1920Year Built
2.5Stories
A1Building Class
R3XZoning
1,120 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · Owner of record: NYC ADVANCED PROPERTIES LLC · 6,000 sf lot · 0.19 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbingGeneral
Floor 21p · 2 filings · 20 docs
Floor 11p · 1 filing · 20 docs
Cellar1p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MICHAEL DERUVO & ASSOC. ARCHITECTS506/25/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PATRICIA L. GASS803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
WP CONTRACTING INCGeneral Contractor407/08/2026
A&H EXPRESS PLBG&HTG CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A TECH ENGINEERING NYC, P6738306/25/2026
Building Lifecycle
All (51)Filed (5)Permit Issued (3)Signed Off (2)Inspection (5)Objection (6)Special Inspection (30)
08/05/2026
Signed off — Alteration
APPLICATION FILED HEREWITH TO ERECT CONSTRUCTION FENCE IN CONJUNCTION WITH ALTERATION TYPE 1 APPLICATION.
S00825993-I1
07/06/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
anthony santoro
07/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
07/06/2026
Special inspection requirement — Subgrade Inspections
anthony santoro
07/06/2026
Special inspection requirement — Concrete - Cast-In-Place
anthony santoro
07/06/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
anthony santoro
07/06/2026
Special inspection requirement — Fire-Resistance Rated Construction
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Final
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Energy Code Compliance Inspections
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Preliminary
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Footing and Foundation
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Permanent certificate
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Maintenance information
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Protection of exposed foundation insulation
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Insulation placement and R values
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Fenestration areas
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Electric vehicle service equipment requirements
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Metering
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Interior lighting power
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Fenestration air leakage
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Air barrier — testing
MICHAEL DERUVO
07/06/2026
Special inspection requirement — Air barrier - visual inspection
MICHAEL DERUVO
06/25/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
S00826432-P2
04/15/2026
Objection resolved — Resolved
04/15/2026
Objection resolved — Resolved
04/15/2026
Objection resolved — Resolved
03/30/2026
Objection raised — Admin
03/05/2026
Objection raised — Admin
03/05/2026
Objection raised — Admin
02/17/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
S00826432-P1
11/01/2024
Inspection — Pass-Final Fence Non-Directive 14
Pass
View inspection ↗
10/25/2024
Signed off — Alteration
APPLICATION FILED HEREWITH TO INSTALL ALL NEW PLUMBING FIXTURES THROUGHOUT IN CONJUNCTION WITH ALTERATION TYPE 1 APPLICATION.
S00826028-I1
10/24/2024
Special inspection requirement — Concrete - Cast-In-Place
anthony santoro
10/24/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
10/24/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
anthony santoro
10/24/2024
Special inspection requirement — Subgrade Inspections
anthony santoro
10/24/2024
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
anthony santoro
10/24/2024
Special inspection requirement — Energy Code Compliance Inspections
MICHAEL DERUVO
10/24/2024
Special inspection requirement — Final
MICHAEL DERUVO
10/24/2024
Special inspection requirement — Fire-Resistance Rated Construction
MICHAEL DERUVO
09/30/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/30/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/12/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/13/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
09/08/2023
Permit issued — Plumbing
S00826028-I1-PL
09/07/2023
Permit issued — Foundation
S00826432-I1-GC-CX
05/20/2023
Permit issued — Construction Fence
S00825993-I1-FN
04/11/2023
Filed — ALT-CO - New Building with Existing Elements to Remain
S00826432-I1
02/28/2023
Filed — Alteration
APPLICATION FILED HEREWITH TO ERECT CONSTRUCTION FENCE IN CONJUNCTION WITH ALTERATION TYPE 1 APPLICATION.
S00825993-I1
02/28/2023
Filed — Alteration
APPLICATION FILED HEREWITH TO INSTALL ALL NEW PLUMBING FIXTURES THROUGHOUT IN CONJUNCTION WITH ALTERATION TYPE 1 APPLICATION.
