← Back
One story - permanent living quarter
40 NEVADA AVENUE
STATEN ISLAND · BIN 5023660
💬 Discuss this project
1970Year Built
1Stories
A2Building Class
R1-2Zoning
2,614 sfGross Floor Area
1Units
5 Open Violations 4 unresolved · 1 paperwork only ▸FDNY Report ↗
One story - permanent living quarter · 6,800 sf lot · 0.38 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Permit Issued — active, not yet Signed-off
Floor 2Under Construction6p · 2 filings · 16 docs
Floor 1Under Construction5p · 2 filings · 16 docs
CellarUnder Construction6p · 2 filings · 16 docs
1 job · most recent 06/05/2026
Water/Sanitary
FiledStatusContractorScope
06/05/2026Permit IssuedAMC PLBG, HTG & CLNG, INCWater/Sanitary
1 job · most recent 12/02/2025
General Wiring
FiledStatusContractorScope
12/02/2025CompleteJ Y ELECTRIC INCGeneral Wiring
Building Lifecycle
All (21)Filed (5)Permit Issued (2)Violation (5)Special Inspection (9)
09/11/2026
Filed — Alteration
RESOLVE ECB VIOLATIONS: 39167880P, 39167881R AND 39167882Z; RENOVATION OF EXISTING CELLAR,1ST AND 2ND FLOOR WITH GENERAL CONSTRUCTION: NEW PARTITIONS, DOORS, FLOORING AND COSMETIC WORK; RESURFACE EXTERIOR WALL. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER
S01323421-P2
09/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FARHAD BASSIRI-TEHRANI
09/11/2026
Special inspection requirement — Energy Code Compliance Inspections
FARHAD BASSIRI-TEHRANI
09/11/2026
Special inspection requirement — Fire-Resistance Rated Construction
FARHAD BASSIRI-TEHRANI
06/12/2026
Violation issued (ECB, open)
Construction
06/12/2026
Violation issued (ECB, open)
Construction
06/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FARHAD BASSIRI-TEHRANI
06/08/2026
Special inspection requirement — Fire-Resistance Rated Construction
FARHAD BASSIRI-TEHRANI
06/08/2026
Special inspection requirement — Energy Code Compliance Inspections
FARHAD BASSIRI-TEHRANI
06/05/2026
Filed — Alteration
RESOLVE ECB VIOLATIONS: 39167880P, 39167881R AND 39167882Z; RENOVATION OF EXISTING CELLAR,1ST AND 2ND FLOOR WITH PLUMBING WORK: REPLACE KITCHEN AND BATHROOM FIXTURES; NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
S01323423-P1
06/05/2026
Filed — Alteration
RESOLVE ECB VIOLATIONS: 39167880P, 39167881R AND 39167882Z; RENOVATION OF EXISTING CELLAR,1ST AND 2ND FLOOR WITH GENERAL CONSTRUCTION: NEW PARTITIONS, DOORS, FLOORING AND COSMETIC WORK; RESURFACE EXTERIOR WALL. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER
S01323421-P1
06/04/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FARHAD BASSIRI-TEHRANI
06/04/2026
Special inspection requirement — Energy Code Compliance Inspections
FARHAD BASSIRI-TEHRANI
06/04/2026
Special inspection requirement — Fire-Resistance Rated Construction
FARHAD BASSIRI-TEHRANI
03/11/2026
Permit issued — Plumbing
S01323423-I1-PL
12/24/2025
Permit issued — General Construction
S01323421-I1-GC
11/21/2025
Filed — Alteration
RESOLVE ECB VIOLATIONS: 39167880P, 39167881R AND 39167882Z; RENOVATION OF EXISTING CELLAR,1ST AND 2ND FLOOR WITH PLUMBING WORK: REPLACE KITCHEN AND BATHROOM FIXTURES; NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
S01323423-I1
11/21/2025
Filed — Alteration
RESOLVE ECB VIOLATIONS: 39167880P, 39167881R AND 39167882Z; RENOVATION OF EXISTING CELLAR,1ST AND 2ND FLOOR WITH GENERAL CONSTRUCTION: NEW PARTITIONS, DOORS, FLOORING AND COSMETIC WORK; RESURFACE EXTERIOR WALL. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER
S01323421-I1
11/21/2025
Violation issued (ECB, open)
Construction
11/21/2025
Violation issued (ECB, open)
Unknown
11/21/2025
Violation issued (ECB, open)
Construction
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
FARHAD BASSIRI-TEHRANI509/11/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ECDESIGN STUDIO403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KALE CONSTRUCTION INCGeneral Contractor104/09/2026
AMC PLBG, HTG & CLNG, INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BASSIRI8394309/11/2026
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedAMC PLBG, HTG & CLNG, INC03/11/2026
DOB NOWGeneral ConstructionPermit IssuedKALE CONSTRUCTION INC12/24/2025
BISOTISSUEDSUSTEN CORP08/04/2016
▾Special Inspection Requirements (DOB NOW) — 9
DateRequirementInspectorRole
09/11/2026Fire-Resistant Penetrations and JointsFARHAD BASSIRI-TEHRANIspecial
09/11/2026Energy Code Compliance InspectionsFARHAD BASSIRI-TEHRANIprogress
09/11/2026Fire-Resistance Rated ConstructionFARHAD BASSIRI-TEHRANIprogress
06/08/2026Fire-Resistant Penetrations and JointsFARHAD BASSIRI-TEHRANIspecial
06/08/2026Fire-Resistance Rated ConstructionFARHAD BASSIRI-TEHRANIprogress
06/08/2026Energy Code Compliance InspectionsFARHAD BASSIRI-TEHRANIprogress
06/04/2026Fire-Resistant Penetrations and JointsFARHAD BASSIRI-TEHRANIspecial
06/04/2026Energy Code Compliance InspectionsFARHAD BASSIRI-TEHRANIprogress
06/04/2026Fire-Resistance Rated ConstructionFARHAD BASSIRI-TEHRANIprogress
▾Documents — 37 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/16/2026S01323421-I1Request digital key ↗
08/16/2026S01323421-P1Request digital key ↗
08/16/2026S01323423-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
07/14/2016540108444Open ↗
▸BISWORK PERMIT APPLICATION1
08/04/2016540108444Open ↗
▸Seals & Professional Certifications15
▸DOB NOWDPL-1: Design Professional Seal & Signature6
09/23/2026S01323421-P2Open ↗
08/16/2026S01323421-P1Open ↗
08/16/2026S01323421-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
09/23/2026S01323421-P2Open ↗
09/01/2026S01323421-P1Open ↗
08/25/2026S01323421-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
09/23/2026S01323421-P2Open ↗
09/01/2026S01323421-P1Open ↗
08/25/2026S01323421-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
07/14/2016540108444Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
07/14/2016540108444Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/14/2016540108444Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
07/14/2016540108444Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
07/14/2016540108444Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
02/23/2017540108444Open ↗
07/14/2016540108444Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
07/14/2016540108444Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
02/23/2017540108444Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
07/14/2016540108444Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
02/23/2017540108444Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY2
02/23/2017540108444Open ↗
07/14/2016540108444Open ↗
▸BISSOIL REPORT1
07/14/2016540108444Open ↗
▸Approvals, Objections & Sign-offs2
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
02/23/2017540108444Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
02/23/2017540108444Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
02/23/2017540108444Open ↗
07/14/2016540108444Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
07/14/2016540108444Open ↗