| Firm | Filings | Most Recent |
|---|---|---|
| JAMES V MORRI | 3 | 05/19/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J. SMITH CONSTRUCTION INC. | General Contractor | 2 | 07/08/2026 |
| CAVAGNARO CONTRACTING LLC | General Contractor | 1 | 07/08/2026 |
| FINE MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JAMES V MORRI, RA | 1042 | 1 | 11/14/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | FINE MECHANICAL CORP | 05/20/2026 |
| DOB NOW | Construction Fence | Permit Issued | CAVAGNARO CONTRACTING LLC | 04/27/2026 |
| DOB NOW | Construction Fence | Permit Issued | J. SMITH CONSTRUCTION INC. | 04/27/2026 |
| DOB NOW | General Construction | Permit Issued | J. SMITH CONSTRUCTION INC. | 04/24/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2026 | Signed-off | FINE MECHANICAL CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/04/2026 | Permit Issued | FLIP CITY ELECT & FIRE LL | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2026 | Signed-off | FINE MECHANICAL CORP | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/24/2026 | Permit Issued | CAVAGNARO CONTRACTING LLC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/01/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/01/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/03/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/11/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/11/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/28/2026 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/05/2025 | Maintenance information | anthony santoro | energy_progress |
| 11/05/2025 | Fire-Resistant Penetrations and Joints | James Morri | special |
| 11/05/2025 | Lighting in dwelling units | anthony santoro | energy_progress |
| 11/05/2025 | Fenestration air leakage | James Morri | energy_progress |
| 11/05/2025 | Energy Code Compliance Inspections | James Morri | progress |
| 11/05/2025 | Fire-Resistance Rated Construction | James Morri | progress |
| 11/05/2025 | Preliminary | James Morri | progress |
| 11/05/2025 | Structural Wood Frame | James Morri | progress |
| 11/05/2025 | Lighting controls | James Morri | energy_progress |
| 11/05/2025 | Fenestration and door U-factor and product ratings | James Morri | energy_progress |
| 11/05/2025 | HVAC-R and service water heating system controls | James Morri | energy_progress |
| 11/05/2025 | Fenestration areas | James Morri | energy_progress |
| 11/05/2025 | HVAC-R and service water piping design and insulation | James Morri | energy_progress |
| 11/05/2025 | Insulation placement and R values | James Morri | energy_progress |
| 11/05/2025 | Air barrier — testing | anthony santoro | energy_progress |
| 11/05/2025 | HVAC-R and service water heating equipment | James Morri | energy_progress |
| 11/05/2025 | Permanent certificate | anthony santoro | energy_progress |
| 11/05/2025 | Air barrier - visual inspection | James Morri | energy_progress |
| 11/04/2025 | Final | James Morri | progress |
| 11/04/2025 | Structural Stability – Alterations of existing buildings | James Morri | special |