S00826028-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offA&H EXPRESS PLBG&HTG CORP09/08/2023
DOB NOWFoundationPermit IssuedWP CONTRACTING INC09/07/2023
DOB NOWConstruction FenceSigned-offWP CONTRACTING INC05/20/2023
2 projects · most recent 01/06/2024
General Wiring
FiledStatusContractorScope
01/06/2024CompleteA&E ELECTRICAL SYSTEMS COGeneral Wiring
09/29/2023CompleteA&E ELECTRICAL SYSTEMS CO1 meters, 1 new_meters
1 project · most recent 02/28/2023
Fence
FiledStatusContractorScope
02/28/2023Signed-offWP CONTRACTING INCFence
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
11/01/2024Pass-Final Fence Non-Directive 14PassView ↗
09/30/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/30/2024Pass-Final CND-Occupancy InspectionPassView ↗
01/12/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/13/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 44
DateRequirementInspectorRole
07/06/2026Structural Stability – Alterations of existing buildingsanthony santorospecial
07/06/2026Fire-Resistant Penetrations and Jointsanthony santorospecial
07/06/2026Subgrade Inspectionsanthony santorospecial
07/06/2026Concrete - Cast-In-Placeanthony santorospecial
07/06/2026Subsurface Investigations (Borings/Test Pits)anthony santorospecial
07/06/2026Fire-Resistance Rated ConstructionMICHAEL DERUVOprogress
07/06/2026FinalMICHAEL DERUVOprogress
07/06/2026Energy Code Compliance InspectionsMICHAEL DERUVOprogress
07/06/2026PreliminaryMICHAEL DERUVOprogress
07/06/2026Footing and FoundationMICHAEL DERUVOprogress
07/06/2026Permanent certificateMICHAEL DERUVOenergy_progress
07/06/2026Maintenance informationMICHAEL DERUVOenergy_progress
07/06/2026Protection of exposed foundation insulationMICHAEL DERUVOenergy_progress
07/06/2026Insulation placement and R valuesMICHAEL DERUVOenergy_progress
07/06/2026Fenestration areasMICHAEL DERUVOenergy_progress
07/06/2026Electric vehicle service equipment requirementsMICHAEL DERUVOenergy_progress
07/06/2026MeteringMICHAEL DERUVOenergy_progress
07/06/2026Interior lighting powerMICHAEL DERUVOenergy_progress
07/06/2026Fenestration air leakageMICHAEL DERUVOenergy_progress
07/06/2026Fenestration and door U-factor and product ratingsMICHAEL DERUVOenergy_progress
07/06/2026Air barrier — testing MICHAEL DERUVOenergy_progress
07/06/2026Air barrier - visual inspectionMICHAEL DERUVOenergy_progress
10/24/2024Concrete - Cast-In-Placeanthony santorospecial
10/24/2024Fire-Resistant Penetrations and Jointsanthony santorospecial
10/24/2024Structural Stability – Alterations of existing buildingsanthony santorospecial
Latest 25 of 44.
▾Documents — 69 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/23/2026S00825993-I1Request digital key ↗
08/23/2026S00826028-I1Request digital key ↗
08/17/2026S00826432-P1Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION2
03/07/2024540250262Open ↗
05/22/2023540250262Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation2
03/19/2024540250262Open ↗
12/05/2023540250262Open ↗
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram3
08/17/2026S00826432-P2Open ↗
08/13/2026S00826432-P1Open ↗
08/13/2026S00826432-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/17/2026S00826432-I1Open ↗
▸Seals & Professional Certifications19
▸DOB NOWProgress Inspector Seal & Signature8
08/23/2026S00826432-I1Open ↗
08/23/2026S00826432-I1Open ↗
08/23/2026S00826432-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/17/2026S00826432-I1Open ↗
08/17/2026S00826432-P2Open ↗
08/17/2026S00826432-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/23/2026S00826432-I1Open ↗
08/23/2026S00826432-I1Open ↗
08/23/2026S00826432-P1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
05/22/2023540250262Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
05/22/2023540250262Open ↗
▸Trade Schedules & Equipment3
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)3
08/17/2026S00826432-P2Open ↗
08/13/2026S00826432-P1Open ↗
08/13/2026S00826432-I1Open ↗
▸Safety & Tenant Protection3
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026S00826432-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/17/2026S00826432-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/17/2026S00826432-I1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/17/2026S00826432-I1Open ↗
08/17/2026S00826432-P2Open ↗
08/17/2026S00826432-P1Open ↗
Showing 3 of 4 on file for this type
▸Inspections & Test Reports5
▸DOB NOWSOIL REPORT3
08/17/2026S00826432-P2Open ↗
08/13/2026S00826432-P1Open ↗
08/13/2026S00826432-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026S00826432-I1Open ↗
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/13/2026S00826432-I1Open ↗
▸Approvals, Objections & Sign-offs2
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff2
03/19/2024540250262Open ↗
12/05/2023540250262Open ↗
▸Filing & Intake Forms3
▸BISADDITIONAL INFORMATION2
03/19/2024540250262Open ↗
12/05/2023540250262Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
05/22/2023540250262Open ↗
▸Other Documents17
▸BISBPP - SUPPORTING DOCUMENTATION4
03/19/2024540250262Open ↗
03/19/2024540250262Open ↗
12/05/2023540250262Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSite Survey: Initial3
08/17/2026S00826432-P2Open ↗
08/13/2026S00826432-I1Open ↗
08/13/2026S00826432-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/17/2026S00826432-P2Open ↗
08/13/2026S00826432-P1Open ↗
08/13/2026S00826432-I1Open ↗
▸DOB NOWProperty Ownership Certification3
08/17/2026S00826432-I1Open ↗
08/17/2026S00826432-P2Open ↗
08/17/2026S00826432-P1Open ↗
▸BISBPP - DOT Builders Pavement Unit Waiver Request Form2
03/19/2024540250262Open ↗
12/05/2023540250262Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026S00826432-I1Open ↗
▸DOB NOWFinal Survey1
08/17/2026S00826432-I1Open ↗