGINEERING ASSOCIATES | 2 | 08/15/2024 |
| WILLIAM MONTAGUE ENGINEER | 1 | 10/15/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| PATRICIA L. GASS | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| OVER DEVELOPEMENT LTD | General Contractor | 13 | 07/08/2026 |
| DOOR TO DOOR REALTY LLC | General Contractor | 7 | 07/08/2026 |
| FLOW-RIGHT PLBG & HTG COR | Plumbing | 4 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ISLAND ENGINEERING ASSOCI | 264 | 2 | 09/26/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | DOOR TO DOOR REALTY | 09/18/2024 |
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 07/10/2024 |
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 06/20/2024 |
| DOB NOW | Earth Work | Permit Issued | DOOR TO DOOR REALTY | 04/22/2024 |
| DOB NOW | Structural | Permit Issued | DOOR TO DOOR REALTY | 01/22/2024 |
| DOB NOW | Construction Fence | Signed-off | DOOR TO DOOR REALTY | 01/19/2024 |
| DOB NOW | Structural | Permit Issued | DOOR TO DOOR REALTY | 01/25/2023 |
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 08/05/2022 |
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 08/04/2022 |
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 04/13/2022 |
| DOB NOW | Earth Work | Permit Issued | OVER DEVELOPEMENT LTD | 03/25/2022 |
| DOB NOW | Construction Fence | Signed-off | OVER DEVELOPEMENT LTD | 02/22/2022 |
| DOB NOW | General Construction | Permit Issued | OVER DEVELOPEMENT LTD | 01/25/2022 |
| DOB NOW | Construction Fence | Signed-off | OVER DEVELOPEMENT LTD | 11/12/2020 |
| DOB NOW | Construction Fence | Signed-off | OVER DEVELOPEMENT LTD | 10/20/2020 |
| BIS | — | ISSUED | J. SMITH CONSTRUCTION INC. | 10/21/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/10/2022 | Complete | GB ELECTRICAL CORP. | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/26/2024 | Signed-off | DOOR TO DOOR REALTY LLC | Steel, Concrete, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/27/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 10/22/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 10/31/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/25/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 09/23/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/16/2024 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 09/16/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/13/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/12/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/22/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/18/2022 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 08/16/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 05/02/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/30/2024 | Subsurface Investigations (Borings/Test Pits) | WILLIAM DURDEN, P.E. | special |
| 09/30/2024 | Subgrade Inspections | WILLIAM DURDEN, P.E. | special |
| 09/30/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | WILLIAM DURDEN, P.E. | special |
| 09/30/2024 | Structural Steel - Details | WILLIAM DURDEN, P.E. | special |
| 09/30/2024 | Fire-Resistant Penetrations and Joints | WILLIAM DURDEN, P.E. | special |
| 09/30/2024 | Concrete - Cast-In-Place | WILLIAM DURDEN, P.E. | special |
| 09/30/2024 | Energy Code Compliance Inspections | WILLIAM DURDEN, P.E. | progress |
| 09/30/2024 | Structural Wood Frame | WILLIAM DURDEN, P.E. | progress |
| 09/30/2024 | Fire-Resistance Rated Construction | WILLIAM DURDEN, P.E. | progress |
| 09/30/2024 | Final | WILLIAM DURDEN, P.E. | progress |
| 09/30/2024 | Footing and Foundation | WILLIAM DURDEN, P.E. | progress |
| 09/30/2024 | Fenestration and door U-factor and product ratings | WILLIAM DURDEN, P.E. | energy_progress |
| 09/30/2024 | Electric vehicle service equipment requirements | WILLIAM DURDEN, P.E. | energy_progress |
| 09/30/2024 | Air barrier - visual inspection | WILLIAM DURDEN, P.E. | energy_progress |
| 09/30/2024 | HVAC-R and service water piping design and insulation | WILLIAM DURDEN, P.E. | energy_progress |
| 09/30/2024 | Fenestration air leakage | WILLIAM DURDEN, P.E. | energy_progress |
| 09/30/2024 | Maintenance information | WILLIAM DURDEN, P.E. | energy_progress |
| 09/30/2024 | Fenestration areas | WILLIAM DURDEN, P.E. | energy_progress |
| 09/30/2024 | Lighting in dwelling units | WILLIAM DURDEN, P.E. | energy_progress |
| 09/30/2024 | Permanent certificate | WILLIAM DURDEN, P.E. | energy_progress |
| 09/30/2024 | Insulation placement and R values | WILLIAM DURDEN, P.E. | energy_progress |
| 09/30/2024 | Lighting controls | WILLIAM DURDEN, P.E. | energy_progress |
| 09/30/2024 | Metering | WILLIAM DURDEN, P.E. | energy_progress |
| 09/30/2024 | Air barrier — testing | WILLIAM DURDEN, P.E. | energy_progress |
| 09/23/2024 | Concrete - Cast-In-Place | WILLIAM DURDEN, P.E. | special |