| Firm | Filings | Most Recent |
|---|---|---|
| HALO ARCHITECTURE PLLC | 8 | 12/03/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| MODERN BUILDING CONSULTANT | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KARAPANJO'S CONSTR LLC | General Contractor | 3 | 07/08/2026 |
| JOHN FITZGERALD PLBG &HTG | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HALO ARCHITECTURE PLLC | 8021 | 5 | 12/03/2025 |
| FACTORY ENGINEERING WORKS | 8855 | 4 | 04/28/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | JOHN FITZGERALD PLBG &HTG | 02/12/2026 |
| DOB NOW | Plumbing | Permit Issued | JOHN FITZGERALD PLBG &HTG | 01/13/2025 |
| DOB NOW | Structural | Permit Issued | KARAPANJOS CONSTR | 10/15/2024 |
| DOB NOW | General Construction | Permit Issued | KARAPANJOS CONSTR | 10/08/2024 |
| DOB NOW | Construction Fence | Permit Issued | KARAPANJOS CONSTR | 10/08/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/03/2025 | Permit Issued | JOHN FITZGERALD PLBG &HTG | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/28/2025 | Permit Issued | CUNNINGHAM ELECTRIC CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/05/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/30/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/15/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/08/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/03/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/04/2025 | Fire-Resistant Penetrations and Joints | Hanli Liu | special |
| 12/03/2025 | Fire-Resistant Penetrations and Joints | Hanli Liu | special |
| 07/01/2025 | Insulation placement and R values | Hanli Liu | energy_progress |
| 07/01/2025 | Fenestration areas | Hanli Liu | energy_progress |
| 07/01/2025 | Air barrier - visual inspection | Hanli Liu | energy_progress |
| 07/01/2025 | Fire-Resistant Penetrations and Joints | Hanli Liu | special |
| 07/01/2025 | Structural Stability – Alterations of existing buildings | Kui He | special |
| 07/01/2025 | Energy Code Compliance Inspections | Hanli Liu | progress |
| 07/01/2025 | Fenestration air leakage | Hanli Liu | energy_progress |
| 07/01/2025 | Interior lighting power | Hanli Liu | energy_progress |
| 07/01/2025 | Fenestration and door U-factor and product ratings | Hanli Liu | energy_progress |
| 05/08/2025 | Subgrade Inspections | Kui He | special |
| 05/08/2025 | Concrete - Cast-In-Place | Kui He | special |
| 05/08/2025 | Post-installed Anchors | Kui He | special |
| 05/08/2025 | Structural Stability – Alterations of existing buildings | Kui He | special |
| 05/08/2025 | Final | Kui He | progress |
| 05/08/2025 | Structural Wood Frame | Kui He | progress |
| 04/16/2025 | Interior lighting power | Hanli Liu | energy_progress |
| 04/16/2025 | Energy Code Compliance Inspections | Hanli Liu | progress |
| 04/16/2025 | Fenestration air leakage | Hanli Liu | energy_progress |
| 04/16/2025 | Fenestration areas | Hanli Liu | energy_progress |
| 04/16/2025 | Air barrier - visual inspection | Hanli Liu | energy_progress |
| 04/16/2025 | Fenestration and door U-factor and product ratings | Hanli Liu | energy_progress |
| 04/16/2025 | Insulation placement and R values | Hanli Liu | energy_progress |
| 04/16/2025 | Fire-Resistant Penetrations and Joints | Hanli Liu | special |