| Owner | Filings | Most Recent |
|---|---|---|
| METROPOLITAN DERMATOLOGY | 11 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| AVID DESIGNS, INC | 4 | 04/21/2025 |
| SCAGLIONE ARCHITECTS | 3 | 08/23/2023 |
| C&P DESIGN CONSULTANTS | 1 | 08/13/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| C P DESIGN CONSULTANTS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| COMPLEX DEVELOPMENT INC | General Contractor | 1 | 07/08/2026 |
| ALMA PLBG SPRINKLER INC | Plumbing | 1 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | SMART PLUMBING & HTG CORP | 03/18/2025 |
| DOB NOW | General Construction | Signed-off | COMPLEX DEVELOPMENT INC | 02/21/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/13/2023 | — | — | Associated Ducts and Piping, Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/22/2023 | — | — | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/08/2025 | Complete | POWER SURGE ELECTRIC, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/23/2023 | — | — | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/20/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 04/04/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/01/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/29/2025 | Energy Code Compliance Inspections | Jeffrey Geary | progress |
| 05/29/2025 | Lighting controls | Jeffrey Geary | energy_progress |
| 05/29/2025 | Interior lighting power | Jeffrey Geary | energy_progress |
| 05/13/2025 | Interior lighting power | Jeffrey Geary | energy_progress |
| 05/13/2025 | Lighting controls | Jeffrey Geary | energy_progress |
| 03/04/2025 | Energy Code Compliance Inspections | Jeffrey Geary | progress |
| 08/01/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 08/01/2023 | Heating Systems | — | special |
| 08/01/2023 | Energy Code Compliance Inspections | — | progress |
| 08/01/2023 | HVAC-R and service water heating system controls | — | energy_progress |
| 08/01/2023 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 08/01/2023 | Duct leakage testing, insulation and design | — | energy_progress |
| 08/01/2023 | Permanent certificate | — | energy_progress |
| 08/01/2023 | Shutoff dampers | — | energy_progress |
| 08/01/2023 | Maintenance information | — | energy_progress |
| 08/01/2023 | HVAC-R and service water heating equipment | — | energy_progress |
| 06/05/2023 | Final | — | progress |
| 06/05/2023 | Mechanical Systems | — | special |