← Back
STATEN ISLAND
700 WILLOWBROOK ROAD
STATEN ISLAND · BIN 5035344
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JAMES A CLANCY111/11/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARC DESIGN AND CONSULTING LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FICAZZOLA CONSULTING LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JAMES A CLANCY9176111/11/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
01/28/2026
Signed off — Alteration
INSTALLATION OF PV SYSTEM ON EXISTING ROOF TOP. NO CHANGES TO THE USE EGRESS OR OCCUPANCY.
S01316544-I1
11/17/2025
Permit issued — Solar
S01316544-I1-SL
11/11/2025
Filed — Alteration
INSTALLATION OF PV SYSTEM ON EXISTING ROOF TOP. NO CHANGES TO THE USE EGRESS OR OCCUPANCY.
S01316544-I1
11/10/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
James Clancy
11/10/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
James Clancy
11/10/2025
Special inspection requirement — Energy Code Compliance Inspections
James Clancy
11/10/2025
Special inspection requirement — Final
James Clancy
11/10/2025
Special inspection requirement — Air barrier - visual inspection
James Clancy
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offFICAZZOLA CONSULTING11/17/2025
1 project · most recent 10/29/2025
FiledStatusContractorScope
10/29/2025CompleteAMBER ELECTL CONTNG INC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
11/10/2025Fire-Resistant Penetrations and JointsJames Clancyspecial
11/10/2025Structural Stability – Alterations of existing buildingsJames Clancyspecial
11/10/2025Energy Code Compliance InspectionsJames Clancyprogress
11/10/2025FinalJames Clancyprogress
11/10/2025Air barrier - visual inspectionJames Clancyenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/17/2026S01316544-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/24/2026S01316544-I1Open ↗
08/24/2026S01316544-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S01316544-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/24/2026S01316544-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S01316544-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01316544-I1Open ↗